1
          1                      UNITED STATES OF AMERICA
          2                    NUCLEAR REGULATORY COMMISSION
          3                                 ***
          4             MEETING WITH NORTHEAST NUCLEAR ON MILLSTONE
          5                                 ***
          6                           PUBLIC MEETING
          7                                 ***
          8
          9                             Nuclear Regulatory Commission
         10                             Commission Hearing Room
         11                             11555 Rockville Pike
         12                             Rockville, Maryland
         13
         14                             Friday, December 12, 1997
         15
         16              The Commission met in open session, pursuant to
         17    notice, at 9:00 a.m., the Honorable SHIRLEY A. JACKSON,
         18    Chairman of the Commission, presiding.
         19
         20    COMMISSIONERS PRESENT:
         21              SHIRLEY A. JACKSON, Chairman of the Commission
         22              GRETA J. DICUS, Member of the Commission
         23              EDWARD McGAFFIGAN, JR., Member of the Commission
         24              NILS J. DIAZ, Member of the Commission
         25
            
                                                           2
          1    STAFF AND PRESENTERS SEATED AT COMMISSION TABLE:
          2              JOHN C. HOYLE, Secretary
          3              KAREN D. CYR, General Counsel
          4              MIKE MORRIS, Chairman, President and CEO,
          5                Northeast Utilities
          6              BRUCE KENYON, President and CEO Northeast Nuclear
          7                Energy Company
          8              DAVE GOEBEL, Vice President Nuclear Oversight
          9              MIKE BROTHERS, Vice President Nuclear Operations
         10              JACK McELWAIN, Vice President - Unit 1
         11              MARTIN BOWLING, Vice President - Unit 2
         12              BRIAN ERLER, Senior Vice President, ICAVP Project
         13                Director, Sargent & Lundy
         14              DON SCHOPFER, Vice President and Verification
         15                Manager, Sargent & Lundy
         16              DAN CURRY, Vice President Nuclear Services,
         17                Parsons Power
         18              JOHN HILBISH, Manager of Regulatory Compliance
         19                Activities on the ICAVP Project, Parsons Power
         20              JOHN BECK, President, Little Harbor Consultants
         21              JOHN GRIFFIN, Deputy Team Leader, Little Harbor
         22                Consultants
         23              BILLIE GARD, Principle, Little Harbor Consultants
         24              HUGH THOMPSON, Deputy, EDO
         25
            
                                                           3
          1    STAFF AND PRESENTERS SEATED AT COMMISSION TABLE: 
          2    [continued]
          3              WAYNE LANNING, Deputy Director for Inspections,
          4                SPO, NRR
          5              WILLIAM TRAVERS, Director, Special Projects
          6                Office, NRR
          7              PHILLIP McKEE, Deputy Director for Licensing and
          8                Oversight, SPO, NRR
          9              EUGENE IMBRO, Deputy Director for ICAVP, SPO, NRR
         10
         11
         12
         13
         14
         15
         16
         17
         18
         19
         20
         21
         22
         23
         24
         25
            
                                                           4
          1                        P R O C E E D I N G S
          2                                                     [9:00 a.m.]
          3              CHAIRMAN JACKSON:  Good morning, ladies and
          4    gentlemen.  The purpose of this meeting is for the
          5    Commission to be briefed on the status of activities related
          6    to the three Millstone nuclear reactors.
          7              The Commission will hear presentations today from
          8    Northeast Utilities, the contractors associated with both
          9    the Independent Corrective Action Verification Program and
         10    the Employees Concerns Program, and the NRC staff.
         11              Millstone Unit 1 has been shut down for 25 months
         12    and Units 2 and 3 have been shut down for approximately 21
         13    months.  All three of the Millstone units were placed on the
         14    NRC's watch list in January of 1996.  The units were
         15    recategorized as Category 3 plants in June 1996.  This
         16    action necessitates Commission approval for restart of each
         17    of the units.
         18              This Commission meeting is the fourth quarterly
         19    meeting to assess the status of activities at the sites. 
         20    The Commission is interested in how the licensee is
         21    measuring and trackings its progress, and how well the site
         22    is function as a whole.  For example, are they finding their
         23    own problems and enacting comprehensive fixes in a timely
         24    manner?
         25              Once again, the Commission looks forward to the
            
                                                           5
          1    updates from the contractors tasked with providing an
          2    independent assessment of the corrective action programs at
          3    the station, as well as the third party associated with the
          4    independent oversight of employee concerns.
          5              The Commission is very interested in hearing the
          6    NRC staff's views regarding the effectiveness of the
          7    licensee's program, including an assessment of what areas
          8    appear satisfactory, what areas are tracking to acceptable,
          9    and what areas are unsatisfactory at this time.  The
         10    Commission desires this type of feedback, satisfactory,
         11    tracking to acceptable, or unsatisfactory, from all of the
         12    participants today.  So if you could phrase whatever you
         13    have to say in that context.
         14              The Commission benefits from a candid discussion
         15    of both the results and your conclusions.  For example, for
         16    the ICAVP contractors, and NRC staff, I expect not only to
         17    hear about the number of issues identified and resolved, but
         18    what the discrepancies are telling you.  For the licensee,
         19    if you believe the contractors or NRC staff are unwisely
         20    spending resources sampling an area that is clearly
         21    acceptable, this is one forum where you should comment to
         22    that effect.
         23              Finally, as I stated at the last Commission
         24    meeting, the Commission is interested in your comments on
         25    this process, in the midst of its implementation, so that
            
                                                           6
          1    fine tuning can be accomplished, as appropriate.  All
          2    parties should keep this in mind during today's discussions
          3    and questions.  All parties should feel not only invited to
          4    but compelled to comment on questions asked of any group. 
          5    So if your turn at the table has passed, please use the
          6    podium as necessary.
          7              I understand that copies of the presentations are
          8    available at the entrances to the meeting.  And so unless my
          9    colleagues have any opening comments they wish to make, Mr.
         10    Morris, please proceed.
         11              MR. MORRIS:  Thank you, Dr. Jackson.  Good
         12    morning, and good morning to fellow Commissioners.
         13              Before I begin the few slides that I have in the
         14    formal presentation, I would to make just a few comments
         15    about this week's announced enforcement action.  And let me
         16    try to make clear to you that we fully accept the
         17    responsibility for the situation that led to that
         18    conclusion.  We understand that the things that were found
         19    in that investigation were of great concern to you and to
         20    us.  We, obviously, accept the judgment that you made and we
         21    will go forward and pay that.
         22              We believe that we are making some progress,
         23    however, on improving our status and our standing, and our
         24    own standards, and today we hope to make that presentation
         25    to you.  We will try to follow your lead with the
            
                                                           7
          1    phraseology that you have suggested.  You will see that we
          2    have chosen the words complete, not complete, those kinds of
          3    things, that really tracking with your satisfactory,
          4    tracking toward satisfactory, and unsatisfactory.  And I
          5    think that you will see there are things are yet to do,
          6    obviously, and there are some things where we believe there
          7    is accomplishment that can allow us to focus on those other
          8    issues that need that kind of focus.
          9              So, I hope with that, that we can make a
         10    presentation that will be helpful to you, and to us, to
         11    establish that progress has, in fact, been made.
         12              With that, I will move to my first slide.  And on
         13    this slide, I am trying to make some very simple points to
         14    the Commission.  I think they are points that are fully
         15    understood by you and your colleagues.  But it is clear to
         16    me, having been on this team now for four months, that there
         17    is a full commitment of this Board of Trustees to inject
         18    themselves into this process to ensure that the management
         19    team not only has their support and their guidance, their
         20    direction and their encouragement.  And I can tell you, in
         21    the audience today, we have our lead Trustee, we have the
         22    Chair of our Nuclear Committee, and we have the Chair of our
         23    Corporate Responsibility and Affairs Committee.  I think
         24    that is a testimony to the commitment that our Board of
         25    Trustees has to this very serious matter in front of us.
            
                                                           8
          1              The second bullet is simply to indicate to you
          2    that I, as the Chief Executive Officer of this company, am
          3    equally dedicated to this assignment and have spent some
          4    time at Millstone, will continue to do that.  I have full
          5    faith and confidence in Bruce and his team, but I do believe
          6    that it is important that the CEO of this organization take
          7    hands-on responsibility and involvement in this process if
          8    we hope to bring it to a reasonable conclusion for all of us
          9    as we move forward.
         10              And, lastly, I would simply like to point out
         11    that, although things aren't as rosy as we wish that they
         12    would be, the financial resources are available to continue
         13    on this recovery process, they are committed to that end,
         14    and we will ensure that that continues to happen.
         15              We, some time ago, decided that we were not going
         16    to concern ourselves overly with heading towards some
         17    absolute deadline schedule, but, more importantly, moving
         18    this process forward so that it is completed in a safe and
         19    appropriate way.  And that is the path that we are on, and
         20    you will hear some of those comments in our presentations
         21    today.
         22              Even though we talk in terms of a hoped-for
         23    meeting with you in the not too distant future, in the early
         24    part of 1998, and we are working toward that end, please
         25    don't overtake from my team our inability or our lack of
            
                                                           9
          1    understanding that that date may float.  We continue to work
          2    toward that end because it is an achievable goal, and an
          3    important goal, and we are going to continue to do that. 
          4    But I don't want any of you to walk away believing that
          5    these folks really are working off of an unachieveable
          6    schedule, because what we are trying to do is get this
          7    process concluded.  And it is more important to us to get it
          8    concluded in an appropriate method, clearly on the fastest
          9    time line that we can, but, more important, in that
         10    appropriate method, and that is what we are dedicating
         11    ourselves to.
         12              The next slide simply points out to you who our
         13    presenters are, and most of these people are very familiar
         14    to you, of course.  Bruce Kenyon, President and CEO of our
         15    Nuclear Activity.  Mike Brothers.  Mike Brothers will talk
         16    about the activities in our safety conscious work
         17    environment, a very important step for us as we move forward
         18    to create a more healthy environment at the Millstone
         19    stations.  Marty Bowling will discuss with you a number of
         20    issues on the programs that he will be going through.  Jack
         21    McElwain, of course, will talk about the readiness of Unit
         22    3.  And Dave Goebel, our Vice President of Nuclear
         23    Oversight, will give you an update on his activities as
         24    well.
         25              So, again, let me close by simply saying I hope
            
                                                          10
          1    that you see some progress today from our last meeting.  It
          2    surely is there in the statistics.  I hope that you see a
          3    substantial increase in power dedication to realizing the
          4    issue of the safety conscious work environment and progress
          5    that has been to date in that end as well.  And I hope that,
          6    hopefully, the next time we do meet with you, we will be
          7    able to present to you the facts and figures that would
          8    allow you to recast your trust with us so that we can bring
          9    these units back on-line in the working environment that
         10    really is reflective of the safety conscious work
         11    environment that we are pursuing.
         12              So, with that, let me turn things over to Mr.
         13    Kenyon.
         14              CHAIRMAN JACKSON:  Before Mr. Kenyon begins, let
         15    me raise a sensitive question.  You mentioned that financial
         16    resources are available and committed, and I noted a press
         17    clipping last week that you had deferred raises for all your
         18    salaried employees pending unit restart and, of course, that
         19    is your decision to make, but the important point was
         20    presumably it was done in a way that still encouraged people
         21    to raise safety issues to management.
         22              MR. MORRIS:  I believe that that's the case.  We
         23    gave that a great deal of consideration before we did that,
         24    but for us to stay on the track that we're on, that was a
         25    necessary step.  And I would tell you that not only the
            
                                                          11
          1    nuclear but the non-nuclear team at NU understands that and
          2    is supportive of that, and although that's never the best of
          3    news, it is something that the team is willing to understand
          4    and willing to dedicate themselves to.
          5              CHAIRMAN JACKSON:  Thank you.
          6              MR. MORRIS:  Thank you.
          7              MR. KENYON:  Good morning, Chairman Jackson and
          8    Commissioners.
          9              I am pleased to have this opportunity to update
         10    you regarding our progress in recovering the Millstone
         11    units.  I'd just add one comment to the question you asked. 
         12    Virtually every major meeting we have on site, we remind our
         13    employees, or if it's a supervisory meeting, of the
         14    importance of raising concerns; that the last thing we want
         15    is to have an unrecognized problem show up later.  So we
         16    continue to emphasize that.
         17              This slide indicates our agenda, and there are
         18    several purposes to our presentation.  First is to
         19    demonstrate that we have made substantial progress in
         20    bringing the various issues affecting the performance of the
         21    Millstone units to closure.  It is also to convey our belief
         22    that physical readiness for Unit 3 will be achieved around
         23    the end of this year, and that clearly is a major milestone. 
         24    We want to clearly demonstrate to you that we understand the
         25    remaining work to be accomplished, and thus we believe we
            
                                                          12
          1    are on track for hopefully a March meeting to consider the
          2    restart of Unit 3.  It is our expectation that Unit 2 can
          3    follow Unit 3 by two to three months, and certainly we are
          4    acknowledging that the schedule for Unit 1 is under
          5    evaluation, and this is pending having the financial
          6    resources to resume full restart efforts.
          7              Substantially all of the material that we will be
          8    covering was included in the briefing book sent to you in
          9    advance of the meeting.  We plan to focus on Unit 3 and site
         10    issues relating to Unit 3, but certainly we are prepared to
         11    address questions on other units, should you desire.
         12              This slide and the next summarize the progress we
         13    are making in addressing the seven success objectives and
         14    the associated 16 key sitewide issues which are an essential
         15    part of our recovery.  I am pleased to report that of the 16
         16    issues, six now meet our success criteria for start-up
         17    readiness.  I translate that into satisfactory on the
         18    terminology that you are using.  We expect seven additional
         19    issues to reach satisfactory in January, and the remaining
         20    three to reach satisfactory in February.
         21              All issues -- and this is looking at the totality
         22    of an issue -- all issues, in my judgment, are tracking to
         23    satisfactory, and that's different from our last quarterly
         24    briefing when I told you I thought there were six issues
         25    that were not tracking to satisfactory at that point in
            
                                                          13
          1    time.
          2              Now within an issue, there can be particular
          3    elements that we are not yet satisfied with.  We are
          4    satisfied that the overall progress is coming together.
          5              CHAIRMAN JACKSON:  Let me ask you a question along
          6    that line.  I note, for instance, that under the strong
          7    nuclear safety philosophy, in particular procedure quality
          8    and adherence, you say yes, it's a closed issue.  Now I
          9    noted in an inspection report, 97-202, that was dated
         10    shortly after the last Commission meeting, there was an
         11    issue involving several failures to follow your own
         12    procedures for overcoating in the Unit 3 service water
         13    piping, and then there was a report that documented some
         14    --several examples of radiation worker violations, and it
         15    noted that this was of concern because it was a repetitive
         16    violation.  And then there were, in the Staff's recent
         17    Commission -- paper to the Commission, that highlighted
         18    enforcement actions associated with a November inspection
         19    report.  It talked about procedural inadequacies, emergency
         20    preparedness issues, training and failure to wear proper
         21    dosimetry.  So the question becomes how do you square, you
         22    know, these findings in these various reports with the
         23    assessment on the success objective that you mentioned?
         24              And I'm going to do this, you know, as you go
         25    through, because the issue is what does the record show
            
                                                          14
          1    versus what you are telling us and, you know, what are you
          2    saying in terms of saying that it's a closed issue.
          3              MR. KENYON:  That's fine.  Let me start by saying
          4    that in saying that an issue is judged to be satisfactory,
          5    it's our judgment, based on an ongoing evaluation of where
          6    we are -- and certainly inspection reports that come along
          7    that identify a problem in a procedure compliance area, not
          8    all of which you indicated in our judgment necessarily
          9    related to procedure compliance as opposed to a training
         10    problem, which is one of our other issues, or as opposed to
         11    emergency planning, which is one of our other issues.  So we
         12    try and separate where the problems lie.
         13              But we reached a judgment that we thought we were
         14    at an acceptable level.  That does not indicate that we
         15    think there are absolutely no problems to deal with; it just
         16    means that in our judgment, we think we have reached a
         17    satisfactory state.
         18              Now what goes on from there is we continue to take
         19    in -- and this applies to any issue.  What goes on from
         20    there is that we continue to take in information as to
         21    what's happening.
         22              One very important source of information is
         23    ongoing management self-assessments.  So we use those
         24    management self-assessments, and obviously we could, if we
         25    got enough information of an adverse nature, we would change
            
                                                          15
          1    our judgment on a particular issue.
          2              Weekly oversight comes out with a very detailed
          3    report on this issue and all the other issues, and with a
          4    numerical score, and if that score drops below a certain
          5    level for a period of time, oversight would revise its
          6    judgment on where management is on a particular issue.
          7              When you look at oversight scores, they bounce
          8    around because everything is going on is on, you know, a
          9    weekly basis, looking at attributes of what was going on in
         10    that particular week.  So whereas we concluded procedure
         11    compliance was satisfactory, that's not uniformly
         12    satisfactory across the station.  We are looking at those
         13    areas where we think it's weaker than others, and we will
         14    continue to assess it.  But at the time we prepared this,
         15    and I think still today, unless Dave, you --
         16              MR. GOEBEL:  No.
         17              MR. KENYON:  We think it's satisfactory.  And
         18    satisfactory is not, you know, perfect.
         19              CHAIRMAN JACKSON:  So this is a window-in-time
         20    snapshot as opposed to being closed, per se?
         21              MR. KENYON:  Yes.  And I had previously included
         22    in my remarks, and then I took it out in the interest of
         23    time, the distinction between an issue reaching what we
         24    judge to be a satisfactory state and an issue being closed. 
         25    We are not proposing to close any issues.  What we are about
            
                                                          16
          1    is a long term process to go from a situation where the
          2    processes and standards at the Millstone station were just
          3    nowhere near what they should be, bring them to a point that
          4    supports start-up.  But we will want, at the next Commission
          5    meeting, to present to you a longer term plan that clearly
          6    recognizes that what we are about is on a long term effort
          7    to bring the plant not just to a satisfactory state for
          8    start-up, but to excellence.  So issues are not closed for
          9    us.  Issues are things that we are going to work on through
         10    start-up and beyond.
         11              CHAIRMAN JACKSON:  Okay.  Well, I'm just
         12    referencing your own terminology here.  And I would just
         13    like to say I would like all the parties, as appropriate, to
         14    comment on this and the next slide in terms of your
         15    assessment in these areas, and particularly the NRC Staff.
         16              MR. KENYON:  I'm ready to move to the leadership
         17    assessment slide, unless there are any further questions on
         18    this one.
         19              CHAIRMAN JACKSON:  Well, let me talk again for a
         20    minute about safety-conscious work environments, and you
         21    indicate, again using the terminology that you have here,
         22    you expect this progress -- or you want it -- you expect it
         23    to be closed in February.  Now what does that mean?  Does
         24    that mean that you will have demonstrated a safety-conscious
         25    work environment, or you will have achieved a
            
                                                          17
          1    safety-conscious work environment?  And there's a
          2    difference.
          3              MR. KENYON:  Well, we -- I hope I am not missing
          4    the distinction.  We have four objectives that we feel we
          5    must meet in order to satisfy having demonstrated a
          6    safety-conscious work environment, and I think that means we
          7    have it.
          8              One is that employees are quite comfortable in
          9    raising concerns.  I think we have demonstrated that.
         10              A second is that line management is effective in
         11    resolving concerns.  We are on track there to achieve a
         12    satisfactory level of performance.  That's very dependent on
         13    a corrective action program, and we are on track in
         14    corrective actions but not there yet.
         15              The third area is an effective employee concerns
         16    program.  I think we are very close, and thus we will be
         17    able to demonstrate that in February.
         18              And, finally, we need to demonstrate that we can
         19    identify problems early enough in emerging problems,
         20    safety-conscious work environment problems, trouble areas, a
         21    building level, fully concerned, in a particular part of the
         22    organization.  We need to be able to identify that early in
         23    the process, and we need to be able to solve that.  We have
         24    not demonstrated that at this point.  We have a lot of work
         25    in progress, and Mike Brothers will talk about that in his
            
                                                          18
          1    presentation.
          2              So against those four criteria, that's an overview
          3    of where we are, and I do believe we are tracking to
          4    satisfactory.
          5              MR. MORRIS:  But, you know, I am not certain, Dr.
          6    Jackson, that this issue really ever closes.  This is an
          7    issue that needs constant vigilance and constant dedication
          8    on behalf of the management team and on behalf of the entire
          9    team at the station to continue to work to improve this
         10    area.  And that is something that you'll see when Mike
         11    Brothers makes his presentation.  Now we do not believe this
         12    is an "oh, great, this is done now."  We fully understand
         13    that this is an issue that we will be working at forever. 
         14    And I think it is true of all stations.  So we want to join
         15    the rest of them in having that dedication toward that end.
         16              CHAIRMAN JACKSON:  Okay.  Mr. Kenyon.
         17              MR. KENYON:  Recognizing that the fundamental
         18    cause of the performance problems at Millstone was
         19    leadership failures, I am pleased to report that the
         20    recently completed leadership assessment by employees and
         21    contractors of their supervision shows scores in all
         22    categories of at least 5.0, and based on my experience with
         23    a similar survey at South Carolina Electric & Gas, this
         24    indicates an organization with an overall healthy leadership
         25    climate.  It also shows continued improvement over the
            
                                                          19
          1    survey conducted this summer, and it shows an overall nearly
          2    20 percent improvement over the first survey conducted in
          3    the winter of 1996.
          4              CHAIRMAN JACKSON:  Do you have another such
          5    assessment, leader assessment, scheduled or planned?
          6              MR. KENYON:  We do.  We have been doing these on
          7    six month intervals.  If this survey had not been as strong
          8    as it was, I would schedule another prior to the March
          9    meeting.  Based on the strength of this survey, I am
         10    currently not intending to do one until the June time frame. 
         11    We are on six month intervals.  These are important surveys
         12    to us.
         13              What you are seeing is aggregate data.  Obviously,
         14    what we do is look particularly at those individuals who
         15    score very well, and those are the -- that is a good
         16    indication that these are the future leaders of the
         17    organization, and we also look particularly at those
         18    individuals who do not score well, and that suggests there
         19    is a problem between that individual and his employees.
         20              And we use this and other input to identify
         21    problem areas.  Once we identify a problem area, there is an
         22    action plan.  In some cases it means removing the
         23    individual.  In some cases, through training and coaching,
         24    the climate in that particular area is improved.
         25              So, based on the strength of these scores, I am
            
