April 30, 2008

MEMORANDUM FOR:

John F. Cordes, Director
Office of Commission Appellate Adjudication

FROM: Andrew L. Bates, Acting Secretary
SUBJECT: STAFF REQUIREMENTS - AFFIRMATION SESSION, 1:25 P.M., WEDNESDAY, JULY 23, 2008, COMMISSIONERS' CONFERENCE ROOM, ONE WHITE FLINT NORTH, ROCKVILLE, MARYLAND (OPEN TO PUBLIC ATTENDANCE)

I. SECY-08-0097 – Progress Energy Carolinas Inc. (Shearon Harris Nuclear Power Plant, Units 2 and 3) – Motion by the North Carolina Waste Awareness and Reduction Network (NC WARN) to Immediately Suspend the Hearing Notice and Request for Expedited Consideration

The Commission approved a Memorandum and Order responding to a request by the North Carolina Waste Awareness and Reduction Network to suspend the period to request a hearing in the Shearon Harris COL proceeding until after the completion of the certified design rulemaking for the AP1000, Revision 16.  The Memorandum and Order denies the motion.

(Subsequently, on July 23, 2008, the Acting Secretary signed the Memorandum and Order.)

cc: Chairman Klein
Commissioner Jaczko
Commissioner Lyons
Commissioner Svinicki
EDO
OGC
CFO
OCAA
OCA
OIG
OPA
Office Directors, Regions, ACRS, ACNW, ASLBP (via E-Mail)
PDR


Privacy Policy | Site Disclaimer
Thursday, July 24, 2008