                                                          20
          1    comfortable with a six month interval.
          2              CHAIRMAN JACKSON:  As you indicated, this is
          3    aggregated data, and at the last Commission meeting, we
          4    discussed pockets.
          5              MR. KENYON:  Yes.
          6              CHAIRMAN JACKSON:  Where the performance was
          7    marginal.  Can you speak to some of those pockets and to say
          8    what the progress has been?
          9              MR. KENYON:  Yes, I can, but the person who is
         10    closest to is Mike Brothers.
         11              MR. BROTHERS:  Right.  We, when I talk about
         12    problem areas, Chairman Jackson, we will identify that. 
         13    When we first identified problem areas, we had 33, what we
         14    call problem areas.  Out of the 33, 17 were a direct result
         15    of leadership surveys.  Now, out of those 17, approximately
         16    half of those people are no longer in that position.  The
         17    other half are under different types of programs, action
         18    plans, remediation plans, to bring their leadership scores
         19    up to where they need to be.  We have taken significant
         20    action on those 17 areas.
         21              CHAIRMAN JACKSON:  Okay.  Thank you.
         22              MR. KENYON:  And while it is important for line
         23    management to demonstrate its ability to address issues, it
         24    is equally important for Millstone to have a highly
         25    credible, independent assessment capability in its oversight
            
                                                          21
          1    organization.  I am pleased to report that Millstone's
          2    Nuclear Safety Assessment Board concluded, through a very
          3    thorough five month process, and this process included an
          4    external assessment, that oversight was effective in the
          5    performance of its responsibilities.
          6              CHAIRMAN JACKSON:  Isn't it true that, in terms of
          7    that outside consulting firm that you engaged in July, that
          8    they felt that considerable progress had been made, but that
          9    significant additional improvement was required, both from
         10    nuclear oversight, as well as from Millstone Station senior
         11    management, before the oversight function was fully
         12    effective?
         13              MR. KENYON:  That is true, and the particular
         14    issue that was of biggest concern to me was the extent to
         15    which the line organization, and I am talking down in the
         16    organization, I am not talking about the senior folks, the
         17    officers, down in the organization recognize that the proper
         18    way to view oversight was in a partnership, not simply a
         19    regulatory requirement.  And, thus, oversight, an effective
         20    oversight organization is involved in helping to set the
         21    standards, and then it is obviously involved in advising
         22    line management where standards are properly met and where
         23    they are not.
         24              I think we have made very good progress in driving
         25    that understanding down in the organization, and part of
            
                                                          22
          1    what the Nuclear Safety Assessment Board did was take -- to
          2    take the input from the external assessment and then, over a
          3    five month process, look at how this was playing out.  And I
          4    am quite comfortable that oversight is now effective and
          5    line management use oversight in the proper way.
          6              CHAIRMAN JACKSON:  Could you speak to some of the
          7    areas where, according to the consultant firm, the feeling
          8    was that the greatest improvement still remained to be
          9    demonstrated?
         10              MR. KENYON:  Yes.  My only -- my only question on
         11    that, are you talking about the initial assessment, or are
         12    you talking -- because we have had that consulting firm come
         13    back in.
         14              CHAIRMAN JACKSON:  Since July.
         15              MR. KENYON:  Yes.  And we have had further input
         16    from then as to where the most attention is needed and --
         17              CHAIRMAN JACKSON:  Well, you should tell us what
         18    is -- whatever is the latest situation.
         19              MR. KENYON:  Okay.  The latest information is that
         20    they felt oversight has made strong progress and, thus, had
         21    minor comments in the area of oversight.  They had more
         22    significant concerns in the area of conduct of operations. 
         23    That is an area that we are not satisfied with yet, and that
         24    is an area that we are working on.  And, here, the situation
         25    is we have put in place, and I am principally talking Unit
            
                                                          23
          1    3, we have put in place a strong standard for conduct of
          2    operations, and this particular consultant feels it is an
          3    excellent standard.
          4              What he observed, and what we don't disagree with,
          5    is there is not uniform implementation of that standard
          6    within the operating groups.  So that was one area of
          7    concern.
          8              There was also an area of concern regarding
          9    standards for corrective action.  And, here, the issue was
         10    more dealing to whether or not there are uniform standards
         11    across the station for how you evaluate a potential issue,
         12    how do you close a potential issue, and, you know, standards
         13    in those areas.  And based on recent work, we feel the
         14    standards have been brought to a much more uniform level. 
         15    But at the time that the consultant saw it, there was still
         16    some raggedness, different -- differing approaches among the
         17    three units.  These were the two concerns that were most
         18    meaningful to me.
         19              Dave, do you want to add on the recent report, or
         20    go back to the earlier report?
         21              MR. GOEBEL:  Well, the earlier report was very
         22    critical of us for not being fully integrated at the site
         23    and not having a strategic focus that supported the overall
         24    site mission.  We were out doing our thing, and with some
         25    degree of success, but it wasn't in a focused manner.  We
            
                                                          24
          1    have restructured to create that focus, and set up a plan,
          2    which I will brief you on a little later, when it's my turn,
          3    that lays out the ability to fully integrate our own staff
          4    and in so doing provide a more meaningful feedback to the
          5    line in their endeavors.
          6              They also felt previously that -- well, I guess
          7    those were the two things, lack of strategic focus by
          8    nuclear oversight and lack of integration among oversight
          9    itself, and both those areas in the follow-up report, they
         10    said they were very satisfied with.
         11              The areas which they -- I've got the report right
         12    here.  The areas which they said they were not satisfied
         13    with are -- two of the ones are -- two main ones are the
         14    ones Mr. Kenyon has already talked about, elements of the
         15    corrective action program and elements of the conduct of
         16    operations.
         17              The other things which they said in particular
         18    they felt nuclear oversight had to concentrate more heavily
         19    on was we had to work harder to improve our plant knowledge. 
         20    So what the individual did, would take my people out in the
         21    plant and see how much they knew about the actual systems,
         22    and he walked away feeling that among some of my team, they
         23    weren't sufficiently knowledgeable in the systems
         24    themselves.  So across the board, they didn't know the plant
         25    well enough.  And that's a true fact.  I've got, out of my
            
                                                          25
          1    entire team, I only have, I think, seven people that have
          2    licenses or something, at one time had been licensed.
          3              So plant knowledge is one area they said we needed
          4    to put more emphasis.  They said we needed to spend more
          5    time in the field; felt that we should really -- it wasn't a
          6    deficiency decided from the past, but basically we needed to
          7    put more emphasis on frank performance appraisals.  We were
          8    not being critical enough to our own employees on how well
          9    they were doing and how well they were not doing, and the
         10    other area was they felt we needed to improve our
         11    communications between my organization and the NRC.  They
         12    felt our communications were not very good.
         13              CHAIRMAN JACKSON:  I'd like for the NRC Staff,
         14    actually, to speak to these issues when you come to the
         15    table.
         16              MR. GOEBEL:  So those are the items that were
         17    pointed out.
         18              CHAIRMAN JACKSON:  Thank you.
         19              Commissioner?
         20              COMMISSIONER DIAZ:  Yes, I just have a question. 
         21    I'm sure that as all of these processes are evolving, they
         22    are always containing a clear separation between oversight
         23    and conduct of operations, that your oversight committee is
         24    not a management function and does not get directly involved
         25    in the conduct of operations, which at times appeared to
            
                                                          26
          1    have been a problem, but actually performs its oversight
          2    functions in an independent manner.  Is that --
          3              MR. GOEBEL:  And that is what we are doing.  We
          4    have -- I have people in my organization who do go, spend
          5    days at a time in the control room, and just sit in the back
          6    and monitor and see who does what and how they do it, and
          7    then we provide that feedback.  We have set up systems to go
          8    back and specifically monitor the conduct of operations. 
          9    And we have brought people in from the outside to assist us
         10    in that, qualified operators from other sites.
         11              MR. KENYON:  But a clear separation --
         12              CHAIRMAN JACKSON:  I think the Commissioner's
         13    point is that the managers -- the management manages the
         14    station?
         15              MR. GOEBEL:  Right.
         16              CHAIRMAN JACKSON:  And at the same time, in order
         17    for oversight to be effective, it has to be independent.
         18              MR. KENYON:  Right.
         19              MR. GOEBEL:  Absolutely.
         20              MR. KENYON:  To wrap up my opening remarks, I
         21    wanted to indicate what I consider to be the most important
         22    remaining challenges, and this is beyond the immediacy of
         23    reaching physical readiness on Unit 3.  One is demonstrating
         24    -- and I have already said this in response to one of your
         25    questions -- demonstrating both that we can identify
            
                                                          27
          1    safety-conscious environment matters before they become
          2    major issues, and that we can effectively resolve them in a
          3    timely manner.  You are going to hear much more about this
          4    in Mike Brothers' presentation.
          5              Another challenge is to demonstrate that the
          6    corrective actions we are implementing are effective, and
          7    Marty Bowling's presentation will discuss our corrective
          8    action efforts in much more detail.
          9              We also must demonstrate the effectiveness of our
         10    configuration management program, and certainly a key item
         11    in this regard is responding to the out-of-scope SSFI
         12    inspection results, and Marty will further address that in
         13    his presentation.
         14              To summarize, I believe that satisfactory progress
         15    is being made on all key issues, which means the issues are
         16    either satisfactory for start-up, or tracking to
         17    satisfactory, recognizing, again, that there are certain
         18    elements inside those issues that still need a lot of
         19    attention.  But on an overall basis, we feel all issues are
         20    on track, or there.
         21              So I would now like to call on Mike Brothers to
         22    continue.
         23              CHAIRMAN JACKSON:  Before he continues, let me
         24    just ask you this question.  This has to do with this issue
         25    of definition of satisfactory.
            
                                                          28
          1              MR. KENYON:  Yes.
          2              CHAIRMAN JACKSON:  Now I noted that on the Sargent
          3    & Lundy last slide, they noted that over half the closed
          4    deficiency reports were not identified by your configuration
          5    management program.  And so what do you mean when you say
          6    it's satisfactory or tracking to satisfactory?
          7              MR. KENYON:  Well, satisfactory means two things
          8    to us:
          9              One -- and we have placed a considerable focus on
         10    safety significance, and thus as we have gone about our
         11    activities, we have looked at what we have discovered from a
         12    safety-significance perspective, and we have also looked at
         13    what Sargent & Lundy has discovered from a
         14    safety-significant perspective, and I think we are in good
         15    agreement there.
         16              But the other important area is compliance, and in
         17    that area there have been more items than we would have
         18    anticipated that don't necessarily represent true safety
         19    issues, but do -- are important from the perspective of
         20    compliance.  I'm not at all trying to say compliance isn't
         21    important.
         22              In that regard, we have more than we thought we
         23    might have, even though the safety-significance level is not
         24    -- and as part of our process, because certainly before we,
         25    Northeast Utilities, present ourselves as ready to start up,
            
                                                          29
          1    we have got to be satisfied that we not only have addressed
          2    the things that need to be addressed from a safety
          3    perspective, but we need to be satisfied that we have
          4    addressed things from a compliance perspective.  And we are
          5    still evaluating, Chairman Jackson, what the Sargent & Lundy
          6    findings, or what the NRC SSFI findings say to us,
          7    particularly from the perspective of compliance.  And we
          8    will be prepared to address that, but that's still open in
          9    our minds, and we need to pursue that.
         10              CHAIRMAN JACKSON:  You know, the Commission
         11    recently issued a statement on safety and compliance, and I
         12    commend it to you, for you to read it.
         13              MR. KENYON:  I have it.
         14              CHAIRMAN JACKSON:  And to share with all of your
         15    key people, and to use it as a template as you think about
         16    the extent to which what you are doing is consistent.
         17              MR. KENYON:  We will.
         18              Mike.
         19              MR. BROTHERS:  Thank you, Bruce.
         20              Good morning.  My name is Mike Brothers, and I am
         21    the executive sponsor for establishing and maintaining a
         22    safety-conscious work environment at Millstone station.
         23              Our definition of a safety-conscious work
         24    environment is a safety-conscious work environment is an
         25    environment where all members of the NU nuclear team feel
            
                                                          30
          1    comfortable raising any issue important to them, with the
          2    confidence that the issue will be addressed with commitment,
          3    respect, and timeliness.
          4              This definition is consistent with the NRC's
          5    position stated in their policy statement dated May 14th of
          6    1996.
          7              This presentation will present our success
          8    criteria and current progress towards establishing a
          9    safety-conscious work environment at Millstone station.
         10              This slide gives our six high level success
         11    criteria which were used to ensure that we have successfully
         12    established and are in a position to maintain a
         13    safety-conscious work environment at Millstone station.
         14              I will discuss the first four of these success
         15    criteria.  The last two, employee concerns oversight panel
         16    and Little Harbor Consulting validation of our efforts, are
         17    independent verifications that are ongoing at this time.
         18              Our assessment shows significant progress has been
         19    made and, although we do not meet our own high standards for
         20    two of our success criteria, we believe that we are on track
         21    to support the restart of Millstone Unit 3 in the area of
         22    safety-conscious work environment.
         23              The first criteria that I will discuss is a
         24    willingness of employees to raise concerns.  We believe that
         25    this success criteria is currently being met; to use your
            
                                                          31
          1    terminology, we rate this as currently satisfactory.
          2              This graph shows our current leadership results to
          3    support the success criterion of employees' willingness to
          4    raise concerns.  As shown in the slide, our criterion is at
          5    greater or equal to 90 percent of people are willing to
          6    raise issues to their immediate supervisor.  The current
          7    value is approximately 97-1/2 percent.  This criterion is
          8    currently satisfactory.
          9              CHAIRMAN JACKSON:  What's your sample size?
         10              MR. BROTHERS:  The sample size is in excess of
         11    2000 respondents; about 2600.
         12              CHAIRMAN JACKSON:  And that's out of how many
         13    people?
         14              MR. BROTHERS:  It's approximately 82 percent
         15    response rate in the survey.
         16              This graph shows the culture survey results to
         17    assess the percentage of respondents who agree that there is
         18    a safety-conscious work environment in their work area. 
         19    Although this measurement is not yet at our long range goal,
         20    we believe that current results in the overall culture
         21    survey, coupled with the percentage of people who are
         22    willing to raise concerns to their supervisor, meet our
         23    acceptance criteria for this success criterion.
         24              CHAIRMAN JACKSON:  What is the actual percentage?
         25              MR. BROTHERS:  82 percent.
            
                                                          32
          1              CHAIRMAN JACKSON:  Is it going down or up?
          2              MR. BROTHERS:  It's approximately the same.  It
          3    went up a statistically insignificant amount from one survey
          4    to another.
          5              CHAIRMAN JACKSON:  Same number of respondents?
          6              MR. BROTHERS:  Correct.
          7              This graph shows our confidentiality plus
          8    anonymous trend.  The top line is the total number of
          9    concerns received per month, and the bottom line is the
         10    total number of concerns which are requesting either
         11    confidentiality or are anonymous.  Our criteria is that no
         12    adverse trend exist in this area.
         13              Through November, this criteria is being met.
         14              CHAIRMAN JACKSON:  You don't have a criteria that
         15    actually relates to whether the number is acceptably low, or
         16    --
         17              MR. BROTHERS:  At this time, no.  We believe that
         18    what we are primarily looking for is an adverse trend.  It's
         19    consistent -- for instance, in November, the total number of
         20    concerns went down dramatically to six; yet the number that
         21    were received that were either confidentiality or requested
         22    anonymous was four.  There's not a lot that you can gain
         23    from that immediately, but we know that if we detect an
         24    adverse trend, we'd act upon it.  So it's really a trend
         25    indicator versus an absolute number.
            
                                                          33
          1              CHAIRMAN JACKSON:  Zero is not an appropriate
          2    goal?
          3              MR. BROTHERS:  Well, that's a goal; we don't think
          4    we can achieve that.  We have some sort of frictional type
          5    of numbers coming in that we believe, this has probably
          6    evolved like an IST acceptance criteria, we develop a
          7    baseline.  The baseline looks to be about three or four.
          8              The second criterion that we will discuss is the
          9    effectiveness of our line management in handling issues. 
         10    Like the first criterion, we believe that we are currently
         11    meeting this success criteria.  Therefore, this will be
         12    judged as satisfactory.
         13              This graph shows the timeliness of our CR
         14    evaluations, CR being condition report.  The goal is 95
         15    percent of all evaluations performed in less than or equal
         16    to 30 days.  The lower line represents our actual
         17    performance.  This indicator is a backward-looking
         18    indicator, since by definition it needs to be at least 30
         19    days after the CR initiation to determine success or
         20    failure.  There are currently 4.9 percent of all CR
         21    evaluations which have not had their evaluations complete
         22    within 30 days on the Millstone Unit 3.  So the snapshot in
         23    time as of yesterday is it's being met.  If current
         24    performance levels continue, this criterion will met for
         25    most of Unit 3.
            
                                                          34
          1              CHAIRMAN JACKSON:  What kind of evaluation is done
          2    within that 30 day time frame?
          3              MR. BROTHERS:  It depends upon the significance. 
          4    A significance level 1 CR requires a root cause evaluation
          5    list, that is formally waived.  A significance level 2 is an
          6    evaluation done and approved by a supervisor and a
          7    management review team, and level 3 requires only the
          8    supervisor's approval.
          9              CHAIRMAN JACKSON:  Are operability issues included
         10    in this number?
         11              MR. BROTHERS:  Yes.
         12              CHAIRMAN JACKSON:  So they are not dealt with or
         13    reviewed on a shorter --
         14              MR. BROTHERS:  A much shorter.  The reasonable
         15    assurance of continued operation is 24 hour clock on
         16    operability call.
         17              CHAIRMAN JACKSON:  What caused that initial
         18    adverse trend?
         19              MR. BROTHERS:  The numbers coming in and our
         20    inability to keep up with them.  And then we turned it when
         21    we started turning -- the numbers came down us, we completed
         22    discovery is what you are seeing.
         23              This graph shows our current condition report
         24    evaluation score.  The score is developed by averaging all
         25    CR evaluations which are reviewed by the management review
            
                                                          35
          1    team during each month.  A CR receives a 4 if its evaluation
          2    is accepted without comment; a 2 if it is accepted with
          3    comment; and a zero if it is rejected by the management
          4    review team.  This criteria is currently satisfactory.
          5              This graph shows the percentage of all action
          6    requests as a result of condition reports which are overdue. 
          7    The goal is less than or equal to one percent.  Currently,
          8    approximately 2.4 percent of action requests as a result of
          9    condition reports are overdue at Millstone Unit 3. 
         10    Significant management attention is being devoted to this
         11    metric and we expect this goal to be at goal for Millstone
         12    Unit 3 prior to restart, so this would be tracking to
         13    satisfactory.
         14              CHAIRMAN JACKSON:  The scale that I am looking at,
         15    can you say what you -- relate what you said in terms of the
         16    small percentage to what looks like 30 percent on this
         17    scale?
         18              MR. BROTHERS:  Yes.  These are -- what you are
         19    looking at here is the total number of overdue action item
         20    tracking and training systems, independent of whether they
         21    are CRs or non-CRs.  The actual CR is much -- is a smaller
         22    subset of this.  So this is all action item tracking and
         23    training systems overdues.
         24              A third criteria that I will discuss is the
         25    effectiveness of our Employee Concerns Program.  While
            
                                                          36
          1    substantial progress has been made in this area, we do not
          2    yet meet our own high standards for performance in this
          3    area.  This area will be judged as tracking to satisfactory.
          4              This slide shows the concern investigation
          5    timeliness.  The top line represents the 90 percent goal, in
          6    other words, that is simply 90 percent of the total number
          7    of concerns received per month, and the bottom line
          8    represents actual performance.  Our goal is to have greater
          9    than or equal to 90 percent of all investigations complete
         10    within 45 days.  If we were meeting this goal, the lower
         11    line would be at or above the 90 percent goal line.  As you
         12    can see, this criteria is not yet being met.
         13              While we are evaluating the validity of this as an
         14    indicator of the effectiveness of our Employee Concerns
         15    Program, we do believe that timeliness of investigations is
         16    a valid indicator of the performance of the Employee
         17    Concerns Program.  We also feel that a focus solely upon
         18    investigation timeliness can result in a degradation of
         19    performance or responsiveness of the Employee Concerns
         20    Programs.  We would just this as tracking to satisfactory.
         21              CHAIRMAN JACKSON:  Let me ask you a question. 
         22    There seems to be a discrepancy between the title, which
         23    says within 30 days, and the legend, which says 45 days.
         24              MR. BROTHERS:  Yes.  The slide is changed to 45
         25    days on the overhead.  That was error in the one that was
            
                                                          37
          1    provided to you.
          2              CHAIRMAN JACKSON:  Okay.  And also the numbers,
          3    the curve seemed to shift.
          4              MR. BROTHERS:  Yes.  This is simply the most
          5    up-to-date values that we have.  Throughout the slide show
          6    that you see, the values are as up-to-date as we can get
          7    them.  They are updated on a weekly basis.
          8              CHAIRMAN JACKSON:  Okay.
          9              MR. BROTHERS:  This slide shows a metric which is
         10    still under development.  What we are trying to measure is
         11    the number of employees who are satisfied with their
         12    experience with the Employee Concerns Program.  The top line
         13    shows the number of employees who were surveyed to assess
         14    their degree of satisfaction with the Employee Concerns
         15    Program.  The bottom line shows the number of employees who
         16    were expressing satisfaction with the Employee Concerns
         17    Program.
         18              As I said earlier, we are evaluating the
         19    implementation of this metric.  For instance, in November,
         20    20 surveys were sent out, four responded, and, of those,
         21    three expressed satisfaction.  Although a clear-cut success
         22    criteria is difficult to establish for this metric, it is
         23    clear that the current satisfaction index, to coin a term,
         24    does not meet our expectations.
         25              CHAIRMAN JACKSON:  What are your expectations?
            
                                                          38
          1              MR. BROTHERS:  We have set an expectation of 75
          2    percent.  We don't know yet if that is going to be
          3    achievable.  And we have to evaluate what the large number
          4    of non-respondents means as well.  So we are using the
          5    Employee Concerns Oversight Panel, in addition to Employee
          6    Concerns Program, to do that for us.
          7              COMMISSIONER DIAZ:  The difference between the two
          8    line is not responding?
          9              MR. BROTHERS:  Correct.
         10              CHAIRMAN JACKSON:  And that is a lower response
         11    than you have for these other?
         12              MR. BROTHERS:  Much.
         13              CHAIRMAN JACKSON:  Much lower.
         14              MR. BROTHERS:  Yes.
         15              CHAIRMAN JACKSON:  What is that the response rate
         16    again?
         17              MR. BROTHERS:  We had 20 surveys sent out and only
         18    four responded in November.  And we don't yet know what that
         19    means.
         20              The fourth criteria is our effectiveness in
         21    recognizing and remediating problem areas within the
         22    Millstone organization.  Based upon our primarily reactive
         23    response to problem areas, we not currently meeting this
         24    success criteria.  This would be judgment as unsatisfactory. 
         25    Probably at the borderline towards tracking to satisfactory,
            
                                                          39
          1    and you will see why, I believe in a few moments.
          2              CHAIRMAN JACKSON:  What is the duration of the
          3    training sessions?
          4              MR. BROTHERS:  Are you on the next slide?
          5              CHAIRMAN JACKSON:  Yes.  I am going to move you
          6    along.  You had 45 minutes and you gave us 61 slides.
          7              MR. BROTHERS:  Okay.
          8              [Laughter.]
          9              MR. BROTHERS:  I can move faster.
         10              MR. MORRIS:  Believe me, he can.  We all know he
         11    can move faster.
         12              [Laughter.]
         13              MR. BROTHERS:  Let me -- let me address each of
         14    these --
         15              COMMISSIONER DICUS:  They have more information,
         16    so they have given it to us.
         17              MR. BROTHERS:  This, the Forum for Leadership
         18    Excellence is two weeks.  The first one, the Managing for
         19    Nuclear Safety, is a one day course.  Civil Treatment is a
         20    one day course.  And 50.7 is four separate half days.
         21              This slide, as I have said, shows a compilation of
         22    our current status of providing training to our supervisors
         23    and above at Millstone Station.  Our criterion is that
         24    greater than or equal to 95 percent of all supervisors have
         25    been trained and demonstrate minimum required knowledge via
            
                                                          40
          1    written testing.  This criteria is not currently being met. 
          2    It would be judged as tracking towards satisfactory.
          3              We expect to meet this criterion by March 1998 to
          4    support the restart of Millstone Unit 3.
          5              CHAIRMAN JACKSON:  Was Little Harbor not satisfied
          6    with these percentages?  Because I am going to read, in
          7    terms of -- from their reviews, they found that the Employee
          8    Concerns Program, the Safety Conscious Work Environment and
          9    the Management Activities were not adequately coordinated. 
         10    I am going to ask them this question, too, but I want your
         11    perspective on it.  And they stated that the training was
         12    not timely and that management training was lacking --
         13              MR. BROTHERS:  Right.
         14              CHAIRMAN JACKSON:  -- in the areas of protected
         15    activities, retaliation and chilling effects.  So tell me
         16    about that.
         17              MR. BROTHERS:  The primarily was due to the slow
         18    start.  I believe that they will express satisfaction now,
         19    but the slow start, and, I would agree, the lack of
         20    coordination earlier this year, is the main result of that.
         21              MR. MORRIS:  We may not have been listening as
         22    well as we should have early on, but the message is clearly
         23    home now.
         24              CHAIRMAN JACKSON:  Okay.
         25              MR. BROTHERS:  The next slide, this slides shows
            
                                                          41
          1    the current trend for employee concerns alleging instances
          2    of harassment, intimidation, retaliation, or discrimination,
          3    with 10 CFR 50.7 implications.  The top line shows the total
          4    number of concerns received and the bottom line indicates
          5    those concerns with 50.7 implications.  Our criteria is that
          6    we do not have an adverse trend in this area.  This criteria
          7    is currently met and will be judged as satisfactory.
          8              It should be noted, however, that when we include
          9    other types of harassment, intimidation, retaliation, or
         10    discrimination, such as age, race or gender discrimination,
         11    that we did not meet our expectations in this area.
         12              Extensive executive involvement in any confirmed
         13    cases of harassment, intimidation, retaliation or
         14    discrimination, regardless of whether or not there are 50.7
         15    implications, will ensure that corrective actions up to and
         16    including reassignment or removal are effective in
         17    elimination of instances of harassment, intimidation,
         18    retaliation or discrimination at Millstone Station.
         19              CHAIRMAN JACKSON:  Is that how you intend to
         20    address, you know, meet your own standards in that area?
         21              MR. BROTHERS:  That's correct.  These are
         22    communicated via ECP HR program to me.  I communicate it to
         23    the executive team and we take action.
         24              This slide shows our total number of problem areas
         25    at Millstone Station.  A problem area is any area in which a
            
                                                          42
          1    safety conscious work environment may not exist.  Problem
          2    areas are identified by input such as Employee Concerns
          3    Program, Employee Concerns Oversight Program, Little Harbor
          4    Consultants, leadership survey or culture surveys.
          5              Our success criteria is that the total number of
          6    problem areas be decreasing.  While we meet that criteria,
          7    we have not yet demonstrated the ability to pro-actively
          8    identify and remediate problems prior to them becoming
          9    obvious problems.  We have several examples of pro-active
         10    responses to potential problem areas in the recent past.  In
         11    other words, we have successfully prevented areas from
         12    becoming problem areas by effective intervention.
         13              We expect this performance level to continue to
         14    improve and the organization's ability to identify and
         15    prevent problem areas to take precedence over our ability to
         16    remediate problem areas which have been allowed to occur.
         17              CHAIRMAN JACKSON:  Well, you know there is Delta
         18    X, I always say this, and there is Delta X Delta T.  Right. 
         19    And so what you have shown us is Delta X Delta T.  But then
         20    one can look at Delta X and ask are you satisfied?
         21              MR. BROTHERS:  And the answer would be no.
         22              Returning to our success criteria, we believe that
         23    we are meeting our criteria for employees' willingness to
         24    raise concerns, shown in green; line management's
         25    effectiveness in dealing with issues raised by employees,
            
                                                          43
          1    also shown in green.  The two shown in yellow -- or you can
          2    barely see it in yellow.  While we have made significant and
          3    meaningful progress towards establishing an effective
          4    Employee Concerns Program, we do not yet meet our own high
          5    standards in this area with regard to timeliness of
          6    evaluations and satisfaction of employees who have used this
          7    program.
          8              The fourth success criterion, our ability to
          9    recognize and address problem areas, is where we have made
         10    the least progress.  Significant progress has been made over
         11    the last month, but, based upon our slow start, this area
         12    will be our focus going forward.
         13              The remaining two success criteria, Employee
         14    Concerns Oversight Panel and Little Harbor Consulting
         15    concurrence are underway and expected to support the
         16    Millstone Unit 3 restart schedule.
         17              CHAIRMAN JACKSON:  Can you give us some sense of
         18    the significance of the issues that have been raised?
         19              MR. BROTHERS:  Within the Employee Concerns
         20    Program?
         21              We have metrics, different types of significance.
         22    From a material significance standpoint, very low numbers. 
         23    We tracked them as impact on maintenance rule and actual
         24    power block implications, very, very small numbers of
         25    employee concerns in that area.
            
                                                          44
          1              The most significant aspects involve either 50.7
          2    or other types of harassment, intimidation, and those are
          3    the most significant we had.
          4              The percentages are, if you roll in all types of
          5    harassment -- intimidation, retaliation, discrimination --
          6    are higher than what we want at this time, and that is where
          7    the significance is.
          8              Finally, I want to address the organizational
          9    changes that we have made to address the establishment of a
         10    safety conscious work environment at Millstone Station.
         11              To allow me to focus on this area, Jack McElwain
         12    has been placed in charge of the day-to-day operation of
         13    Millstone Unit III.  This is a direct result of a need to
         14    continue the momentum we have towards establishing a
         15    safety-conscious work environment at Millstone Station.
         16              In addition, Jack McElwain, taking over the
         17    day-to-day operation of Millstone Unit III, the reporting
         18    relationship of the Employee Concerns Program has been
         19    changed to report directly to me.
         20              This change, along with the designation of a
         21    recovery officer to oversee the area of Human Resources and
         22    a more coordinated utilization of the Employee Concerns
         23    Oversight Panel, ensure that we have the organization in
         24    place to fully establish a safety-conscious work environment
         25    at Millstone Station.
            
                                                          45
          1              The progress indicated in the metrics presented
          2    today and in more detail in your briefing information along
          3    with the organizational changes recently put in place give
          4    us the assurance that we are on track to support Millstone
          5    Unit III's startup in the area of safety conscious work
          6    environment.
          7              If there are no further questions, I will turn the
          8    presentation over to Marty Bowling to discuss corrective
          9    action and configuration management.
         10              CHAIRMAN JACKSON:  Thank you.
         11              MR. BROTHERS:  Thank you.
         12              MR. BOWLING:  Good morning.  Before I start my
         13    formal remarks, let me go back to your question on procedure
         14    adherence and let you know that our standard for procedure
         15    adherence has not been acceptable.
         16              We have put considerable effort into revising and
         17    raising that standard and as of September 30th implemented a
         18    newer and higher standard commensurate with the industry.
         19              We also have a number of metrics with which we are
         20    monitoring our procedural adherence so that we will have
         21    real-time feedback on what more we may need to do, but we
         22    have the right standards in place.  They are implemented and
         23    now we need to implement them.
         24              CHAIRMAN JACKSON:  Let me ask you a question.
         25    Everything leads to another question.
            
                                                          46
          1              You made an interesting statement.  You said that
          2    as of September 30th you had put a new procedural adherence
          3    standard into place that is consistent with industry and
          4    then as we talk you talk about the various standards you
          5    have in place.
          6              How do you determine those standards, and in fact
          7    are you using industry standards in all of these key areas,
          8    not just for procedure adherence but corrective actions --
          9              MR. BOWLING:  Yes.  These key programs that Bruce
         10    listed for you, we have executive sponsors and issue
         11    managers for each one of those and part of our job is to
         12    make sure that our program area is at the right standard, at
         13    the industry standard or higher.
         14              I want to talk about the radiological control area
         15    errors.  I have a specific slide for that as well as the
         16    Sargent & Lundy issues.
         17              MR. KENYON:  But to continue with the question,
         18    this is a leadership team that came from the rest of the
         19    industry, so we have our individual perspectives on
         20    standards in the industry and we utilized that to a
         21    considerable extent, but there are also areas such as safety
         22    conscious work environment where I think by the time we get
         23    through with this we will probably have set a model for the
         24    rest of the industry, so we are very attentive to industry
         25    standards but, first and foremost, we must satisfy ourselves
            
                                                          47
          1    that what we are doing is right and it makes sense.
          2              I think by the time we finish the Millstone
          3    recovery others are going to come to us in a number of areas
          4    to see what -- the standard that we have set.
          5              CHAIRMAN JACKSON:  Right.  I appreciate that
          6    point.  The only reason I raised the question is because
          7    obviously you had a renormalization of your standard --
          8              MR. KENYON:  Yes.
          9              CHAIRMAN JACKSON:  -- in this particular area. 
         10    You were not at or above the industry standard so that that
         11    is a relevant question.  Why don't you go on.
         12              MR. BOWLING:  When I talked to you in August I
         13    discussed the status of corrective actions to restore
         14    configuration at Millstone.
         15              Mike Brothers has just discussed the relationship
         16    of a strong Corrective Action Program for a safety conscious
         17    work environment.
         18              Today I will update you on our progress.  In doing
         19    so, I will review the major attributes of our program as
         20    well as overall effectiveness.
         21              In general terms, it is my view that the
         22    Corrective Action Program is on track to fully support Unit
         23    III restart readiness.
         24              This slide shows the four major programmatic
         25    elements and the supporting attributes of our Corrective
            
                                                          48
          1    Action Program.  I have color coded this slide to represent
          2    the current status which focuses on Unit III.
          3              Overall, significant progress is being made but as
          4    you can see we are not yet complete.  The two key elements
          5    of problem identification and problem evaluation are meeting
          6    expectations.  They are satisfactory.
          7              However, the key elements of problem resolution
          8    and corrective action effectiveness needs improvement,
          9    although they are on track for satisfaction.
         10              We have action plans in place to meet expectations
         11    in each of these areas by the end of January of next year.
         12              Let me further elaborate on some of the key
         13    attributes of the Corrective Action Program.
         14              CHAIRMAN JACKSON:  Let me look at that.  I have
         15    this page A-73, okay?
         16              MR. BOWLING:  Yes.
         17              CHAIRMAN JACKSON:  And that is from your status
         18    book, and I noted that as of November, '97 you have 908
         19    items to work off in three months, according to the schedule
         20    that you have laid out.
         21              MR. BOWLING:  Yes.
         22              CHAIRMAN JACKSON:  But if you look at, and now I
         23    am looking at delta x delta t, you know, if you look at the
         24    rate of work-off --
         25              MR. BOWLING:  Yes.
            
                                                          49
          1              CHAIRMAN JACKSON:  -- you know, per month or per
          2    three months, up to this point, it's not consistent with
          3    working off 908 items in the next three months.
          4              MR. BOWLING:  Yes.  I have a graphic on the
          5    restart task, but just before I get there, some of that
          6    will --
          7              CHAIRMAN JACKSON:  Address --
          8              MR. BOWLING:  -- in terms of delta t, some of it
          9    supports physical readiness, some of it heat-up, and some of
         10    it actual criticality, so it does go over a number of
         11    months.
         12              CHAIRMAN JACKSON:  Okay.  Why don't I let you do
         13    that.
         14              MR. BOWLING:  All right, okay.  Next slide,
         15    please.
         16              We have achieved a low threshold for reporting. 
         17    So far in 1997 Millstone has identified and submitted over
         18    9000 condition reports.  Most of these condition reports
         19    have been internally identified by both unit and support
         20    organizations through activities such as the Configuration
         21    Management Project and the over 300 self-assessments that
         22    have been performed on all aspects of our operations.
         23              In addition, over 30 audits and 319 surveillances
         24    have been conducted by Nuclear Oversight for key programs,
         25    processes, and activities.
            
                                                          50
          1              As a result, the percent of self-identified
          2    condition reports, as opposed to being identified by the NRC
          3    or actual events, is very high and is achieving our goal of
          4    greater than 90 percent.
          5              COMMISSIONER DIAZ:  Yes, but what does "low" mean? 
          6    Does that mean that it is satisfactory?
          7              MR. BOWLING:  Yes.
          8              COMMISSIONER DIAZ:  You could set a very low
          9    threshold and be swamped or you can set it -- you are
         10    satisfied with the low threshold that you are receiving?
         11              MR. BOWLING:  Yes.  I think this is consistent
         12    with what you would expect to see at the best performing
         13    plants in terms of low threshold.
         14              CHAIRMAN JACKSON:  And I am going to ask Little
         15    Harbor Consultants, because apparently -- I mean the
         16    question is, is this an indicator that the employees are
         17    using this system to bring forth safety concerns, and I
         18    believe based on your response to Commissioner Diaz's
         19    question you would say yes.
         20              MR. BOWLING:  Yes.
         21              CHAIRMAN JACKSON:  But of course, you know, you
         22    look at all the slides and Little Harbor seems to be saying
         23    something different.
         24              Do you have any sense of why the disparity?
         25              MR. BOWLING:  Well, let me just comment on the
            
                                                          51
          1    information that I am providing.
          2              A significant percentage of what we are
          3    identifying has to do with maintenance rule systems --
          4              CHAIRMAN JACKSON:  Okay.
          5              MR. BOWLING:  Organizational programmatic issues
          6    and process errors and so it is at the heart of our
          7    business.
          8              CHAIRMAN JACKSON:  Well, it is, but there is an
          9    issue related to people feeling that, you know, they have
         10    the freedom and flexibility to bring forth issues including
         11    issues that may relate to hardware, and so it is a relevant
         12    question in terms of what the nexus is --
         13              MR. BOWLING:  Yes.
         14              CHAIRMAN JACKSON:  -- between the two, okay, so it
         15    is not just a question of do we deal with hardware.
         16              In the end you have people who run your station
         17    and the question is do they feel that, you know, that they
         18    can bring up the issues and get them resolved, so I am
         19    interested in some resolution between what you are saying
         20    about the hardware and what Little Harbor is saying about
         21    people's willingness to use the system.
         22              MR. KENYON:  And we believe they are and we do not
         23    believe there is a disagreement between us and Little
         24    Harbor, but certainly Little Harbor needs to speak for
         25    themselves.
            
                                                          52
          1              CHAIRMAN JACKSON:  Okay.
          2              MR. BOWLING:  Finally, no backlog of operability
          3    and reportability determinations demonstrates that our
          4    employees understand the importance of whether a potential
          5    condition adversely effects nuclear safety or compliance
          6    with the design and licensing basis.
          7              Expectations for the third element of the
          8    Corrective Action Program, timely resolution, are on track. 
          9    Management and programmatic issue resolution is an important
         10    indicator of an effective Corrective Action Program.
         11              We are now on track to close all of the key
         12    management issues.  As Bruce indicated earlier, six of the
         13    16 key issues necessary for restart are now showing
         14    satisfactory results with the 10 remaining issues scheduled
         15    for January and February resolution.
         16              As an example of an effective resolution of a key
         17    management issue, this slide shows the progress that has
         18    been made in reducing entry errors into the radiological
         19    controlled areas, a longstanding and recurring problem area
         20    at Millstone.
         21              CHAIRMAN JACKSON:  Let me ask you a question --
         22              MR. BOWLING:  Yes.
         23              CHAIRMAN JACKSON:  -- on an earlier slide, right,
         24    and I know they are the new ones, but you had overdue
         25    assignments for condition reports are being reduced, and the
            
                                                          53
          1    backlogs.
          2              MR. BOWLING:  Yes.  I am going to come back to --
          3              CHAIRMAN JACKSON:  You are going to come back to
          4    those two issues?
          5              MR. BOWLING:  Yes, ma'am.
          6              CHAIRMAN JACKSON:  Okay, very good.
          7              MR. BOWLING:  Achievement of these positive
          8    results require management standard-setting, accountability,
          9    and coaching of the workforce.  We are now performing at an
         10    error rate much better than the industry with more than
         11    750,000 entries into the RCA already in 1997.  More detailed
         12    discussion of each key issue has been provided in our
         13    December 4th Progress Toward Readiness to Restart briefing
         14    book.
         15              Coming back to overdue assignments, the timely
         16    resolution of issues are the number of overdue corrective
         17    actions which Mike Brothers has already discussed.  I would
         18    just add that the overdue rate for the most significant,
         19    which we call the level one of the condition reports, is
         20    around 5 percent at this point and that is why it is not yet
         21    satisfactory.  And the size and control over our backlogs.
         22              Backlogs are being reduced on Unit 3 as indicated
         23    in the next slide.
         24              Restart tasks include those items that must be
         25    completed to support the conduct of safe operation as well
            
                                                          54
          1    as compliance with the regulations.  Backlog performance
          2    indicators for the NRC significant items list and procedure
          3    revision backlogs are also provided in your handout and they
          4    show similar trends.  Jack will also discuss maintenance and
          5    modification backlogs in his portion of the presentation.
          6              COMMISSIONER DIAZ:  Excuse me.
          7              MR. BOWLING:  Yes.
          8              COMMISSIONER DIAZ:  Are you tracking the time lag
          9    between an engineering issue being put into the task of the
         10    work orders and the actual initiation or completion of the
         11    process, the actual work?  Is that a problem?  Because I
         12    seem to see a time lag.
         13              MR. BOWLING:  There is a time lag.
         14              MR. McELWAIN:  The time lag from the engineering
         15    perspective, we put a corrective action in place that
         16    requires physical work.  We track that very rigorously and
         17    we are aware of everything that is out there that may be
         18    physical work.  If it's not, if it's a calculational change
         19    or if it's a study, we're not quite as rigorous in tracking
         20    the time from conception to completion.
         21              COMMISSIONER DIAZ:  You do realize that this last
         22    slide that you have in there, by some measure, you are
         23    tracking leniently down, which normally means you have a
         24    very rigorous and rigid process.  Is that true?
         25              MR. BOWLING:  The process is efficiencies
            
                   
                                                          55
          1    obviously could be improved.  But one of the things that you
          2    have to consider is that some of the tasks are interrelated. 
          3    So a lot of corrective action because of our controls, that
          4    is, you can't close out until all the work is done, is tied
          5    to physical work.
          6              So we would expect, with reaching the milestone of
          7    physical readiness, which is projected later this year, that
          8    a significant amount of these will go to closure.  Presently
          9    there are 46 percent of these activities that are coded to
         10    completion of physical work completion review.
         11              COMMISSIONER DIAZ:  Okay.
         12              MR. BOWLING:  Next slide, please.
         13              The last element of the Millstone corrective
         14    action program is resolution effectiveness.  We are using a
         15    number of attributes to judge effectiveness in this area,
         16    including the NRC's seal closure quality, self-assessments
         17    of completed corrective action and the ICAVP review results.
         18              With respect to the NRC's significant items list,
         19    more than 80 percent of the required closure packages have
         20    been provided to the NRC for review.  As is documented in
         21    the NRC inspection reports, the quality and completeness of
         22    these packages has been good.
         23              CHAIRMAN JACKSON:  Let me ask you a question,
         24    Mr. Bowling.
         25              Have you had examples or do you track whether
            
                                                          56
          1    there are any design basis issues that continue to arise
          2    after the system has been completed?  Do you keep track of
          3    that?
          4              MR. BROTHERS:  Yes, we do.  One of the first
          5    questions that we ask, when a condition report comes up for
          6    the management review team is, should this have been
          7    discovered, this discrepant condition, and if it is, in most
          8    times, not only is there a CR written on that fact, but
          9    there is also a CR on the actual condition.  So we track
         10    that.
         11              MR. BOWLING:  And we are also keeping the staff as
         12    well as the ICAVP contractor informed when we have those
         13    misses.
         14              CHAIRMAN JACKSON:  What are some of the most
         15    significant technical issues that you are grappling with?
         16              MR. BOWLING:  Now?
         17              CHAIRMAN JACKSON:  Now.
         18              MR. BOWLING:  Well, let me just give you that from
         19    the things we found that are most significant at Millstone
         20    Unit 3, the most significant item is a generic industry item
         21    which was the emergency core cooling system throttle valve
         22    erosion that we found.  It is now a generic industry issue
         23    that most plants are resolving by putting orafaces in to get
         24    the valves out of the cavitation range.  That's one.
         25              I would say the aggregate impact of all the eight
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                          57
          1    problems we found with the recirculation spray system was
          2    significant, although the system would still have been able,
          3    we believe, to perform its safety function.  There is a
          4    final evaluation going on to in fact prove that we found a
          5    number of issues on RSS and the SBO station blackout diesel
          6    battery capacity was significant in our minds as well. 
          7    Those were the most significant items that we found.
          8              CHAIRMAN JACKSON:  Okay.
          9              I note, you know, it's always interesting to me,
         10    and I know that you prpeare your slides and, you know, you
         11    get your final form but what's interesting is what's
         12    missing.
         13              [Laughter.]
         14              CHAIRMAN JACKSON:  And in your previous set of
         15    slides related to this in this category about corrective
         16    action resolution effectiveness, one of your criteria was
         17    that longstanding problems are being addressed.
         18              MR. BOWLING:  Yes.
         19              CHAIRMAN JACKSON:  But yet it is removed in this
         20    current set.  Can you just explain that removal?
         21              MR. BOWLING:  Yes.  This was an administrative
         22    change.  I tried to address the effectiveness in the third
         23    element and my example of radiological controlled areas was
         24    meant to address that.
         25              CHAIRMAN JACKSON:  Okay, so you're saying --
                                                                      58
          1              MR. BOWLING:  But it's certainly not lost from our
          2    program.
          3              CHAIRMAN JACKSON:  It is subsumed?
          4              MR. BOWLING:  Yes.
          5              CHAIRMAN JACKSON:  Okay.  Thank you.
          6              MR. BOWLING:  Okay, we are also performing our own
          7    self-assessments of the completed corrective actions that
          8    are most important to nuclear safety and overall
          9    organizational effectiveness.  We have not found any
         10    technical deficiencies with completed corrective actions
         11    that will be considered of high safety significance. 
         12    However, I want to take just a minute to elaborate on this
         13    point because we have found more deficiencies than expected
         14    with completed corrective actions, especially for those
         15    corrective actions that were completed prior to implementing
         16    our current standards.
         17              As a result, we are verifying the quality and
         18    completeness of the most significant corrective actions we
         19    have completed during the last two years.  This extra effort
         20    will provide additional confidence that past corrective
         21    actions meet today's standards.  And with respect to
         22    corrective actions being completed now, we are setting a
         23    high standard and our assessments show that corrective
         24    action quality has significantly improved.
         25              Finally, our assessment of the ICAVP review
            
                                                          59
          1    results today are telling us that the corrective actions
          2    taken to restore the design, licensing and operating basis
          3    have been effective in identifying both safety and
          4    programmatic issues.  A characterization of the issues found
          5    by the NU during the configuration management project are
          6    summarized in your handout.
          7              The next slide shows the significance of what has
          8    been found.  This slide shows the licensee reports submitted
          9    under 50.73 that have been submitted by Millstone Unit 3 as
         10    a result of the corrective actions taken to restore the
         11    design licensing and operating basis.  The safety
         12    significance is based on risk-informed qualitative insights. 
         13    As you can see, most of the 101 total items are classified
         14    as low safety significance.
         15              We have also reviewed approximately one-third of
         16    the potentially safety significant discrepancy reports
         17    identified by the ICAVP contractor.  These are the level 1,
         18    2 or 3 discrepancy reports.  Out of that we have confirmed,
         19    out of that one-third, that only three low safety
         20    significant issues, and no moderate or high safety
         21    significant issues have been missed by the NUCMP effort. 
         22    And so if you go to the Sargent & Lundy slide, you will see
         23    that two of the three that I am talking about are indicated
         24    there.
         25              CHAIRMAN JACKSON:  You mentioned that you use
            
                                                          60
          1    risk-informed qualitative insights.  Have you been able to
          2    apply more analytical, quantitative analytical methodologies
          3    for certain key systems to get a sense of the relative risk
          4    significance?
          5              MR. BOWLING:  We have not done a quantitative.  We
          6    are extending the qualitative assessment to look at the
          7    aggregate impact to the extent that we can, and this is
          8    certainly something that has not been undertaken, but we are
          9    trying to look at, from a total aggregate standpoint, what
         10    is the safety significance.
         11              CHAIRMAN JACKSON:  Okay.
         12              MR. BOWLING:  Okay.  Although we must still
         13    complete our reviews of all of the identified potential
         14    discrepancy reports, and have them confirmed by both the
         15    ICAVP contractor and the NRC staff, we believe that the
         16    Configuration Management Program has been effective in
         17    finding and addressing safety significant issues.
         18              With respect to the NRC inspections, the tier 1
         19    out of scope safety system function inspection has been
         20    evaluated on Unit 3.  Their tier 2 and 3 inspections are in
         21    progress.  As you know, these NRC inspections are resulting
         22    in a number of potential violations.  Although we do not
         23    believe that the findings, in themselves, are of high safety
         24    significance, they do indicate some program weaknesses and
         25    absolutely do not meet our standards for compliance.
            
                                                          61
          1              From the NRC tier 1 inspection report, we are
          2    addressing the identified program weaknesses now.  The first
          3    deals with the design and operating interfaces between
          4    systems that are relied upon to perform a safety function.
          5              With respect to design and operating interfaces,
          6    we have utilized a multi-discipline functional review team. 
          7    This effort expands what we have already done on CMP by
          8    addressing accident mitigation and the dynamic interactions
          9    of stand-by systems with operating systems during a
         10    transient.
         11              Conceptually, we are looking horizontally at an
         12    overall system response to accidents and integrating that
         13    with our CMP, which was a deep but graded system-specific
         14    vertical slice.
         15              Therefore, our functional review is a reasonable
         16    self-check of the effectiveness of CMP from a safety and
         17    design basis perspective, and provides a higher assurance
         18    that safety systems will function in concert during any
         19    plant transient.
         20              This review has not found any significant safety
         21    issues or non-compliances with the design or licensing
         22    basis.  Lower significant items have been identified and are
         23    being assigned for corrective actions.
         24              The second weakness identified in the tier 1
         25    inspection report deals with the accuracy of procedures to
            
                                                          62
          1    meet the technical specifications surveillance requirements. 
          2    With respect to compliance with the technical
          3    specifications, we are currently conducting further reviews
          4    and no new reportable non-compliances have been identified.
          5              The NRC tier 1 inspection report also indicates
          6    that additional attempt to FSAR accuracy and procedural
          7    compliance issues are warranted.
          8              Finally, the NRC preliminary tier 3 inspection
          9    results have been debriefed with us.
         10              CHAIRMAN JACKSON:  Let me ask you question about
         11    this.
         12              MR. BOWLING:  Yes.
         13              CHAIRMAN JACKSON:  In terms of technical
         14    specification compliance.  I mean you say no new
         15    non-compliances have been identified.  Have you done a full
         16    scope of assessments?
         17              MR. BOWLING:  This project is still ongoing and is
         18    scheduled to finish in early February.
         19              CHAIRMAN JACKSON:  You mean have not been
         20    identified to date?
         21              MR. BOWLING:  To date.  Right.
         22              CHAIRMAN JACKSON:  And that is based on what kind
         23    of a scope of review?
         24              MR. BOWLING:  That is looking at all of the
         25    surveillance procedures that are used to meet and adhere to
            
                                                          63
          1    the tech spec surveillance requirements, and that has been
          2    in progress since we -- our own self-assessment showed that
          3    we needed to re-look at that, and so that has been going on
          4    for several months.
          5              CHAIRMAN JACKSON:  Okay.
          6              MR. BOWLING:  Okay.  With respect to the tier 3
          7    inspection, the design -- the NRC has debriefed with us and
          8    indicated that the design control program meets Appendix B
          9    requirements and is able to effectively maintain
         10    configuration.
         11              In summary, the actions that have been taken to
         12    date to restore and maintain configuration, and to address
         13    longstanding safety and programmatic issues, are being
         14    effective.  Still, we recognize that all the corrective
         15    actions necessary to restore full compliance have not yet
         16    been completed.  This will be completed prior to restart.
         17              Also, we must make sure that our organization
         18    demonstrates, going forward, --
         19              CHAIRMAN JACKSON:  Prior to your coming to ask us
         20    for a restart decision.
         21              MR. BOWLING:  Yes, ma'am.  Going forward -- also,
         22    we must make sure that our organization, going forward,
         23    demonstrates a healthy respect for regulations, from both an
         24    intent and a compliance standpoint.  However, I do believe
         25    that our Corrective Action Program will support the conduct
            
                                                          64
          1    of safe operations.
          2              If there are no further questions, I will turn it
          3    over to Jack.
          4              CHAIRMAN JACKSON:  Commissioner Dicus has a
          5    question.
          6              COMMISSIONER DICUS:  It's another case where the
          7    slides, the packet we had, that I studied, changed a little
          8    bit from the packet that we have in front of us.  The slide
          9    didn't, but its location did.
         10              I would like for you to go to back-up slide No. 7,
         11    please.
         12              The slide is entitled, "Radiation Protection," and
         13    it says, "Progress.  Radiation protection practices continue
         14    to improve and oversight will continue to monitor
         15    performance."  But the graphics don't show that on the
         16    slide, from my -- my viewpoint, and it is over only about a
         17    four month period of time, but the graphics basically show a
         18    steady state, fluctuating somewhat, but a steady state.
         19              It is back-up slide No. 7.
         20              So my question is, your statement, radiation
         21    protection practices continue to improve, but the graphics
         22    don't show it.
         23              MR. BOWLING:  Okay.  This -- this is from the
         24    Nuclear Oversight assessment of the Radiological Protection
         25    Program, from a total program concept, and Dave Goebel can
            
                                                          65
          1    address that more.  But from my standpoint, what I was
          2    trying to show was the actual violations of procedural
          3    requirements or regulatory requirements on performance in
          4    the RCA, radiological control areas.  And, so, based on that
          5    trend, we have shown substantial progress.  But that is only
          6    one element of the overall Radiological Protection Program.
          7              COMMISSIONER DICUS:  Okay.  So there are other
          8    aspects of it that are keeping this from being higher?
          9              MR. BOWLING:  Well, the other thing about this.
         10              COMMISSIONER DICUS:  That would be my point.
         11              MR. BOWLING:  Right.  The other thing about this
         12    graph is that you can see that, even though it is at stable
         13    trend, it is well into the satisfactory area.  So it is
         14    meeting expectations.
         15              MR. KENYON:  Commissioner Dicus, I think it would
         16    be helpful that when --
         17              COMMISSIONER DICUS:  Okay.
         18              MR. KENYON:  -- Mr. Goebel gets to his
         19    presentation and takes you through what these kinds of
         20    slides mean, that then we can talk specifically about that
         21    one and put it in context.
         22              MR. McELWAIN:  Good morning.  I am Jack McElwain,
         23    I would like to give a present status on Unit 3.
         24              We are on track for Unit 3 physical readiness by
         25    the end of December.  The key issues are completion of
            
                                                          66
          1    motor-operated valve work, restart modifications, and
          2    restart maintenance backlog.
          3              The next two slides, I will explain why I believe
          4    we are on track.
          5              This slide represents the total start-up related
          6    automated work orders.  As you can see, the first vertical
          7    bars on the left are representing monthly totals and the
          8    right side are further broken down by week through the end
          9    of December.  This was done to illustrate clearly what
         10    remains to be done prior to being physically ready.
         11              There are currently, on the slide, there are 677
         12    automated work orders required for physical readiness.  This
         13    is broken down into those three categories, MOVs, MODS and
         14    maintenance.
         15              The slide depicts our continuing plan which shows
         16    the effort required for these three areas relating to AWO
         17    closeout.
         18              As you can see in the motor-operated valve area,
         19    there are 97 completed and 46 remaining, which will close
         20    out -- of the 46 that are remaining, when we finish that
         21    work, we will close out 171 automated work orders.  That is
         22    what this slide is intended to show us.
         23              COMMISSIONER DIAZ:  What is the difference?  I got
         24    lost between the 143 and the 171.
         25              MR. McELWAIN:  There is no one-to-one ratio for
            
                                                          67
          1    143 valves and 143 work orders.  There have been about 400
          2    work orders for motor-operated valves, for the 143 valves. 
          3    There is no one-to-one, bean for bean.  But that just shows
          4    when we close out those last 46, we will close 171 of those
          5    automated work orders.
          6              CHAIRMAN JACKSON:  Now, does completed or closed
          7    out mean that the drawings are updated?
          8              MR. McELWAIN:  The red line drawings are updated. 
          9    The testing is complete.  The analysis has been done for
         10    operability.  For example, in the differential pressure
         11    testing, dynamic testing, you have to go through an
         12    operability determination analysis before we say that that
         13    valve and that work orders are complete.  And that will
         14    happen.
         15              Of the 46, all but four are issued to the field
         16    today, and work is approximately 40 percent complete.  And
         17    the four that are not issued to the field are boundary
         18    valves for the alpha training that we are in now.  We need
         19    to get five valves back before we can issue those last four.
         20              In the MOD area there are 127 of 182 complete. 
         21    The remaining 55, 35 are in progress and will complete with
         22    the present alpha training outage, and the remaining 20 are
         23    scheduled to be completed prior to 12/24/97.
         24              CHAIRMAN JACKSON:  Let me go back to -- well, it
         25    doesn't matter, you can pick either category.  But if we go
            
                                                          68
          1    back to the MOVs, you said 97 are complete, and I appreciate
          2    what you say about the number of automated work orders
          3    versus the number of valves, but in terms of getting some
          4    sense of, you know, of a match-up between the two, if 97,
          5    the work, I presume you mean, on 97 MOVs is complete.  How
          6    many of the automated work orders does that -- none of them
          7    are done, related to that, or --
          8              MR. McELWAIN:  About 300 of the automated work
          9    orders relating to motor-operated valves are done with those
         10    97.
         11              CHAIRMAN JACKSON:  With those 97.
         12              MR. McELWAIN:  But the number might be 250, but it
         13    is --
         14              CHAIRMAN JACKSON:  I understand.
         15              MR. McELWAIN:  It is in that range.  And it is not
         16    just the physical work, is through testing complete also.
         17              CHAIRMAN JACKSON:  So the 171 are associated with
         18    the 46 left?
         19              MR. McELWAIN:  Yes.
         20              CHAIRMAN JACKSON:  Okay.
         21              MR. McELWAIN:  In the corrective maintenance area,
         22    the work for alpha training has been issued and performance
         23    is on schedule to meet completion prior to 12/24/97.
         24              CHAIRMAN JACKSON:  Now, again, you know, you
         25    always have steep work-off curves.  I asked the question
            
                                                          69
          1    about stress when you were here before, you know, stress on
          2    your manager and stress on your people.
          3              MR. McELWAIN:  Yes.
          4              CHAIRMAN JACKSON:  Do you want to make some
          5    comments along --
          6              MR. McELWAIN:  Well, I will tell you that if you
          7    looked at the people responsible for these activities right
          8    now, they are the opposite of stressed.  They are excited
          9    because they see the end of their very, very long effort. 
         10    That is purely my personal judgement, but that is what I
         11    see.
         12              MR. MORRIS:  My team always gets a little upset
         13    with me when I raise this issue, but if we don't finish this
         14    work till after the holidays, so that people can enjoy some
         15    time, that would be acceptable with us.  But they don't like
         16    me to say that.
         17              MR. KENYON:  And it is not that we don't like him
         18    to say it.  It's really okay.
         19              But just to add another comment, Chairman Jackson,
         20    the difference between what you are seeing now and what you
         21    have seen in previous presentations is that we have had
         22    previously a big backlog of work, some of which was
         23    scheduled.  What we have now is a much smaller backlog of
         24    work.
         25              CHAIRMAN JACKSON:  Still big though.
            
                                                          70
          1              MR. KENYON:  But this is very do-able.  What --
          2              CHAIRMAN JACKSON:  But is it scheduled now?
          3              MR. KENYON:  It is all scheduled and that's --
          4    that's the key point.  What Jack has taken you through is
          5    categories of work orders, but they are into an outage
          6    schedule that comes to completion before the end of this
          7    year.  And, you know, if we have a valve testing problem, or
          8    whatever, that carries us over into January 5, but
          9    everything is scheduled and this is very do-able, and the
         10    employees who are doing this work absolutely believe that
         11    this can be done in the time frame that is laid out.  So
         12    this is very achievable.
         13              CHAIRMAN JACKSON:  You know, I asked you this
         14    before, and I will ask you every time, and that's why I
         15    asked the question about if you complete things and you find
         16    problems after you have completed them, do you feel that you
         17    are appropriately balancing scheduler concerns with
         18    comprehensive resolution of the issue?
         19              MR. McELWAIN:  Yes.  I can give you what I think
         20    is a concrete example.  When we have come out of the two
         21    major evolutions we were in prior to the alpha training,
         22    which was the VCT outage, which was a very lot of work
         23    involved in that, we did not put pressure on getting into
         24    the bravo training outage from a transitional point of view. 
         25    We just stayed away from having any perception that we had
            
                                                          71
          1    to force the evolutions to go to meet a certain time frame.
          2              It took longer than it would normally take in an
          3    outage situation, but that is the situation we are in, so we
          4    didn't make a lot of noise about that.  The same with going
          5    from the bravo training to the alpha training.  It took
          6    longer than it should have, but where we are at in time,
          7    that's okay, and we didn't put any pressure on operations or
          8    anyone else to speed it up, to make it happen quicker.
          9              CHAIRMAN JACKSON:  Now, again, you know, you had a
         10    slide 50, which is the current set, and a slide 47, which
         11    was the previous, and it mentioned is the key activity
         12    complete for the OSTI readiness inspection, safety system
         13    reviews and alignments?
         14              MR. McELWAIN:  Yes.
         15              CHAIRMAN JACKSON:  Why did you remove that?
         16              MR. McELWAIN:  It is part of what is scheduled. 
         17    Every system walkdown, system review and the procedure that
         18    evaluates that system for readiness is in the schedule. 
         19    They have been working them off.
         20              CHAIRMAN JACKSON:  Presumably, the pre- -- these
         21    other three bullets are in the schedule, too.
         22              MR. McELWAIN:  Yeah, but these are really relating
         23    to the physical work end.
         24              CHAIRMAN JACKSON:  I see.
         25              MR. McELWAIN:  The system readiness reviews,
            
                                                          72
          1    although they are ongoing, are not going to complete prior
          2    to physical work, you wouldn't expect they would.
          3              CHAIRMAN JACKSON:  Okay.  So this is physical
          4    readiness.
          5              MR. McELWAIN:  Yes.
          6              MR. BROTHERS:  The system readiness reviews will
          7    be completed prior to the system being required by tech
          8    specs, so, in other words, when we go, transition to mode 4,
          9    where most of our tech specs kick in on Unit 3, the system
         10    readiness reviews will be done for all the systems required. 
         11    The same thing for mode 3, mode 2.
         12              CHAIRMAN JACKSON:  Okay.  Well, when you talk
         13    about, you know, readiness for the operational safety team
         14    inspection, --
         15              MR. McELWAIN:  They will be done before that.
         16              CHAIRMAN JACKSON:  Right.  Then you need to, you
         17    know, be comprehensive, as opposed to kind of lifting it off
         18    and then saying to me this only has to do with physical
         19    readiness.  If it has to do with physical readiness only,
         20    then you should say it is such.
         21              MR. McELWAIN:  Yes.
         22              CHAIRMAN JACKSON:  If it really has to do with the
         23    OSTI, then you should say, you know, --
         24              MR. McELWAIN:  Although they aren't related,
         25    certainly.
            
                                                          73
          1              CHAIRMAN JACKSON:  Obviously, they are related,
          2    but you want to have done the systems reviews and
          3    alignments.
          4              MR. McELWAIN:  Yes.
          5              CHAIRMAN JACKSON:  And that is the point.
          6              MR. McELWAIN:  This slide introduces the topics to
          7    be covered in the next several slides is all this is for.
          8              Marty talked about the significant items list. 
          9    This is just a graphic representation of where we are at. 
         10    We are on track to meet the unit schedule.
         11              The next slides shows our current organizational
         12    assessment for Millstone Unit 3.  Our current assessment
         13    shows that we do not currently meet the overall unit
         14    organizational performance levels required to support a
         15    return to operation today, but we believe we are tracking to
         16    satisfactory and will be at that level, in all departments,
         17    to support the current unit schedule.  Therefore, as you can
         18    see from the slide, our overall organizational
         19    self-assessment is yellow.
         20              We have shown significant progress over the first
         21    two quarters in basically all of the areas that we have been
         22    monitoring.  So we have been doing it by quarter and now we
         23    are doing it monthly.  Dave will tell you we also get the
         24    same look from oversight from their perspective.  Next
         25    slide.
            
                                                          74
          1              Operational readiness is on track to support OSTI. 
          2    As you brought up earlier, there are some questions about
          3    where we are with operations and I'll get to that as I go
          4    through this a little bit.
          5              CHAIRMAN JACKSON:  Are you going to talk about how
          6    you addressed the issue with the operator performance?  As I
          7    recall, a year ago you had six of seven license applicants
          8    who failed examinations.
          9              Are you going to speak to what has been done to
         10    correct that and how that plays into the numbers here?
         11              MR. McELWAIN:  We could.  We recognize that was
         12    one issue, but yes.
         13              CHAIRMAN JACKSON:  Well, that would be helpful.
         14              MR. McELWAIN:  Sure.
         15              Presently on Unit 3 the requal program is judged
         16    to be satisfactory.
         17              CHAIRMAN JACKSON:  You are Vice President, Unit 1,
         18    right?
         19              MR. McELWAIN:  Yes, ma'am.
         20              CHAIRMAN JACKSON:  Okay.
         21              MR. McELWAIN:  I understand.  Staffing is
         22    adequate.  We presently have 41 licenses, 28 of which are
         23    SROs; 13 are reactor operators.
         24              We also have, it's not shown on the slide, 30
         25    plant equipment operators.
            
                                                          75
          1              We have a new conduct of operations, which was
          2    kind of talked about before.  It was approved and issued on
          3    September 5th and we are making strides to have everyone
          4    embrace that and understand exactly what it means, and that
          5    was one of the things that the consultant that you mentioned
          6    earlier had given me personally as well as Mike some
          7    feedback on, and that's the kind of issues he is talking
          8    about in operations now, and going to watch the operators
          9    perform, it's the same thing you would see if you did it or
         10    I did it.
         11              We have also started to perform at power
         12    familiarization at other power plants including Comanche
         13    Peak, Vogel, North Anna, and Seabrook.  Eleven of the 28
         14    SROs have participated in this familiarization and the
         15    remaining are scheduled for that.
         16              We also have experienced SROs from other utilities
         17    working with our operations management, particularly one
         18    from Virginia Power that's been there for awhile doing I
         19    would say a standards intervention.
         20              We also have recently lined up an intervention
         21    from a person who was formerly the Senior Manager of
         22    Operations at Peach Bottom when they went from a SALP 2 to a
         23    SALP 1 and that area is working directly with Ops Management
         24    and they are having a hands-on, face-to-face time away from
         25    the plant intervention so everybody gets to understand
            
                                                          76
          1    clearly what all the expectations are going forward.
          2              So we are taking some direct interventions to have
          3    an impact on the perception of operator readiness.
          4              To go back to the original question, six out of
          5    the seven failures on Unit 1 license exam in December of
          6    '96, we have taken actually a very thorough look at the
          7    Licensed Operator Initial Training.  We have spent the last
          8    nine months of '97 looking at the systematic approach to
          9    training and how it applies to the LOIT class.
         10              We have looked at every task, analyzed them all.
         11              Dave analyzed the organization.  The training
         12    people worked very well with the unit to develop and get
         13    ready to implement in February, probably late February,
         14    early March of 1998, another Licenced Operator Initial
         15    Training class for Unit 1.
         16              MR. KENYON:  But I think what needs to be added
         17    here is that as a result of those training failures and a
         18    lot of work we had a class go forward on Unit 3, a total of
         19    eight.
         20              MR. McELWAIN:  Eight for eight.
         21              MR. KENYON:  And eight out of eight passed at
         22    either the SRO or our reactor operator level that they were
         23    put up for.
         24              CHAIRMAN JACKSON:  Let me give you some advice.
         25              Now you are here -- you are talking to us and you
            
                                                          77
          1    want us to focus on Unit 3 and we are certainly here to hear
          2    that, because that is the station that the reactor you have
          3    lined up for early start, but all three of your reactors are
          4    shut down because of some systemic issues, and therefore it
          5    is important, you know, if you are asked a question about it
          6    that you think about it within the context of all your
          7    units.
          8              MR. McELWAIN:  Thank you.
          9              MR. KENYON:  Thank you.
         10              MR. McELWAIN:  Next slide, please.
         11              The following significant milestones have been
         12    achieved, particularly in the area of Operations.
         13              The reactor coolant system fill, sweep, and vent
         14    was done very well.  This was perceived to be very well done
         15    and event-free by both the line and the oversight
         16    organizations.
         17              The spent fuel pool anti-siphon modifications are
         18    complete, and the implementation was very well performed,
         19    but we did not, going into it, have it clearly,
         20    well-planned, as well as it could have been planned, from
         21    both a tech spec perspective as well as an actual execution.
         22              The reason I bring that us is because it is
         23    accurate and to tell you that the input we got from
         24    oversight in the pre-planning process made this evolution
         25    happen as well as it did.  It speaks very well from my
            
                                                          78
          1    perspective to positive intervention from oversight and
          2    adding value to something that is a very complex process,
          3    but the end result was it was very well executed.
          4              The containment basemat physical work is complete
          5    and the preliminary core bore results are acceptable, and as
          6    I mentioned earlier, the Bravo train outage is complete and
          7    the Alpha train is in progress.
          8              The last slide shows the Unit 3 milestone
          9    schedule.  I have already talked a little bit about the Tier
         10    2, Tier 3 -- Tier 2 and 3.  The plant will be physically
         11    ready or on track to meet this milestone by the end of the
         12    year.  The NRC in-scope SFFI is scheduled for January as
         13    well as a 40,500 ready for Mode 4 operations presently
         14    scheduled in January also and ready for OSTI in 2-98
         15    timeframe.
         16              In conclusion, I believe we are on track to meet
         17    all these milestones in support of the Unit 3 schedule.
         18              CHAIRMAN JACKSON:  Where do you stand on emergency
         19    preparedness?  There was an inspection report, 97203, that
         20    noted some problem areas.
         21              MR. McELWAIN:  Having participated in a graded
         22    exercise and looking at the results of the programmatic look
         23    I was encouraged by the results of the graded exercise
         24    itself and the level of performance of the participants,
         25    recognizing that from the dose assessment piece as well as
            
                                                          79
          1    some of the procedural issues about maintenance of those
          2    procedures and of facilities that was more disheartening,
          3    but it is fixable.
          4              We have been working diligently since the exit,
          5    not waiting for the report to come out, to have plans in
          6    place to remedy the issues that were brought up during that
          7    inspection.
          8              CHAIRMAN JACKSON:  So you are saying you are
          9    developing plans to specifically address all of those?
         10              MR. BOWLING:  Well, I'll just add we will be
         11    speaking with the Region Staff next week on this subject.
         12              An extensive amount of corrective action on the
         13    program has taken place.  However, we did have some dose
         14    assessment calculational issues.
         15              In the currently ongoing Tier 2 inspection, the
         16    inspectors have brought up some issues in this area.  Our
         17    own self-assessment tells us we need to look more at this
         18    area and we have formed a team that's already just started
         19    to -- actually brought an external consultant in, into this
         20    area, to make sure that what we have is correct and meets
         21    all the requirements.
         22              MR. KENYON:  I would like to give a little broader
         23    answer though, because we are working on certain very
         24    discrete issues in the emergency planning area, but in terms
         25    of the performance of the overall exercise and how the
            
                                                          80
          1    individuals involved in responding to the situation and
          2    dealing with it and the performance of outside agencies and
          3    so forth, I am quite comfortable sitting here today saying
          4    we have an effective program.  We just have certain things
          5    we need to address.
          6              CHAIRMAN JACKSON:  I'm sorry, please.
          7              COMMISSIONER McGAFFIGAN:  Can I ask one question
          8    about what morale is like back at Unit 1 at the moment?
          9              Have other workers also been assigned to the other
         10    two units to do work, and what is the situation there?
         11              MR. McELWAIN:  Morale honestly ebbs and flows on
         12    Unit 1 depending on where we are in time and what the latest
         13    analyst says in the Wall Street Journal and things like that
         14    do have a direct and immediate impact.
         15              Yesterday we had an all-hands meeting from the
         16    entire unit staff, and we went over the Vision and Mission
         17    for 1998 and all of the questions centered around finances
         18    and the ability to support what we need to do to get Unit 1
         19    ready in 1998.
         20              But to answer the other part of your question,
         21    currently we have approximately 40 maintenance I&C; people
         22    working on Unit 3 so they are having that sense of
         23    accomplishment.  They are very busy.
         24              At the same time, we have been able to maintain
         25    our shutdown risk status as Green while still doing some
            
                                                          81
          1    work.  For example, we had the gas turbine outage and
          2    earlier this week we had a very brief planned diesel
          3    generator outage, so we are doing a lot of things but mostly
          4    right now the physical workers are supporting Unit 3 and
          5    what is currently happening on the ICAVP or CMP for Unit 1,
          6    so morale does ebb and flow.
          7              Yesterday it wasn't nearly as bad as it was a week
          8    before, but it does change depending on the kind of
          9    information they get, and most of it is from outside.
         10              COMMISSIONER McGAFFIGAN:  Is that a distraction to
         11    the site as a whole at all, the ebb and flow?
         12              MR. McELWAIN:  I think my perception is that the
         13    Unit 3 people for example understand the impact of what we
         14    are doing on 3 and not doing on 1 has, and I believe the
         15    interaction is very positive and they do ask me routinely
         16    the same question you asked me, which is good.  This is an
         17    issue that we are all very aware of.  As Jack says, you can
         18    imagine the impact on the people when they read and hear
         19    things about Unit 1 but it is an issue that we are trying
         20    very hard to be straightforward and open with so that they
         21    have a clear picture of where we're going.  But it is
         22    something that we are tuned in to.
         23              CHAIRMAN JACKSON:  Okay.  Anything else.
         24              MR. McELWAIN:  That's it.
         25              Dave?
            
                                                          82
          1              MR. GOEBEL:  Good morning.  Today, we will provide
          2    you a synopsis of nuclear oversights, readiness for restart
          3    and how I am assessing the readiness of the Millstone units
          4    for restart.
          5              First, I will discuss senior management's success
          6    criteria for nuclear oversight and then I will discuss the
          7    nuclear oversight restart verification plan or NORVP and
          8    some of the specific results from that plan.
          9              Let me start with the success criteria for nuclear
         10    oversight.  There are three success criteria.
         11              First, that the Nuclear Safety Assessment Board or
         12    NSAB has confirmed the effectiveness of nuclear oversight. 
         13    They have done that.  The NSAB has reviewed oversight's
         14    performance and stated that oversight has effectively
         15    performed its 10 CFR 50 Appendix B functions.
         16              Let me make it clear however that this vote of
         17    confidence means to me that we have met the minimum
         18    expectations for recovery and I intend on making additional
         19    improvements to our current state before restart.
         20              The second criterion is problems that are being
         21    identified by Millstone organizations prior to external
         22    agencies well before events occur.  Last month, looking at
         23    the station, about 90 percent of all condition reports were
         24    identified by Millstone nuclear organizations.  Marty has
         25    already addressed that.  Over the past six months, 92
            
                                                          83
          1    percent of all condition reports have been self-identified
          2    by NU.  Oversight, that is the line and nuclear oversight,
          3    are therefore meaningless success criteria.
          4              The third success criteria is that management
          5    embraces oversight's assessments.  This chart shows that the
          6    unit and support organizations have been working to address
          7    the nuclear oversight to generate the condition reports. 
          8    You can see that the total number of condition reports that
          9    are open, that is need evaluations and corrective action
         10    plans, have dropped significantly since the first half of
         11    the year.  The number now is less than 35.
         12              I might add that I am still assessing our ability
         13    to close out the corrective actions associated with the CRs
         14    which are being written and by closed out, I mean the
         15    necessary corrective actions have been completed and were
         16    effective in addressing the initial problem.  Marty has
         17    talked to the team which the line organizations have set up
         18    in order to go back and look at old CRs.  I have a separate
         19    team which is doing a similar effort to show that we have an
         20    independent view of what the success rate is in that area.
         21              Thus far, my initial look says that the conditions
         22    have improved.  We have gone back and looked at 44 condition
         23    report packages and within those packages are 257 individual
         24    actions that had to be taken and our evaluations on a
         25    grading system went up above 15 percent on capability and
            
                                                          84
          1    put clearly into the satisfactory range.
          2              Let me now turn to how we are assessing unit
          3    readiness for restart, the nuclear oversight restart
          4    verification plan.  First, we identified 22 key issues such
          5    as corrective action, leadership, self-assessment, training
          6    and then some functional areas such as security and
          7    emergency preparedness and that provided us the strategic
          8    focus for the plan.  Then we developed a list of critical
          9    attributes to examine for each issue.  The attributes were
         10    drawn from NRC documents such as inspection guides and
         11    manual chapters.  Such as, for instance, manual chapter
         12    0350, which are staff guidelines for restart approval and
         13    from industry guidance.  For instance, the INPO performance
         14    objectives as criteria for operating nuclear generating
         15    stations.  We also took attributes from the NU success
         16    criteria and the NU standards and management expectations.
         17              To assess and score these attributes, we developed
         18    a score sheet to grade all activities to perform on a zero
         19    to 100 scale.  The form we use is in the backup book.  In
         20    brief, the way the scoring works is this.  Fifty points
         21    relate to the quality of the task performed so that if there
         22    is a programmatic weakness in the task that is being
         23    performed, it would get a very low score and if it is an
         24    industry strength, it would get a high score.  And 50 points
         25    are allocated to the human side of the equation, with a
            
                                                          85
          1    clear expectation for trained people, clear procedures, was
          2    there teamwork involved, was there good self-checking and
          3    self-assessment involved.
          4              We then take the scores developed throughout the
          5    entire organization and create a report for each issue.  The
          6    report includes a numerical score and very specific review
          7    of strengths and weaknesses which are identified during that
          8    particular evaluation period.  On the report that we provide
          9    back to the line organization, we also list those attributes
         10    which specifically require attention in order to move the
         11    issue into the satisfactory overall range.  This information
         12    is then shared throughout the line and support
         13    organizations.
         14              On the next slide, what you see is results, the
         15    nuclear oversight restart verification plan for Unit 3 for
         16    the past several weeks.  We are now actively viewing 20
         17    areas for both Unit 3 and Unit 2.  Five of the areas are
         18    common or site-wide issues such as emergency preparedness
         19    and security.
         20              As is aid, we use our normal audit, surveillance,
         21    field observation and other processes as part of our
         22    verification plan, grade each of the activities on a zero to
         23    100 scale and then average the scores on a bi-weekly basis. 
         24    Last week, we had over 450 observations.
         25              In order to improve our observation of oversight
            
                                                          86
          1    activities, I have also grouped the issues into three areas. 
          2    Readiness for the 4500 inspection of corrective actions and
          3    self-assessment, physical plant readiness and readiness for
          4    the operational safety team inspection and I will provide my
          5    recommendation to the president and the CNO as to whether
          6    nuclear oversight believes the unit is ready for the NRC to
          7    come in and conduct its inspections.
          8              What I would like to do now is go over a couple of
          9    these issues with you.  Conduct of operations.  This is one
         10    of the most important issues.  As you can see, there is a
         11    standby for each evaluation period which represents the
         12    average score of all the attributes which were assessed in
         13    that period.  And you can see that the trend of the scores
         14    over several weeks is generally upward.
         15              You can also see the scores required to achieve a
         16    color.  For example, a score between 70 and 100 is green or
         17    satisfactory.  You can see that operations is hovering near
         18    green or satisfactory performance.
         19              We have some strengths in operations.  For
         20    example, control room decorum is very good.  There are few
         21    distractions allowed and communications is a notable
         22    improvement area.  Enunciated response is also meeting
         23    industry standards.  But there are also some areas that need
         24    attention.
         25              We feel that there is inconsistency in performance
            
                                                          87
          1    between the operating crews.  Maintaining configuration
          2    control is not as rigorous as we want them to be and, by
          3    that, I mean valve mispositioning and that sort of thing. 
          4    Operators in the field need to actively monitor the
          5    housekeeping industrial safety practices of other
          6    departments that are in the field.  We take those and then
          7    after each grading period feed that back to the line and
          8    have a lot of discussion between my lead person and the lead
          9    people on the line.
         10              The next slide shows work control and planning
         11    which is also another critical issue.  Here, you see again
         12    there are some ups and downs over the past few weeks and
         13    generally you can see that work control process is
         14    improving.
         15              Now, the areas in which improvement is needed here
         16    are greater focus on completing the PMs and surveillances on
         17    time, ensuring that work is not released to the field with
         18    wrong or insufficient parts and ensuring the post
         19    maintenance testing requirements are not changed without
         20    proper authorizations.
         21              CHAIRMAN JACKSON:  How are you saying on this
         22    slide and the previous one that it's improving?  I mean, it
         23    seems like the bar graphs are going the other way, but maybe
         24    it's my imagination.
         25              MR. GOEBEL:  Chairman, these are individual,
            
                                                          88
          1    bi-weekly forms.
          2              CHAIRMAN JACKSON:  So you are saying if you have
          3    more integrated data
          4              MR. GOEBEL:  Right, and it's gradually as a whole
          5    coming up.
          6              CHAIRMAN JACKSON:  Okay.
          7              MR. GOEBEL:  I mean, for instance, there may be 10
          8    pages of attributes.  We don't get them all every week so
          9    it's --
         10              CHAIRMAN JACKSON:  Okay.
         11              MR. GOEBEL:  Then when you look at procedure
         12    quality and adherence, you can see that there has been
         13    steady improvement in the degree and range.
         14              Now, if you go back and take Marty's comment that
         15    there was a procedural change in the standards back near the
         16    end of September and you compare that against the chart,
         17    what you see is it took a little bit of time for that to
         18    take hold but as those improved standards took hold, then
         19    the performance improved.  So there is a tie -- unknowingly,
         20    there is a tie in the process.  I mean, if there are
         21    improvements made, the process is able to pick that up. 
         22    That's the point I'm trying to make.
         23              What I've tried to do is just present a sampling
         24    of the results from the verification plan process and what
         25    I've provided you in your backup materials is all of the
            
                                                          89
          1    issues from both Unit 2 and Unit 3.
          2              In conclusion, I would like to state that nuclear
          3    oversight believes that restart readiness is within reach. 
          4    The NSAB has confirmed that nuclear oversight is effective
          5    in carrying out its 10 CFR 50 Appendix B duties and we are
          6    continuing to improve our performance through internal
          7    self-assessment, external assist visits from industry
          8    experts and improvement plans.  Line management is listening
          9    to our findings and appreciates the insights provided by
         10    oversight.
         11              I can conclude therefore that, based on the
         12    objective evidence being provided through our verification
         13    plan assessments, audits and surveillances that we do, field
         14    observations and inspections, that the station is focusing
         15    management attention on the correct issues and is
         16    demonstrating improvement in the key issue areas and a
         17    restart of Unit 3 in the first quarter of '98 is an
         18    achievable goal.
         19              Subject to any further questions, I will pass it
         20    back to Bruce.
         21              COMMISSIONER DICUS:  Back on slide 7, I assume
         22    that your response to my previous question would be I guess
         23    the same as the response to the Chairman's questions on the
         24    previous graphs.  Again, the statement and the graphs just
         25    don't quite seem to meet.
            
                                                          90
          1              MR. GOEBEL:  Right.  In the radiation protection
          2    area, again, we don't get all the attributes on any one
          3    week.  And, for instance, the latest one, just to give you
          4    an example of the type of information we go back with on the
          5    observations we had, positive points that got fed back to
          6    the organization was a good team spirit within the RP
          7    organization, when they interface with other departments,
          8    good ALARA practices are present, a lot of proactive
          9    planning briefs and coaching for rad work and practices
         10    improvement, positive self-assessment planning for the
         11    three-year to complete the RP program review so there are
         12    some positive long-range things that we are looking at to
         13    make themselves better.
         14              But we did find a problem as well in this
         15    particular week and one of those problems was that there was
         16    a meeting that determined a certain performance criteria
         17    which they are setting for their own windows evaluation,
         18    their own criteria needed some buffing up, that it wasn't as
         19    strong a criteria set as we felt you ought to have.  It was
         20    not as -- it was more subjective than we would like to see.
         21              The types of things which we recommended are major
         22    areas to continue strong work on is basically continue there
         23    from and have people comply with the various RP controls and
         24    you have to constantly stay at that and continue to work
         25    synergistically with the rest of the organization.
            
                                                          91
          1              So those are the types of things that we feed back
          2    to the organization on a biweekly basis.  And then I, in my
          3    interface with the officers at the frequent meetings we
          4    have, I point out either in writing or verbally those key
          5    areas that I see really need work if they want to get on to
          6    the time lines which they have set.
          7              CHAIRMAN JACKSON:  You mentioned earlier at an
          8    earlier point when we were talking about oversight a lack of
          9    familiarization with people in your organization with the
         10    plant.  Where do the people in your organization come from? 
         11    What are their backgrounds?  I don't see their
         12    backgrounds --
         13              MR. GOEBEL:  No, I understand.
         14              CHAIRMAN JACKSON:  I mean, where do they fit
         15    within the overall corporate organization.
         16              MR. GOEBEL:  A lot of the folks -- I'm not even
         17    sure I can qualify a lot.  Some of the folks have been in
         18    oversight for some time and are not licensed operators and
         19    they have had -- they may have come from engineering, have
         20    an engineering background.  They may have come out of a
         21    function associated with a plant which does not put them in
         22    the direct licensing path so they don't get the true
         23    operational feel for the plant.  And we have some folks that
         24    we've -- some of the skill that we've brought in from the
         25    outside, we've particularly tried to go after people who
            
                                                          92
          1    have had increased experience in all the key issue areas
          2    where we have to have expertise.  So when I've gone out
          3    shopping for people, I've looked at it from the standpoint
          4    of what skill sets we need to fill and I've gone after those
          5    particular skill sets.  And some of those folks, although
          6    they have an individual specialty skill set, they don't know
          7    these systems because they came from someplace else.
          8              So the outside consultants' comment to us was not
          9    that your folks are not knowledgeable because they are
         10    knowledgeable but, on these particular systems, you need to
         11    get them out so they really understand these systems and
         12    that was the tenor of the comment -- that was the tenor of
         13    the conversation.
         14              CHAIRMAN JACKSON:  Does the line organization
         15    respect your organization?
         16              MR. GOEBEL:  I think the answer to that is yes,
         17    but I will say that it is up and down.
         18              It has been up and down and we -- it's something
         19    that we all have to continue to work at.
         20              I have it work at it on my side so that -- I think
         21    in this business you earn respect and I have got to provide
         22    a quality product so that the line has a reason to respect
         23    my product.
         24              On the other side, on the line side, if they don't
         25    respect it they need to come back with constructive
            
                                                          93
          1    criticism on how to make that work and we are making that
          2    dual loop work for us.
          3              MR. MORRIS:  I would tell you that that respect is
          4    growing from points that I have been checking on, that very
          5    issue.  It is very important to us that that be the case and
          6    it is there and it is growing, but there is work to be done.
          7              MR. KENYON:  In closing, I would like to restate
          8    our challenged somewhat differently.
          9              First, to directly address the leadership
         10    challenges at Millstone it was necessary to establish a new
         11    leadership team and to regain the confidence of our
         12    employees.  This has been achieved.  I have a lot of
         13    confidence in this leadership team.
         14              Second, our challenge has been to set the proper
         15    standards, and in so doing address the various site issues
         16    which have been the major performance problems at Millstone,
         17    and I want to pause here to really acknowledge our
         18    receptivity to the advice that you gave earlier in the
         19    meeting.
         20              These are site issues.  Some of these site issues
         21    can only be looked at as site issues -- emergency planning,
         22    security.  I mean these are clearly issues that there's no
         23    way to subdivide.
         24              There are other issues such as the restoration of
         25    the design and licensing basis where the standards that must
            
                                                          94
          1    be met are site standards, but you can talk about where a
          2    particular unit is in relation to those standards -- issues
          3    of work backlog and effectiveness of how we do business.
          4              We want to have a common way of doing business but
          5    then you can talk backlog on a particular unit, so we are
          6    very sensitive that what we are about is to some extent it
          7    is getting a particular unit ready but what I have said from
          8    our very first meeting is that the fundamental problem at
          9    MIllstone was leadership and the ensuing issues that are
         10    site issues in terms of how leadership functioned.
         11              So we recognize that what we have to do even
         12    though we are getting ready to say to you that we think a
         13    particular unit is ready to go, we have to have addressed
         14    the site issues in order for a unit to be in a reasonable
         15    place to start up, so we certainly acknowledge the advice
         16    you have given us.
         17              With regard to the site issues, I want to make two
         18    points.
         19              First is that in contrast to my last briefing with
         20    you, our last briefing with you, I do believe we are on a
         21    success path, tracking to satisfaction, for all of the
         22    issues, and as I indicated earlier, most of the issues are
         23    going to reach satisfaction in January and the remaining
         24    three in February.
         25              But I really want to emphasize something I said
            
                                                          95
          1    earlier in response to one of your questions, and that is
          2    that we absolutely recognize that reaching satisfaction for
          3    startup is not the end of the road for us.  This has got to
          4    be part of a long-term effort toward excellence.
          5              Taking safety conscious work environment as an
          6    example, we absolutely know that the training that we have
          7    in progress, which we think is excellent training and it is
          8    what our management team needs, this can't be the end of
          9    training on this issue.  This can't be the end of emphasis
         10    on this issue.
         11              This has got to be part of our ongoing how we do
         12    business.
         13              The same thinking applies for all of the other
         14    site issues that we have.  Improvements must continue as
         15    part of a long-term plan to achieve excellence.  This plan
         16    is under development and will be addressed to you at our
         17    next meeting.
         18              A third challenge has been to reduce the large
         19    backlog of work to a manageable level with the achievement
         20    of physical readiness around the end of this month.  I think
         21    that challenge will have largely been met.
         22              The fourth and final challenge I want to mention
         23    is to prepare the unit for operation.
         24              In January, following achieving physical
         25    readiness, we'll be ready for Mode 4.  That will allow us to
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                          96
          1    heat the plant up.
          2              That will allow us to really exercise operations
          3    and we need to do that to satisfy ourselves that the
          4    operating folks are really ready to go, because up to now
          5    they have been largely dealing with not only a shut down
          6    plant but it's been mostly system lineups and what do you do
          7    to support work over here versus work over there, and we
          8    have really got to get them back into an operating mode for
          9    our own purposes in preparation for startup and to achieve
         10    readiness for the NRC's operational safety team inspection
         11    in early February.
         12              Chairman Jackson and Commissioners, I truly
         13    believe we are on the home stretch for Unit 3 in recovering
         14    our first Millstone unit, and I look forward to our next
         15    meeting.
         16              CHAIRMAN JACKSON:  Thank you.  Mr. Morris, do you
         17    have any final comments you wish to make?
         18              MR. MORRIS:  No, I do not, Chairman Jackson. 
         19    Thank you very much for your time and attention and the
         20    questions.
         21              I think our team learned a lot today.
         22              CHAIRMAN JACKSON:  Thank you.  While the next
         23    group, which I believe -- I see the various consultant
         24    groups coming forward.  We are going to take a five-minute
         25    break.
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                          97
          1              [Recess.]
          2              CHAIRMAN JACKSON:  Good morning.  I think it is
          3    still the morning.
          4              I think we will hear in turn from Sargent & Lundy
          5    and then from Parsons Power and why don't you just begin. 
          6    You can identify yourselves and proceed.
          7              MR. ERLER:  Good morning Chairman Jackson and
          8    Commissioners.  I am Brian Erler, Senior Vice President,
          9    Sargent & Lundy, and Project Director for the ICAVP.
         10              As we did last time, we will be going through some
         11    of the general information that applies to both Parsons and
         12    our work and then a report in detail on the status of where
         13    we are at.
         14              With me is Don Schopfer, Vice President and
         15    Manager of the Sargent & Lundy ICAVP and he will be
         16    presenting the data in detail.
         17              MR. SCHOPFER:  Good morning.
         18              The first slide.
         19              We have some background information and some
         20    refresher information on the structure and the processes
         21    used on the ICAVP for both units.  As described in the
         22    commission paper written by the staff, the ICAVP is being
         23    performed in a three-tiered process.  The tier one reviews
         24    or, excuse me, verifies that the system meets the licensing
         25    and design basis and system functionality.  The tier two
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                          98
          1    review verifies that the system design parameters relied on
          2    to mitigate the consequences of accidents analyzed in
          3    Chapter 15 of the FSAR are consistent with the performance
          4    of the current system configuration.  And the tier three
          5    review verifies that the configuration control processes
          6    used by Northeast Utilities at Millstone have not introduced
          7    any changes that have put the unit in nonconformance with
          8    its licensing and design basis.  The majority of the work is
          9    being performed in the tier one, that is where the majority
         10    of the effort is being spent.
         11              The NRC staff and Sargent & Lundy and Parsons have
         12    developed a common process for reporting the findings
         13    identified during the review process.  These findings are
         14    called discrepancy reports.  As I go through, this is how we
         15    stepped through that discrepancy report process.
         16              An individual reviewer initiates a preliminary DR. 
         17    It then undergoes an internal review process within Sargent
         18    & Lundy or Parsons, as the case may be.  Upon completing
         19    that process, the preliminary DR is issued to Northeast
         20    Utilities, the NRC staff and the NEAC, Nuclear Energy
         21    Advisory Council of the State of Connecticut and it is
         22    posted on the web site.
         23              Northeast Utilities evaluates that preliminary DR
         24    and submits a response back to us and we then review that
         25    response and either return it to them with additional
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                          99
          1    comments or we may close it at that time based on their
          2    response.
          3              CHAIRMAN JACKSON:  Did you look at proposing any
          4    alternatives, for example, in sampling?  You know, based on
          5    what you find?
          6              MR. SCHOPFER:  We have developed sampling programs
          7    for certain aspects of the review.  When we do that, we
          8    submit that to the staff for their acceptance.
          9              CHAIRMAN JACKSON:  Right.  But, I mean, are they
         10    renormalized by what you find?  Did you suggest additional
         11    samples, enlargement, different techniques?
         12              MR. SCHOPFER:  We have not made a change in those
         13    things that we have sampled as a result of that.
         14              DRs are closed based on our review and acceptance
         15    of the NU responses.  The NU response to a discrepancy
         16    report, a preliminary discrepancy report is, it expected to
         17    include whether they agree with the condition that we have
         18    identified as a discrepancy, whether they have
         19    previously -- had previously identified that during their
         20    configuration management program and, if they have not
         21    previously -- if they agree that it is a discrepancy and
         22    they have not previously identified it, they identify what
         23    action has been taken or will be taken to correct that
         24    particular discrepancy.  And whether they agree with the
         25    significant level that we have established for the DR and if
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         100
          1    there is any impact, specifically on plant hardware.  And,
          2    in the case of generic or programmatic issues, the response
          3    should address the extent or condition that may exist with
          4    the discrepancy.
          5              CHAIRMAN JACKSON:  How does this discrepancy
          6    report process allow you to get at the tier three aspect?  I
          7    understand that in doing the discrepancy report you could
          8    verify that the system -- whether it meets its licensing or
          9    design basis, you could verify that the system parameters
         10    correspond to the actual performance.  You know, the design
         11    parameters correspond to the performance.
         12              But how do you verify in this process that the
         13    configuration control processes have not introduced changes
         14    that would put or that have put the unit into
         15    nonconformance?
         16              MR. SCHOPFER:  Well, part of the tier three as we
         17    will show a little bit later what the scope is, part of the
         18    tier three is review of corrective actions and we review the
         19    corrective action process to see that they have done an
         20    adequate job in resolving the issue that is identified.
         21              On some of the past changes, we look at did they
         22    make that design change appropriately and not -- this is
         23    outside of the tier one systems -- did they make those
         24    design changes or those procedure changes without making the
         25    other appropriate changes to the design basis and licensing
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         101
          1    basis.
          2              CHAIRMAN JACKSON:  Does that get captured in the
          3    discrepancy report?
          4              MR. SCHOPFER:  Yes, it does.  Everything that is
          5    in noncompliance with what our expectations are, our
          6    checklists and the scope of the review plan, is identified
          7    as a discrepancy report.
          8              CHAIRMAN JACKSON:  So you are actually looking at
          9    process as well as looking at the actual confirmed DR with
         10    design and licensing?  Okay.
         11              MR. SCHOPFER:  The DRs, when they are closed,
         12    based on the review of the NU response, may be categorized
         13    into three different areas.  It may be a confirmed DR and
         14    that is one that is not -- a discrepancy that has not been
         15    previously identified by the Northeast Utilities
         16    configuration management program, or it may be identified as
         17    previously identified, categorized as previously identified,
         18    which means they did in fact identify it prior to the start
         19    of the ICAVP and we were not able to discern that during our
         20    review process, or we may agree that it is, in fact, a
         21    nondiscrepant condition based on some additional information
         22    they submit with their response.
         23              CHAIRMAN JACKSON:  Are you going to talk about how
         24    your discrepancy reports break out between the tier one,
         25    tier two and tier three categories?
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         102
          1              MR. SCHOPFER:  I have some of that --
          2              CHAIRMAN JACKSON:  And are there any conclusions,
          3    even preliminarily, on the strengths and weaknesses of the
          4    licensee's programs as a consequence that you can make?
          5              MR. SCHOPFER:  And I will address that.
          6              CHAIRMAN JACKSON:  Okay.
          7              MR. SCHOPFER:  There are four levels of
          8    discrepancy report significance that have been established
          9    for the ICAVP.  They are noted here on this slide.  A level
         10    one is a discrepancy that results in a system not meeting
         11    its design licensing basis and cannot perform its intended
         12    function when both trains of that particular system are
         13    affected.  Level two is similar except that only one train
         14    of a redundant system is affected.
         15              Level three is a discrepancy that -- under which
         16    the system is also not meeting its design and licensing
         17    basis but it does not render that system incapable of
         18    performing its intended function.
         19              A level four DR is a discrepancy that is a minor
         20    technical error in a calculation or a procedural change that
         21    is not significant in terms that it made -- allowed someone
         22    to do something incorrectly on a large number of processes,
         23    or it is inconsistency perhaps between documents.
         24              CHAIRMAN JACKSON:  Let me ask you this question. 
         25    In looking at the level three significance level, do you
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         103
          1    look at -- if a system doesn't meet its licensing and design
          2    basis but is capable of performing its intended function,
          3    are you reviewing as part of that or evaluating as part of
          4    that whether the licensee has done an analysis to in fact
          5    demonstrate that the system is capable of performing its
          6    intended function?
          7              MR. SCHOPFER:  We are not doing the analysis -- an
          8    analysis, per se, to verify.
          9              CHAIRMAN JACKSON:  No, no, no.  I'm saying, are
         10    you verifying that they have done that?
         11              MR. SCHOPFER:  Yes.  Yes, that is part of our
         12    expectation of receiving a response on a level three, that
         13    they have done that review and convinced us that -- and
         14    provided the results of that analysis to show that that
         15    discrepancy in fact does not render that inoperable.
         16              CHAIRMAN JACKSON:  And are you keeping track of
         17    whether that analysis was already existing or whether it is
         18    analysis that is done in response to your query?
         19              MR. SCHOPFER:  Yes, we are looking at that.
         20              CHAIRMAN JACKSON:  And my last question is, are
         21    you overlaying on all of this a risk ranking in terms of in
         22    the various tiers and looking at what you found?  That's
         23    probably reflected in the systems in fact that you are
         24    reviewing?
         25              MR. SCHOPFER:  Yes.  We have not done that in
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         104
          1    terms of risk ranking but the selection of the systems was
          2    based on risk ranking.
          3              CHAIRMAN JACKSON:  And then one last thing.  When
          4    you look at what the licensee has done in terms of its
          5    analysis, do you -- do you review whether that analysis is
          6    done from the point of view of capturing the things that
          7    have the greatest risk or safety significance?
          8              MR. SCHOPFER:  Yes.
          9              CHAIRMAN JACKSON:  Okay, thanks.
         10              MR. SCHOPFER:  That is basically the last of my
         11    comments on the overall ICAVP process for both units and
         12    this will begin the discussion now of Unit 3 specific ICAVP. 
         13    As a background, again, the scope of the tier one review for
         14    Unit 3 is as shown here.  The systems identified,
         15    servicewater, QSS, RSS system, three HVAC systems that
         16    includes the supplemental leakage collection and release
         17    system, the aux building ventilation system and the
         18    emergency diesel generator room ventilation system.  And the
         19    fourth system, fourth set of systems is the diesel generator
         20    and associated support systems.
         21              The -- each of these systems, and this constitutes
         22    I think about 14 of the 88 maintenance rule group one and
         23    two systems at Millstone Unit 3.  The designations at the
         24    bottom of that slide are the shorthand notations we have
         25    used for that grouping of systems in our -- in our process.
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         105
          1              In addition to the systems, the specific systems
          2    listed there, the review also includes the electrical power
          3    feeds from each component up to the first motor control
          4    center feeding that and then a load path review which is a
          5    somewhat less detailed review from that particular motor
          6    control center back to the diesel generator.  Also, the INC
          7    signals that interface with these systems from other systems
          8    are also included in that review process.
          9              CHAIRMAN JACKSON:  Let me ask you this quick
         10    question.  Can you describe a couple of the DRs that were
         11    not identified by the licensee's Configuration Management
         12    Program and what significance you would attach to them?
         13              MR. SCHOPFER:  Sure.  We have one that is in
         14    process right now that was submitted.  We responded and we
         15    returned it back to them, asking for additional -- to
         16    address other aspects.  That was a containment penetration
         17    design that is fixed on both ends of the inside and outside
         18    the containment, plates that are welded on and this
         19    penetration is welded at both ends.
         20              The RSS system temperature went up as part of some
         21    of the changes in the RSS modifications that was talked
         22    about previously, went up to 257 degrees and that
         23    temperature change on that penetration itself being welded
         24    at both ends was not addressed.
         25              It is a calculation error that we identified that
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         106
          1    needs to be addressed, and that is a safety or significance
          2    level 3 item, a significance level 3 item where a corrective
          3    action was done.  This is a Tier 3 review.  The corrective
          4    action document we reviewed did not address everything that
          5    needed to be addressed including the procurement of
          6    environmentally qualified terminal blocks.  That was a level
          7    3.
          8              Level 4s -- you probably don't want me to identify
          9    level 4s.  There's multiple examples of those but is that
         10    sufficient?
         11              CHAIRMAN JACKSON:  If I jump ahead to your last
         12    slide, that's not to say you can't talk about the ones in
         13    between --
         14              MR. SCHOPFER:  Thanks.
         15              [Laughter.]
         16              CHAIRMAN JACKSON:  I note that over half of those,
         17    the DRs, that were acceptable and closed were not identified
         18    by the licensee's Configuration Management Program and you
         19    heard me talk about that earlier.
         20              MR. SCHOPFER:  Yes.
         21              CHAIRMAN JACKSON:  Is there any significance that
         22    you attach to that or that we should attach to that?
         23              MR. SCHOPFER:  Well, I think we have to sort that
         24    out in total when we are finished here, but at this point a
         25    couple things to note, I guess.
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         107
          1              Of those 38, only two have been confirmed as level
          2    3's.  I did mention one of those, which was a terminal block
          3    EQ.
          4              The rest have been level 4s.
          5              Many of them have been calculation errors.  The
          6    last slide is in fact the slide that is on the screen now,
          7    which is a couple slides added to what perhaps was submitted
          8    earlier, but that summary shows the type and discrepancy
          9    level of the 38 closed DRs.
         10              You can see that they are mostly in the
         11    calculation area.  There are some in the basically as-built
         12    configuration, the installation implementation, and some in
         13    the licensing documents, but what this may indicate is that
         14    the Configuration Management Program and the ICAVP are not a
         15    one-for-one that they did exactly the same thing and exactly
         16    the same depth.
         17              I think particularly in the calculation area, we
         18    have done a detailed review of all the calculations on these
         19    systems and the CMP program performed by NU did not
         20    necessarily go to that level of detail for all those
         21    calculations.
         22              That is why you will see a number of those as not
         23    previously identified.
         24              CHAIRMAN JACKSON:  Okay, thank you.
         25              MR. SCHOPFER:  Okay.  The slide that shows the
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         108
          1    scope of Tier 1 system review has the four system
          2    designators, the shorthand designators, at the top and it
          3    identifies the magnitude of the scope of the review really,
          4    and I am not going to go through any of these numbers other
          5    than the fact that these are the system requirements for
          6    each system.  The numbers of calculations are the numbers of
          7    the various documents including the corrective action
          8    documents in the NU system that were reviewed as part of
          9    this.
         10              Again, this is where the majority of the ICAVP
         11    process has been.
         12              The Tier 2 review scope included all of the
         13    accidents analyzed in Chapter 15 of the Millstone 3 FSAR. 
         14    It included 22 systems that are used to mitigate the
         15    consequences of an accident and 230 critical characteristics
         16    that were identified from the review of the accident
         17    analysis and verified.
         18              Those critical characteristics were submitted to
         19    the Staff for their acceptance and they concurred or
         20    commented on those.
         21              The intent of the Tier 3 review is to review
         22    various changed processes on a greater number of systems
         23    than the Tier 1 does and to verify that the design and
         24    licensing basis has in fact been maintained.
         25              We reviewed the current NU change processes and
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         109
          1    that included 11 changed processes, 20 procedures, and 8
          2    chapters of their Design Control Manual.
          3              We also reviewed the implementation of those
          4    current processes, and those procedures basically were new
          5    as of earlier this year.
          6              We had some additional corrective action reviews
          7    that were selected, sample selected by the NRC Staff outside
          8    of the Tier 1 systems and some 280 changes that were done in
          9    the past at various times, all the way back to the 1985-86
         10    timeframe to see that changes made then did not adversely
         11    impact the licensing and design basis.
         12              CHAIRMAN JACKSON:  Now I noted that the Tier 1
         13    review is scheduled to be completed on Monday.  Are you
         14    going to make that schedule?  It's the 15th of December.
         15              MR. SCHOPFER:  The Tier 3 review.
         16              CHAIRMAN JACKSON:  Tier 3, right.
         17              MR. SCHOPFER:  Tier 3 review, yes.  Yes, in fact,
         18    we are, and the tier -- and the next slide shows that the
         19    Tier 2 review is in fact complete from the discovery phase,
         20    and I'll just mention that.
         21              That is the discovery portion of the reviews that
         22    we are talking here.  Obviously we have to get the responses
         23    from NU for the discrepancy reports and evaluate them, and
         24    then basically analyze the results and submit a final
         25    report, but our review process will be done on the dates
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         110
          1    that are shown here in terms of identifying issues and
          2    writing the discrepancy reports that may have to be written.
          3              CHAIRMAN JACKSON:  Mr. McGaffigan.
          4              COMMISSIONER McGAFFIGAN:  Could I ask, the
          5    schedule that we had back in August obviously was about
          6    three months --
          7              CHAIRMAN JACKSON:  Your mike is not on.
          8              COMMISSIONER McGAFFIGAN:  The schedule we had back
          9    in August contemplated dates about three months earlier than
         10    these dates.
         11              Was that always -- you hinted at the time that
         12    there were problems and maybe with additional resources you
         13    could keep to it, but it was going to be a stretch.
         14              Was it always close to "mission impossible" to
         15    have kept to anything like that schedule?
         16              MR. SCHOPFER:  During the August meeting we said
         17    we were evaluating the schedule.  We had just gotten the
         18    additional systems and we were evaluating what it would take
         19    to do that.
         20              We did in fact change by about two months, I
         21    believe, from the date that we established after this
         22    meeting in August.  We established I think an October date
         23    at that time -- or, excuse me, a November date, and now it
         24    is two months beyond that.
         25              COMMISSIONER McGAFFIGAN:  Since I have the floor,
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         111
          1    I will ask one other question that is a hypothetical
          2    question and those are probably always -- your counsel would
          3    tell you to avoid answering it, but let me ask it anyways --
          4              [Laughter.]
          5              CHAIRMAN JACKSON:  That never stops Commissioner
          6    McGaffigan.
          7              COMMISSIONER McGAFFIGAN:  I'll ask you -- it would
          8    help me if you could answer it.
          9              If we took a top quartile plant, you know, INPO 1,
         10    SALP 1, or 1.24-5 plant and subjected them to the same
         11    inspection that you have been doing, how would Millstone be
         12    different?  Do you mean compare?  How would Millstone
         13    compare?  We have gone through a very extensive process and
         14    there are relatively small numbers of discrepancies, or
         15    levels -- levels of the discrepancies are not very
         16    significant, it looks like.  I mean two level 3's and 30-odd
         17    level 4's.
         18              Take a top plant, you know, that you may have some
         19    experience with.  If they went in -- I mean --
         20              CHAIRMAN JACKSON:  Would they look the same?
         21              COMMISSIONER McGAFFIGAN:  Would they look the
         22    same?
         23              MR. SCHOPFER:  No, they wouldn't necessarily look
         24    the same, but you would have -- you would still have a
         25    number of discrepancy reports written on the basis that this
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         112
          1    program was set up on.  The level of detail, and looking
          2    back at calculations done, I said -- I talked about changes
          3    made in -- processes made in '85 and '86.  We are looking at
          4    calculations done perhaps in '70s and early '80s, and other
          5    plants that are in that category would have some issues with
          6    calculations done at that time also.
          7              That doesn't mean they are not significant.  But
          8    there would -- I am sure there would be some differences in
          9    terms of the numbers and the type.  But there would be
         10    issues like this.
         11              COMMISSIONER McGAFFIGAN:  Would Millstone be
         12    comparable to a -- at this point, having -- not every plant
         13    has invested what Millstone has over the last year to get
         14    ready for you all, but would Millstone now be comparable to
         15    a pretty good plant, if you were to do a similar inspection
         16    at -- at one of the top quartile plants?
         17              MR. SCHOPFER:  I guess, based on the review to
         18    date and, as you can see, the number of responses that we
         19    have actually looked at in terms of -- or closed, I would
         20    use the term that they are on track.  Their configuration
         21    control, their design and licensing basis has been restored,
         22    I think, relatively well, based on the Configuration
         23    Management Program, which is what we are basically
         24    reviewing.  So, as it stands today, they are on track to
         25    satisfactory, if that was the terminology that you used
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         113
          1    earlier, Chairman Jackson.
          2              COMMISSIONER McGAFFIGAN:  You are doing a good job
          3    avoiding the question.
          4              MR. SCHOPFER:  Thank you.  Thank you.  I was
          5    successful.
          6              [Laughter.]
          7              CHAIRMAN JACKSON:  Why don't you go on.
          8              MR. SCHOPFER:  Okay.  Where was I?  I guess I was
          9    on the project milestone schedule.  As we said the discovery
         10    completes on the date shown there.
         11              There were three specific areas that were included
         12    in the scope of the ICAVP for Unit 3 that had significant NU
         13    engineering activities continuing this summer and fall, and
         14    that was, as Northeast Utilities personnel mentioned
         15    earlier, a significant number of -- or a number of
         16    significant modifications that were made to the
         17    recirculation spray system, some revisions to the service
         18    water system hydraulic calculations and the motor-operated
         19    value work in accordance with Generic Letter 89-10.
         20              Those -- those things, issues were completed and
         21    -- from an engineering standpoint, and most of that
         22    information was submitted to us in mid to late November and
         23    we are in the process of finalizing that, and that is what
         24    has pushed that tier 1 date, or the -- the date out to
         25    1/15/98, that's the primary basis for that.
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         114
          1              And, as noted here, our final report date is
          2    somewhat dependent how well we do, "we" meaning both Sargent
          3    & Lundy and Northeast Utilities, in responding to the
          4    discrepancy reports and getting that -- those issues closed
          5    out.
          6              The next slide, which is not really my last slide,
          7    but it was previously submitted last slide, is a summary of
          8    the closed discrepancy reports.  As noted earlier, we have
          9    the process that issues preliminary discrepancy reports and
         10    then end-user response and the closure process.  There have
         11    been about 500-plus preliminary DRs issued to date, and
         12    about 220 of those have been responded to by Northeast
         13    Utilities.  And of those, we have completed the review as of
         14    last week on 74, with 38 of those as confirmed DRs, 20
         15    previously identified and 16 undiscrepant, the 38 show a
         16    significance level here of primarily, almost entirely level
         17    4's, with the two level 3's DRs.
         18              CHAIRMAN JACKSON:  How many total do you have yet
         19    to review then?  I mean to close out in the sense that you
         20    have closed these.
         21              MR. SCHOPFER:  We have issued 550.
         22              CHAIRMAN JACKSON:  Five fifty.
         23              CHAIRMAN JACKSON:  Five hundred and fifty to date. 
         24    In fact, -- and that's, the next slide probably provides
         25    that information.  And I have tried to break it up by tier
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         115
          1    1, tier 2 and tier 3, to give a sense of where we are on the
          2    closure process.  Those numbers should add up to about 547,
          3    I believe, on the issued numbers, and those preliminary DRs,
          4    the NU responses, again, as of last week, it's 184, and I
          5    think that number is probably about 220 or 230 now, and the
          6    74 that have been closed.
          7              As you can see, tier 1 is most complete in terms
          8    of the DR responses provide by NU and reviewed by Sargent &
          9    Lundy.  NU has responded to something over 80 percent of the
         10    tier 2 DRs and we have completed the review on about 75
         11    percent of those.  And the result is that we have found
         12    nothing significant there.  Basically, we have, you know, a
         13    handful -- a handful, some more to get responses on and some
         14    more to be reviewed, some, including some level 3's, but we
         15    believe that, what we have seen to date, that we can
         16    conclude that their systems that are needed to mitigate the
         17    consequences of an accident are, in fact, in the correct
         18    configuration and design basis for that.
         19              Tier 3 is the next most complete with about half
         20    of NU responses, and our review being about half of that. 
         21    Part of that being there are various pieces of a tier 3
         22    review, as we went through earlier, and the NU -- the
         23    comments that we have -- or the conclusions that we have
         24    reached, similar to what was reported today on the NRC tier
         25    3, is that we do believe their design control process is --
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         116
          1    meets 10 CFR 50 and is an adequate, satisfactory process for
          2    going forward.
          3              And their corrective action reviews and past
          4    changes appear to be satisfactory also.
          5              So we have no -- no significant findings coming
          6    out of either the tier 2 or the tier 3 at this time.
          7              COMMISSIONER DIAZ:  Is this tracking which is
          8    scheduled, the number that are still to be responded and
          9    closed, how does that track with the proposed schedule?
         10              MR. SCHOPFER:  The -- I'll tell you that I also
         11    will have a steep work-off rate, but the resources are truly
         12    being focused on finishing the discovery.  And when they are
         13    finished, and as the schedule slide showed, next week,
         14    basically, we will be able to spend more time on the
         15    responses.  We have done that as we go along, but those
         16    resources will then be allowed to focus more on the
         17    responses and take a large updraft.  So I think we will be
         18    able to meet the dates that we are talking about here.
         19              CHAIRMAN JACKSON:  So you are saying there are no
         20    show-stoppers to this point?
         21              MR. SCHOPFER:  That is correct.
         22              And the last slide, I think we talked about
         23    earlier, is basically a breakdown of the levels and types of
         24    the confirmed DRs of the closed -- excuse me, of the
         25    confirmed DRs that are discrepant and calculations and
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         117
          1    as-built configuration being a couple of the primary areas,
          2    but nothing significant found in those areas.
          3              CHAIRMAN JACKSON:  Okay.
          4              MR. SCHOPFER:  That's all I have.
          5              CHAIRMAN JACKSON:  Thank you very much.
          6              MR. CURRY:  Good morning, Chairman Jackson.
          7              CHAIRMAN JACKSON:  Good morning.
          8              MR. CURRY:  My name is Dan Curry and I am the Vice
          9    President of Nuclear Services for Parsons and I am also
         10    acting as the Project Director the Unit 2 ICAVP.  I have
         11    John Hilbish with me today.  John is the head of our
         12    regulatory review portion of the ICAVP project.
         13              I would start, addressing the agenda, and tell you
         14    that there is a difference between these two units, if you
         15    think about the age of these two units, and that will cause
         16    some significant changes to the volume of work that we will
         17    be talking about, that we will be doing.  And, certainly, as
         18    we would recognize the difference between a plant that went
         19    on-line in 1975, when we talk about calculations, these are
         20    calculations that in some cases have been done back in the
         21    '60s.  So some of the things have been moving ahead.  And
         22    some of our reviews, of course, encompass, in some cases,
         23    ten years more than what you have heard about on Unit 3.
         24              We are performing this, primarily this review at
         25    our headquarters in Redding, Pennsylvania, supported by our
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         118
          1    site walkdown team at the site.  The tier 1 review, as has
          2    been discussed previously, a deep vertical slice.  Our two
          3    systems, the last time I was here, we had just completed the
          4    boundary review for those first two systems.  We have now a
          5    second set of systems selected by NEAC in the middle of
          6    September.  Each one of these selected systems, as Sargent &
          7    Lundy had indicated, have significant interfaces and it
          8    averages about 14 additional systems of the maintenance rule
          9    systems would interface with each one of these.
         10              If I talk about the tier 2, again, a very similar
         11    process.  We have identified, to give you a further idea of
         12    the extent, about 56 of the 63 maintenance rule systems are
         13    affected by things that we must look at to validate the tier
         14    2 requirements.  The process here is one that we identify
         15    the critical design characteristics and then go through a
         16    validation process.
         17              Of interest, and we will discuss it later, is the
         18    fact that eight of the analysis, that it will impact or need
         19    to be reviewed as part of the tier 2, have been
         20    self-identified by the licensee, that require re-performance
         21    and so that is going to -- we will discuss that slip to the
         22    schedule later.
         23              Our tier 3, again, is a historical review, and, as
         24    I had mentioned, that takes us back numbers of years, and we
         25    are doing that in five year increments to look at their
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         119
          1    ability to continue to assess the adequacy of the CMP.
          2              You asked earlier, Chairman Jackson about any
          3    changes that we might have had, and, although this was not a
          4    normalization based upon a sample, some of the things that
          5    we have seen in our tier 1 reviews have led us to propose
          6    some things to the staff saying that we have -- we will have
          7    seen enough in some areas that we can propose limiting, if
          8    not eliminating, some of the samples done in their
          9    particular tier.
         10              Moving to the overall tier status, I would like to
         11    tell you the first thing we have done is we have focused our
         12    reviews starting off with the high pressure safety injection
         13    system, tier two and tier three, so that we can prepare for
         14    the staff's implementation audit which is applied to the
         15    approved audit plan.  Last week, that audit was completed
         16    successfully and so, as you see, the numbers for HPSI in
         17    tier two and tier three are reasonably focused in those
         18    directions.
         19              I would also point out by doing one system in tier
         20    one, that has allowed us not only to do the deep vertical
         21    slice but it allows us to branch into a related system so
         22    that the baselines for the programs that support all systems
         23    will be evaluated as the work that we do in the
         24    high-pressure safety injection.  So that as we move forward,
         25    we will have gotten the baseline requirements for all those
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         120
          1    19 major topical areas in the plant complete so that we
          2    expect, if you will, I won't say it was a pilot but it will
          3    essentially function as a pilot for us to move ahead more
          4    rapidly in the other areas.
          5              CHAIRMAN JACKSON:  So this all relates to Unit 2?
          6              MR. CURRY:  Yes, ma'am.
          7              CHAIRMAN JACKSON:  Is the unit doing better than
          8    you expected?  In terms of moving along and completing --
          9              MR. CURRY:  I think, and we have identified and
         10    had meetings with the licensee and the staff on that. 
         11    Because of the age, issue of retrieval of documents has been
         12    significant and certainly the process by which we are
         13    independent of the licensee makes it such that you would ask
         14    for information and maybe it doesn't come back complete so
         15    you must ask for something else.
         16              And we have been working through a process that we
         17    have included now formal conferences twice a week which I
         18    think, all parties would agree, have tended to aide that
         19    process so we can say, when you send us the answer to this
         20    REI, make sure that you include something that deals with
         21    this.  And I think we would all agree that it has been a
         22    learning process of how to retrieve documents on a plant of
         23    this age.
         24              And also a priority between the Unit 3 plant and
         25    Unit 2.  As you can imagine, there is a focus.  And they
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         121
          1    have assured me that they love me but not necessarily am I
          2    the first one in their heart.
          3              CHAIRMAN JACKSON:  At least you're loved.
          4              MR. CURRY:  Well, as was previously mentioned,
          5    maybe some days it wanes up and down.
          6              On AFW, if I could comment about that, early on
          7    one of the reasons we did focus with HPSI is the fact that
          8    the licensee had self-identified that there were significant
          9    modifications to be done that would affect the main steam
         10    line break and the loss of coolant accident analysis.  And
         11    rather than trying to be inefficient and jump back and forth
         12    from changes they might be making, we decided it would be
         13    more efficient to focus on that one particular system and
         14    proceed directly.
         15              As you see, our current schedule for a final
         16    report is now April 7.  Again, part of that depends upon
         17    completion of corrective actions, completions of DRs and,
         18    particularly, also some completions of the things they have
         19    to do with AFW for us to be able to complete our review.
         20              Our Unit 2 discrepancy report status is, of
         21    course, they are much less mature from a numbers standpoint. 
         22    As you see, all the confirmed DRs in our particular case,
         23    although the percentage is about the same, they are all
         24    level fours right now and they are -- it would be too early
         25    for me to try to draw a conclusion based upon what I see on
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         122
          1    their responses from level fours.
          2              We do now presently have about 118 in progress,
          3    132 have been posted on the web and, much as Sargent &
          4    Lundy, we are working through that process.
          5              CHAIRMAN JACKSON:  Any other questions?
          6              Okay, thank you very much.
          7              We will now hear from Little Harbor Consultants.
          8              Mr. Beck, you are leading the discussion?
          9              MR. BECK:  Thank you, Chairman Jackson.  Good
         10    morning, Commissioners.
         11              I am John Beck, President of Little Harbor
         12    Consultants and team leader for the Independent Third Party
         13    Oversight Program at the Millstone site.  With me this
         14    morning is John Griffin, who is my co-team leader, and
         15    Ms. Billie Gard, who is a principal on our team.
         16              As you are aware, Little Harbor has the
         17    responsibility to oversee Northeast's efforts to establish a
         18    safety-conscious work environment at Millstone.  We have
         19    been acting in this capacity since approximately March of
         20    this year.  During this time, we have reported our findings
         21    to Northeast and your staff at eight public meetings. 
         22    Little Harbor has maintained essentially a full-time
         23    presence at Millstone, typically with five or six team
         24    members at the site, depending on the requirements of the
         25    particular oversight activities that were being conducted.
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         123
          1              Our next major activity will be to conduct a
          2    second round of structured interviews with the work force at
          3    the Millstone site.  This will add a set of data points to
          4    those which we gathered last June.  The purpose of the
          5    interviews is to determine how people at Millstone feel
          6    about all facets of a safety-conscious work environment. 
          7    Those to be interviewed will be chosen by Little Harbor to
          8    be representative of the work force and will be a different
          9    set of people from those interviewed in June.  The results
         10    will be available prior to the anticipated Commission vote
         11    and we will also continue our oversight of the various
         12    Northeast programs supporting a safety-conscious work
         13    environment with a particular emphasis on the effectiveness
         14    of these programs.
         15              CHAIRMAN JACKSON:  Let me ask you some overarching
         16    questions.  And if you are going to get into them with your
         17    specific slides later, please say so.
         18              The first is, have you sensed or detected an
         19    improvement in leadership on site as the leadership
         20    assessment that the licensee spoke about indicates?  And, if
         21    so, or if not, you know, what specifics support your
         22    conclusion?
         23              MR. BECK:  We are going to have some specific
         24    comments that will directly address that question about
         25    leadership, particularly with respect to the criteria
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         124
          1    relating to retaliation and so forth.
          2              But, in general, I would say that there has
          3    clearly been an improved understanding by the management
          4    team at Millstone, vis-a-vis a safety-conscious work
          5    environment, particularly over the last three months.  And
          6    we can perhaps illustrate that better in a few minutes.
          7              John, would you like to add?
          8              MR. GRIFFIN:  No, I agree.
          9              CHAIRMAN JACKSON:  Do you find that employee
         10    concerns rise as Millstone nears its deadline with the steep
         11    work-off rates?  Is there any detectable change?
         12              MR. BECK:  There has been a slight increase in
         13    December over the month of November.  But I wouldn't
         14    particularly associate that with approaching a deadline. 
         15    That is always a question.  What do the numbers, in and of
         16    themselves, mean.  Frankly, we are far more interested in
         17    looking at the issues that are involved and looking at the
         18    quality of those concerns.  And, in particular, with respect
         19    to any questions of retaliation or 50.7 issues.
         20              One of the questions you raised earlier, and
         21    perhaps I can respond to it now, was with regard to the
         22    correlation between the corrective action program and
         23    employee concerns issues.  If I heard you correctly, we have
         24    not, for example, none of us can recall a technical issue
         25    that went to ECP that had not already been a CR and the
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         125
          1    concern was either unsatisfactory resolution of the CR by
          2    the management team or untimely resolution of the CR and
          3    that's not a --
          4              CHAIRMAN JACKSON:  Not that it wasn't addressed?
          5              MR. BECK:  Not that it was not addressed.
          6              CHAIRMAN JACKSON:  Do you have a way of measuring
          7    or of detecting the overall stress on the managers and the
          8    employees?  Do you have experience with other sites to make
          9    a comparison?
         10              MR. BECK:  Being on site essentially full time, we
         11    cannot help but have our finger on the pulse of the
         12    organization.  The stress levels we have seen ebb and fall
         13    or rise and fall depending on particularly what's going on
         14    and who's affected by it.  It is certainly not an unexpected
         15    phenomenon to see people, when they are working as hard as
         16    they are, show some signs of stress.  I have seen on the
         17    part of management a recognition that this is a fact of life
         18    and some pretty careful attention being paid to stress in
         19    general.
         20              For example, if you go back to the MOV incident,
         21    there was a lot of stress in that organization prior to the
         22    retaliatory action that was taken.  The stress level, in our
         23    opinion, subsequent to that change in management, in the
         24    group, although they are working very hard, appears to have
         25    diminished somewhat.
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         126
          1              CHAIRMAN JACKSON:  Okay, why don't you go on.
          2              COMMISSIONER DICUS:  If I may ask a quick
          3    question?
          4              CHAIRMAN JACKSON:  I'm sorry.  Go ahead.
          5              COMMISSIONER DICUS:  This round of interviews that
          6    you have scheduled for February.  What is the sampling size?
          7              MR. BECK:  we are going to sample approximately
          8    280 to 300 individuals and they will be chosen across the
          9    organization and up and down, excluding directors and above
         10    in this particular case.
         11              COMMISSIONER DICUS:  Is that about the same
         12    sampling size?
         13              MR. BECK:  Yes, it will be.
         14              CHAIRMAN JACKSON:  Okay.
         15              MR. BECK:  There have been -- slide number
         16    3 -- two events at Millstone since our last meeting for
         17    which we performed an independent investigation per the
         18    provisions of our oversight program.  The first involved
         19    potential retaliation against contractors in the MOV
         20    department by their immediate management who also happened
         21    to be contractors.  The second incident involved an
         22    allegation of retaliation claimed by one of the individuals
         23    disciplined by Northeast as a result of the training
         24    department investigation.
         25              In the first instance, we verified and agreed with
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         127
          1    the conclusions reached by the company investigation of the
          2    ECP investigators of the MOV issue that retaliation was, in
          3    fact, a factor in the termination of two contract engineers. 
          4    In the second case, we concluded that there was no evidence
          5    of retaliation by Northeast management in the disciplinary
          6    actions that they took.
          7              Moving on to our evaluation of Northeast's
          8    progress, with respect to establishing a safety conscious
          9    work environment, our oversight plan contains 11 attributes
         10    which we think are critical to an ideal safety-conscious
         11    work environment.  Since the plan was published in June, we
         12    have added another attribute to cover incidents related to
         13    harassment, intimidation, retaliation or discrimination.
         14              Little Harbor continuously monitors these
         15    attributes through interviews, reviews, investigations and
         16    observations.  As information dictates, the Little Harbor
         17    team members working in a particular area meet to discuss
         18    data and reach consensus for relative attributes.  As
         19    changes occur in the future, we will communicate these
         20    changes to the NRC staff, Northeast Utilities and the
         21    public.
         22              CHAIRMAN JACKSON:  What was the additional
         23    attribute that you --
         24              MR. BECK:  It relates to the question of
         25    harassment, intimidation, retaliation and/or discrimination,
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         128
          1    specifically.
          2              CHAIRMAN JACKSON:  And how do you weight the -- do
          3    a relative weighting?  You talk about doing program reviews,
          4    interviews and then you have these attributes.  How do
          5    you -- is it you have a weighting system or you do one to
          6    kind of check the other?
          7              MR. BECK:  Some of them are relatively
          8    straightforward and simple and it is easy to make the
          9    evaluation.  Others involve a lot of subjective evaluation,
         10    discussion by the team members who are involved in various
         11    reviews or investigations and that consensus reaching demand
         12    which we place on ourselves results in the weighting taking
         13    place.
         14              As we -- and I will go into later -- roll up our
         15    12 attributes, if you will, to be consistent with the four
         16    that you heard from the company on earlier this morning, you
         17    will see how they --
         18              CHAIRMAN JACKSON:  Stack up?
         19              MR. BECK:  Yes.
         20              This next slide shows our approach to evaluating
         21    the status of Northeast's safety-conscious work environment
         22    implementation efforts.  And I will relate that to your
         23    desire for satisfactory approaching expectations and not
         24    meeting them in a moment.  We have chosen to use five
         25    gradations for evaluation of each Little Harbor attribute or
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         129
          1    roll-up to end use success criteria.
          2              Green meets all expectations.  Red, on the other
          3    hand, requires significant improvement.  And we use three
          4    levels within the yellow band, as indicated on the slide.
          5              We also evaluate our view of the current
          6    performance trend for each attribute as indicated by an
          7    arrow in the box.  It is the consensus of the Little Harbor
          8    team that each of the four Northeast success criteria, which
          9    you heard discussed by the Company this morning, must be
         10    rated neutral yellow or better to be considered ready for
         11    restart of the unit at Millstone.  Therefore, if you drew a
         12    line below neutral yellow, a horizontal arrow, above that
         13    line, you would have to be at that point or above to be
         14    satisfactory.
         15              The next slide, the status reports which we will
         16    be sharing in a moment are based on our evaluation of
         17    progress to date.  Little Harbor opinions are based on our
         18    initial structured interview results, initial reviews of the
         19    employee concerns program and corrective action program and
         20    other activities.  We are continuing our review of the
         21    comprehensive plant effectiveness, another round of
         22    structured interviews, closure of our employee concerns
         23    program and corrective action program reviews and continued
         24    observations of site activities.
         25              I am not going, due to the limited time available,
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         130
          1    to go through each of our 12 attributes but rather focus on
          2    the four end use success criteria this morning.  We did
          3    include those other evaluations in our advance package,
          4    however.  If you have any questions about any of these, we
          5    would be pleased to respond.
          6              Going to the first end use success criteria,
          7    willingness to raise safety concerns, we rate this
          8    satisfactory today, a neutral yellow with a holding steady. 
          9    It is based on a roll-up of our attributes 2, 6, 7, 9 and
         10    12, which were in your advanced package.
         11              While there continue to be some problem areas at
         12    Millstone, we believe that this attribute has improved and
         13    workers at Millstone are willing to raise safety concerns
         14    via one of the available mechanisms.  Resolution of the
         15    existing problem areas coupled with the ongoing training of
         16    the work force should provide further improvement in this
         17    criteria in the future.
         18              The next criteria, issues are effectively resolved
         19    by line management, which is really the corrective action
         20    program, is also evaluated as neutral yellow but with an
         21    improving trend.  It is based on our attribute number 10 and
         22    the evaluation of it, the corrective action program which we
         23    reported on in September.  We performed a comprehensive
         24    review of the program and completed it as I said in
         25    September.
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         131
          1              We concluded that Northeast has established an
          2    excellent corrective action program which is being
          3    aggressively implemented.  Our continuing review in this
          4    area will focus on the effective resolution of problems
          5    addressed by the program.
          6              The next area, effectiveness of the ECP, we do not
          7    consider to be satisfactory today.  It is a minus yellow
          8    with an up arrow.  And it is identical to our attribute
          9    number 11.  Northeast, however, has made significant strides
         10    in improving the employee concerns program.  We feel that
         11    this rating would be up at least one notch to neutral
         12    yellow, improving or satisfactory, but for the apparent high
         13    percentage of persons who have used the program and who
         14    indicate that they wouldn't use it again.
         15              We are not satisfied today that we totally
         16    understand why users of the employee concerns program feel
         17    this way and will develop that understanding over the next
         18    few weeks.  Thus, our conservative rating at this time.
         19              Overall, we feel that NU management and the
         20    employees and contractors in the employee concerns program
         21    have made significant strides over the next few months and
         22    the program is continuing to improve but for that one
         23    aspect.
         24              And, finally, the last NU success criteria,
         25    recognizing and dealing with harassment, retaliation,
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         132
          1    intimidation or discrimination we rate as red today.  This
          2    is a roll-up of our attributes 3, 4, 5, 8 and 9.  The
          3    sources of input were the Little Harbor reviews of end
          4    process training, observations in the work place, specific
          5    investigation of Millstone incidents, employee concern
          6    follow-up interviews, validation of comprehensive action
          7    plan action items and walk-in interviews.
          8              I should add that we have observed positive
          9    movement by Northeast management in this area very recently. 
         10    Some examples include the 10 CFR 50.7 training effort which
         11    you saw as in progress.  We were involved in communicating
         12    our expectations of such a program while it was being
         13    developed.  We have monitored the training sessions as they
         14    are under way and we think it has significant potential to
         15    raise the level of awareness from first line supervisors up
         16    within the Northeast management chain.
         17              We also have witnessed some behavior on the part
         18    of management responses to recent issues involving potential
         19    retaliatory behavior and it has been very positive and
         20    significantly better than it had been in the past.  The
         21    consolidation and addition of management resources under
         22    Mr. Brothers regarding all matters associated with a
         23    safety-conscious work environment at Millstone we think is a
         24    very positive step and is beginning to show positive
         25    results.
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         133
          1              That concludes our prepared remarks.
          2              In summary, we have seen improvement in the last
          3    few months with respect to the safety-conscious work
          4    environment.  The employee concerns program in particular
          5    has made significant strides but requires some effort to
          6    improve the perception of its users.  The most difficult
          7    task facing Northeast management is clearly the need to
          8    improve its performance with respect to harassment or
          9    potential retaliatory actions in the work place.  We are
         10    going to in particular monitor very closely these areas.
         11              We would be pleased to respond to any questions
         12    you may have.
         13              CHAIRMAN JACKSON:  The first one is an
         14    informational one.  I didn't take down the roll-up.  If you
         15    go back through the 1, 2, 3, 4, tell me how your criteria
         16    roll up into the different ones.
         17              You're saying that NU's Criteria 1 is a
         18    combination of which ones of yours?
         19              MR. BECK:  Their Criteria 1 involves our Criterion
         20    2, which is employee perceptions of the policy that NU has
         21    established for a safety-conscious work environment.
         22              CHAIRMAN JACKSON:  You can just give me the
         23    numbers.
         24              MR. BECK:  Okay, I'm sorry -- 2, 6, 7, 9, and 12.
         25              CHAIRMAN JACKSON:  Okay, and number 2?
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         134
          1              MR. BECK:  Number 2 is number 10.
          2              CHAIRMAN JACKSON:  Okay.
          3              MR. BECK:  Number 3 is number 11.
          4              Number four is three, four, five, eight, and nine
          5    again.
          6              CHAIRMAN JACKSON:  No, I appreciate your doing
          7    that grouping, but essentially what you are saying is that
          8    the ability to grapple with alleged instances of harassment,
          9    intimidation, retaliation or discrimination -- they really
         10    have a long way to go yet, and then the very thing that is
         11    the subject of your existence, namely the Employee Concerns
         12    Program and its effectiveness they have some improvements to
         13    make.
         14              MR. BECK:  That's correct.
         15              CHAIRMAN JACKSON:  Okay.  All right.  Are there
         16    any additional questions?  Yes?
         17              COMMISSIONER DICUS:  In the presentation that
         18    Northeast Utilities made on their program they analyzed
         19    themselves and they indicated, as you are well aware, that
         20    you concurred with where they felt they stood in the issues
         21    that they were dealing with with the program.
         22              Do you concur completely or is there an area, a
         23    significant area not a minor area, a significant area where
         24    maybe you don't concur with their own analysis?
         25              MR. BECK:  If I may, Commissioner, I interpreted
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         135
          1    that "LAC concurs" as another criteria they are setting for
          2    themselves.
          3              Today we do agree on those four elements, namely
          4    the first two are satisfactory, the last two are not today,
          5    so we are in synch at this point in time.
          6              CHAIRMAN JACKSON:  Okay.  Thank you very much.
          7              Now we will hear from the NRC Staff -- last but
          8    not least.
          9              MR. THOMPSON:  Good afternoon.
         10              CHAIRMAN JACKSON:  Yes, I guess it is.  Good
         11    afternoon.  You sure it is not tomorrow?
         12              MR. THOMPSON:  Chairman Jackson, Commissioners, as
         13    you know, this is an effort that the NRC Staff has put a
         14    major focus on.  This is our fourth presentation and I think
         15    you know the gentlemen at the table with me.
         16              Before I turn it over to Bill though, I would like
         17    to indicate that we are recognizing the importance of where
         18    we are in this program -- I'm sorry --
         19              CHAIRMAN JACKSON:  We know who you are.
         20              MR. THOMPSON:  We have our tent cards here.
         21              Before we get to having Bill go through and
         22    summarize what we believe are the important elements of our
         23    0350 process, and that is our restart assessment program, I
         24    would like to indicate that this is a time we recognize that
         25    there are lots of activities that are ongoing at the site. 
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         136
          1    There are a lot of activities that the Staff will be doing
          2    at the site and we need to keep the Commission currently
          3    informed of those programs and previously we had given
          4    reports on kind of a quarterly basis, but we think it is
          5    important that we do that more on a monthly basis now.
          6              The next report we believe would be in January and
          7    it would obviously be toward the middle or the end of
          8    January, depending on the site activities but it is part of
          9    the process that we need to keep you currently informed of
         10    the status and we intend to do that and with those brief
         11    remarks I would like to turn it over to Bill, who will hit
         12    the highlights of some of our activities as well as address
         13    your concerns with an overall summary of where we are with
         14    our evaluation of the status.
         15              CHAIRMAN JACKSON:  Thank you.
         16              DR. TRAVERS:  Good afternoon.
         17              My first slide simply presents an overview of what
         18    I would like to cover.  It is very similar to the topics
         19    that we have touched on in previous briefings.
         20              I'll move right on.  In the second slide I'll
         21    mention that the Special Projects Office was formed just
         22    about one year ago, just one year and one month ago, to
         23    focus on the Millstone issues and we have been continuing to
         24    implement the Millstone review plan that we described to the
         25    Commission in SECY 97-003.
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         137
          1              Of course we have based our plan on Manual Chapter
          2    0350, which provides the guidance that we typically use to
          3    assess the restart status of plants that are facing
          4    troubles, and we have at Millstone developed Restart
          5    Assessment Plans for each of those units.
          6              I have indicated in bulletized form the principal
          7    elements, so I am going to touch on probably each one of
          8    those.  I have some, more in detail in some than others, but
          9    this listing includes the principal areas that we have
         10    identified as those issues which we expect to identify
         11    improvements and issue resolution prior to coming to the
         12    Commission for an ultimate decision on restart of any of the
         13    three units.
         14              An important element that I would like to mention
         15    right upfront, and we have been doing this in the past, of
         16    our program is the fact that we have a commitment up in the
         17    Millstone area to make our process a very public and open
         18    one.
         19              We think we have been meeting that by virtue of a
         20    number of activities that we have been carrying out that are
         21    somewhat extraordinary, somewhat above the norm.
         22              Just mentioning a few of those, we have continued
         23    to brief the public in evening sessions every four to six
         24    weeks or so.  We have been carrying out most of the
         25    technical exchanges that we have had with the utility in
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         138
          1    public forums at the Millstone site or near the Millstone
          2    site such that those meetings are observable to members of
          3    the public.
          4              We have had a very close working relationship, a
          5    continuing one, with the State of Connecticut Nuclear Energy
          6    Advisory Council.  You may recall that we have an agreement
          7    with the Council to participate at least as observers in our
          8    conduct of ICAVP design basis, licensing basis verification
          9    activities, and they have been expending quite a lot of
         10    effort to participate with us, observe our process and
         11    provide their own sense of how we are carrying out our
         12    activities in their own public meetings.
         13              So those are sort of the principal elements of our
         14    public -- I'll call it outreach program for lack of a better
         15    term.
         16              Before I turn to a more detailed discussion of
         17    some of the elements that we have listed in our Restart
         18    Assessment Plan, I would like to tell you that our overall
         19    assessment is that the licensee is continuing to make
         20    progress in their efforts to bring about needed change at
         21    Millstone.
         22              Led by essentially a new Senior Management team
         23    since late 1996, NU has initiated a rather broad scoped
         24    effort to identify problem areas and to implement corrective
         25    actions.
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         139
          1              Although progress has not kept pace with the
          2    licensee's initial schedules, our oversight program is
          3    identifying improvements in essentially all of the elements
          4    of our NRC Restart Assessment Plans for Units 3 and 2.
          5              Despite this progress, I think it is important to
          6    point out that NU has not yet completed some significant
          7    work.  You have heard enough about that.  We will talk some
          8    more about it as well.
          9              As a result though, a number of our most important
         10    inspections have not yet taken place.
         11              For example, of a total of eight team inspections
         12    that are planned at Unit 3, two are complete, two are in
         13    process, and four are planned.
         14              Examples of some of the planned inspections
         15    include ones which will assess corrective actions, work
         16    planning and control, quality assurance, and the operational
         17    readiness of both the plant and operations personnel.
         18              These NRC evaluations are necessarily focused in
         19    the latter stages of the licensee's improvement program and
         20    we are planning to initiate a number of inspections
         21    following the licensee's own determination that they are
         22    ready.
         23              I think it is fair to say thus far that our
         24    planning for the conduct of our own verification activities
         25    has not resulted in delays.  We have been pretty efficient
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         140
          1    at rescheduling in the face of some of the slips that have
          2    occurred in their schedule and the necessity of rescheduling
          3    some of the important team inspections.
          4              With that as an overview, let me turn to some of
          5    the specifics.
          6              DR. TRAVERS:  The next slide provides a listing of
          7    the significant items list.  That list, which is a portion
          8    of our restart assessment plan, contains a detailed listing
          9    of both the programmatic and specific issues that we have
         10    identified for each unit that we think are important for
         11    resolution before we come to the Commission.
         12              To facilitate our review, NU is providing us with
         13    packages or submittals that address each of the -- or most
         14    of them, most of the significant items list.  Some of the
         15    issues do not require packages and we are handling those
         16    without.  But this rack-up includes the total number of the
         17    SIL items identified at unit three, for example, is 86.  The
         18    number of packages, and these -- this number specifically
         19    addresses the number of completed -- complete packages as
         20    58.  And the fact that at Unit 3, at least, to date, we have
         21    closed 30 of those.
         22              This chart, the more I thought about it, the more
         23    I think about it, does not provide a very good indication of
         24    the overall status of where we stand in carrying out our
         25    assessment at Unit 3 particularly, in that because of the
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         141
          1    fact that we are getting and have reviewed, in fact, a
          2    number of partial submittals of packages, we would estimate
          3    that the percent completion is closer to about 70 percent
          4    and that really is not -- this slide could throw you off
          5    from that considerably if you didn't know the fact that we
          6    are reviewing partial submittals, we have closed a number of
          7    those at least in part.
          8              CHAIRMAN JACKSON:  How are you documenting staff
          9    review and closure of the SIL items?
         10              DR. TRAVERS:  Each of the significant items that
         11    are identified here as closed, and the future items as well,
         12    are being identified and documented in NRC inspection
         13    reports.  The reason I haven't added the fact that we have
         14    closed an additional 10 at Unit 3 is because we haven't
         15    issued the inspection report yet that will in fact document
         16    our closure of those items.
         17              CHAIRMAN JACKSON:  Okay, so that's the fundamental
         18    documentation?
         19              DR. TRAVERS:  Yes, that's right.
         20              CHAIRMAN JACKSON:  And what issues on this list do
         21    you believe pose the greatest challenge for the licensee at
         22    this stage?
         23              DR. TRAVERS:  I think you are going to hear
         24    something similar to what's been said already but let me
         25    take off what I see as the most significant challenges that
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         142
          1    lie ahead.  In the area of safety conscious work
          2    environment, we have heard from Little Harbor and we are
          3    certainly relying on their expertise to a great extent, that
          4    focus on the need for substantial improvement in the area of
          5    HIRD issues and we concur with that.
          6              We have also identified some issues that I am
          7    going to be discussing in a minute related to the
          8    verification of design basis/licensing basis issues.  We see
          9    that as a challenge.
         10              We see the corrective action program, at least our
         11    assessment of it, as adequate to be a challenge.  We
         12    have -- I don't want to mislead you about the future
         13    inspections that we have planned.  They are certainly
         14    important.  We have, although relying on those to a great
         15    extent in the future, been carrying out assessments in all
         16    of these areas and we have, as I indicated generally,
         17    identified improvements in even the area of corrective
         18    actions.  But if you look at backlogs, if you look at the
         19    physical modifications that are still required to be
         20    completed before restart, certainly these pose a number of
         21    challenges for this utility.
         22              I also agree with what Mr. Kenyon said about the
         23    importance of the transition to an operating state.  These
         24    plants have been shut down two years or more or less in some
         25    cases.  But it is an awfully long time and an important
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         143
          1    aspect of what they have to accomplish is to move into a
          2    period where they can establish an operational confidence
          3    that translates into safe operations.
          4              CHAIRMAN JACKSON:  Let me ask you this question
          5    now.  You have identified as, you know, among the greatest
          6    challenges, the backlogs and physical modifications.  But
          7    when we heard from the licensee, they were indicating, at
          8    least for Unit 3, that they expected to have -- you know, be
          9    physically ready at the end of the month.  And so how do you
         10    square those two?
         11              DR. TRAVERS:  Well, they may very well be.  But as
         12    I look at the data, I look at it the same way as you.  I'm
         13    sort of in a "show me" mode.  I think that's less important,
         14    frankly, than doing it right.  But, nevertheless --
         15              CHAIRMAN JACKSON:  I understand.
         16              DR. TRAVERS:  -- we understand what you've been
         17    told by NU and we think we understand, for example, that
         18    many of the items that they have to complete are simply
         19    lacking some element as, for example, testing.  So many of
         20    these may fall in rather quick succession.
         21              But by virtue of the numbers not falling for so
         22    long, we are sort of in a conservative mode and want to list
         23    that as an example of something we think is a challenge
         24    still.
         25              CHAIRMAN JACKSON:  Thank you.
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         144
          1              DR. TRAVERS:  Sargent & Lundy and Parsons have
          2    given you a summarized version of their activities and under
          3    the ICAVP order, the NRC staff is carrying out related but
          4    independent activities as well, as you know.  And we wanted
          5    to list several of the activities that have been completed
          6    since last we met with the Commission and they are included
          7    on this slide.
          8              The first item has to do with the fact that we
          9    carried out a team inspection to evaluate the implementation
         10    of Sargent & Lundy of its NRC approved audit plan for the
         11    conduct of their activities.  Our findings were generally
         12    positive.  We did note in our inspection that when we went
         13    in, it was fairly early.  We didn't have an opportunity to
         14    review everything we would have liked to at that time.  But
         15    we will have an opportunity in our subsequent tier two and
         16    three inspections.
         17              So we have completed this inspection.  We have
         18    generally found positive results.  Those minor findings that
         19    were identified have been acted on by Sargent & Lundy and
         20    corrected, in our view, and we still have an opportunity and
         21    we expect to exercise that as we carry out some of our
         22    remaining team inspections.
         23              CHAIRMAN JACKSON:  So when you say then that it
         24    was completed, you mean it was completed relative to what
         25    there was for you to inspect at that point?
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         145
          1              DR. TRAVERS:  That's exactly right.
          2              CHAIRMAN JACKSON:  But there are some additional
          3    inspections you would have to do?
          4              DR. TRAVERS:  We have been having an opportunity,
          5    as we have gone on, really, to have a pretty -- a very close
          6    understanding of the way Sargent & Lundy is carrying out its
          7    activities.  At the time this inspection was ongoing, they
          8    weren't there yet.
          9              CHAIRMAN JACKSON:  I see.  Okay.
         10              DR. TRAVERS:  The second bullet has to do with an
         11    inspection that has been referenced briefly here and I am
         12    going to cover it in my next slide but it fundamentally has
         13    to do with our first system, safety system functional
         14    inspection at Unit 3.
         15              Additionally, completed over this period is the
         16    fact that the Nuclear Energy Advisory Council selected the
         17    final two systems to be reviewed by Parsons at Unit 2.
         18              And, lastly, we have also, similar to the first
         19    inspection I mentioned, carried out a team inspection at
         20    Parsons of their implementation and, again, we found
         21    positive indications of their conformance with the
         22    NRC-approved audit plan.
         23              At Unit 3, the NRC staff has completed the first
         24    of two team inspections which involve a detailed evaluation
         25    of an important safety system.  These NRC inspections are in
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         146
          1    addition to the ICAVP reviews being carried out by S&L; with
          2    one inspection focusing on one of the systems being reviewed
          3    by S&L; and one system focusing on a system outside the scope
          4    of S&L;'s program.  The staff's first safety system
          5    functional inspection focused on a review of the emergency
          6    core cooling system mode of the chemical and volume control
          7    system.  And a number of issues were identified and
          8    documented in a recently issued inspection report, and I
          9    have listed the principal issues resulting from that.
         10              CHAIRMAN JACKSON:  But these appear troubling.  I
         11    mean should I be troubled?
         12              DR. TRAVERS:  I would characterize them as raising
         13    a concern, perhaps a fundamental concern, that we feel we
         14    can address in subsequent inspections by --
         15              CHAIRMAN JACKSON:  Would you say what that
         16    fundamental concern is?
         17              DR. TRAVERS:  The fundamental concern is, goes
         18    back to what the purpose of our verification inspections
         19    really are here.  A little while ago there was a question
         20    about where Millstone is, or maybe where it was, relative to
         21    industry standards.  What we have, and are dealing with now,
         22    is a situation where we have asked, by virtue of a number of
         23    problems that were identified several years ago, for
         24    Northeast to go in and carry out a very rigorous assessment
         25    of their licensing and design basis.
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         147
          1              They have completed, essentially completed that
          2    program, and we are now coming in at the end of that. 
          3    Sargent & Lundy, NRC staff, Parsons at Unit 2.
          4              The question that the findings raise, and I don't
          5    think they answer, is whether or not the licensee's program
          6    for identifying on its own where they stand, relative to
          7    licensing basis and design basis, was adequate, and whether
          8    or not we should rely on it by virtue of the sampling
          9    program that looks at a very limited, or somewhat limited,
         10    set of systems.
         11              CHAIRMAN JACKSON:  Because of the findings in your
         12    out of scope SSFI?
         13              DR. TRAVERS:  That's right.
         14              CHAIRMAN JACKSON:  Commissioner.
         15              COMMISSIONER McGAFFIGAN:  Did you intentionally
         16    not adopt the same vocabulary as Sargent & Lundy, and
         17    Parsons, with regard to level -- the levels?  How would you
         18    assign these issues to the levels that the contracts are
         19    using?  Are these level 3's, are they level 4's, are they --
         20    what are they?
         21              DR. TRAVERS:  Well, I should point out that they
         22    are preliminary findings at this point, and -- but they
         23    potentially could be --
         24              COMMISSIONER McGAFFIGAN:  Level 1's?
         25              DR. TRAVERS:  Level 1, the first one at least.
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         148
          1              COMMISSIONER McGAFFIGAN:  At least the first one,
          2    sure.
          3              DR. TRAVERS:  But the reason I say they are
          4    preliminary is because we have identified them with the
          5    team.  We will be attending an enforcement conference,
          6    because of the significance of this issue, with the licensee
          7    in January.  And, at that time, they will have an
          8    opportunity to provide us some additional information on
          9    what -- what they think the issue is or isn't, and what they
         10    are doing about it.
         11              Now, we have heard today, and we have heard before
         12    today, that they have implemented a number of activities
         13    that are directed at addressing this issue, not just in this
         14    system, but across the 88 maintenance one and two systems
         15    that were covered in their own program.
         16              So that's why I say I don't think this finding,
         17    and where we are at today, answers the question that has
         18    been raised.  And rather than suggest to you that it does,
         19    what I would suggest is what we intend to do as follow-on to
         20    pursue this fundamental question and, that is, simply to
         21    evaluate the information that the licensee provides to us,
         22    in whatever mechanism, whether it is the enforcement
         23    conference, or through whatever means, and to garner the
         24    information that we will obtain in three remaining team
         25    inspections that also, essentially, address the same issue,
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         149
          1    you know, whether or not we can rely on what was done as a
          2    good and rigorous assessment of licensing basis and design
          3    basis.
          4              CHAIRMAN JACKSON:  Yes.  Commissioner Diaz.
          5              COMMISSIONER DIAZ:  In other words, you believe
          6    that the remaining inspections should give you assurance
          7    that the Configuration Management Program of the licensee is
          8    adequate to not have this kind of problems in other safety-
          9    related systems?
         10              DR. TRAVERS:  I think it certainly will provide
         11    additional data for us to assess the overall question.
         12              CHAIRMAN JACKSON:  To make that judgment.
         13              DR. TRAVERS:  To make that judgment.  And since
         14    this is one of four, and if you recognize the very
         15    substantial effort that Sargent & Lundy is going through, we
         16    really think that we have to integrate all of that
         17    information before we make a conclusion.
         18              But -- excuse me.  But there is an indication, and
         19    even at this early stage, that, based on these findings,
         20    which we think were a good find on the part of our team, it
         21    was a very good team, very -- very capable people who were
         22    working on it, that the licensee has identified on its own a
         23    need to assess across the other systems whether or not the
         24    implications identified apply to those other systems.
         25              Now, they are going to be telling us more about
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         150
          1    that.  We have had some preliminary information.  I think
          2    they told you that activity is not complete yet.  So, we
          3    will certainly be interested in that information and include
          4    it in our assessment of the fundamental question.
          5              CHAIRMAN JACKSON:  Okay.  Thank you.
          6              DR. TRAVERS:  In the next three -- I didn't
          7    mention the other issue.  The first one is the most
          8    significant.  I will mention the second issue just briefly.
          9              CHAIRMAN JACKSON:  Let me make sure I understand
         10    something before --
         11              DR. TRAVERS:  Yes.
         12              CHAIRMAN JACKSON:  Is the licensee going to
         13    revisit, they are going to revisit their Configuration
         14    Management Program, or are they going to be waiting on the
         15    results of your other SSFI?
         16              DR. TRAVERS:  They are not waiting.  They are, in
         17    fact, carrying out analysis which, ultimately, may render
         18    the issue not to be very significant.  The question has to
         19    do with air entrainment and the possibility of binding of
         20    pumps.
         21              CHAIRMAN JACKSON:  Right.
         22              DR. TRAVERS:  But there is a possibility that when
         23    the analysis is conducted, that it is judged to not be
         24    significant.
         25              CHAIRMAN JACKSON:  Right.
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         151
          1              DR. TRAVERS:  But the expectation we would have
          2    had, of their program, is that they would have identified it
          3    and triggered the analysis.  So, as a minimum, that is what
          4    we see as --
          5              CHAIRMAN JACKSON:  So it is the identification of
          6    the issue, and the significance of that, as well as the
          7    significance the issue turns out to have in and of itself.
          8              MR. THOMPSON:  That's exactly right.
          9              DR. TRAVERS:  Yes.  That's exactly right.
         10              CHAIRMAN JACKSON:  Okay.
         11              DR. TRAVERS:  The last -- the second two issues,
         12    principal issues from that inspection finding, the second
         13    one has to do with an identification of the fact that tech
         14    spec requirements that should have resulted in a number of
         15    valves being tested for leak tightness, did not result in
         16    those valves testing.  And so that is an issue that they are
         17    looking a little bit more broadly at as well.
         18              And, lastly, we found a number of fairly minor,
         19    but nevertheless discrepancies from the as-found condition
         20    of the plant with the description in the FSAR.
         21              In the next three months, we expect to complete
         22    all of the remaining ICAVP inspection activities at Unit 3,
         23    and they are listed here as the tier 2 and tier 3 inspection
         24    which is underway, the Unit 3, tier 1, in scope inspection,
         25    our corrective action inspection at Unit 3, and we also
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         152
          1    expect, at Unit 2, to have completed the tier 1 out of scope
          2    system review and the tier 2 and tier 3.
          3              At Unit 2, three of five ICAVP inspections will be
          4    complete, we expect, within the next three months.
          5              An extremely important element of our restart
          6    assessment plan is the issue of Employee Safety Concern
          7    Program and safety conscious work environment, more broadly. 
          8    You have heard from Little Harbor, and, as a matter of fact,
          9    in this area, we are relying to a great extent on this
         10    independent contractor's expertise in assessing these
         11    issues.  The staff is, nevertheless, however, acting
         12    independently as well to assess the status of improvements
         13    in this area, and this slide is meant to give you a
         14    summarization of some of the activities that we have
         15    completed since last we met with the Commission.
         16              CHAIRMAN JACKSON:  Now, are the project officer,
         17    special project office managers and staff making any
         18    observation on a day-to-day basis as they go about in
         19    documenting those in any way?
         20              DR. TRAVERS:  Documenting, I think not.  But what
         21    we are certainly doing is observing and garnering a view in
         22    this area.
         23              But, as I was going to mention, in a formal sense,
         24    we are just this week --
         25              CHAIRMAN JACKSON:  You are going to develop a plan
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         153
          1    to assess what, the ECP?
          2              DR. TRAVERS:  We have actually developed a plan
          3    that we forwarded in the recent SECY.
          4              CHAIRMAN JACKSON:  SECY paper, that's right.  As
          5    well as the safety conscious work environment.
          6              DR. TRAVERS:  Exactly right.
          7              CHAIRMAN JACKSON:  Right.
          8              DR. TRAVERS:  And to a very great extent, the
          9    parameters that we are think are reasonable to assess these
         10    issues are the ones you have heard about today.  We don't
         11    have any suggestions for major changes.  We are looking at
         12    them on our own and, to the extent that we have had a
         13    continuing audit, a few personnel up at the site looking at
         14    these issues.  Just this week, we have implemented the first
         15    week of a two week on-site inspection team -- or on-site
         16    evaluation team, to assess both Northeast's progress and
         17    ECP, and, more generally, safety conscious work environment.
         18    But also to get a sense of the implementation of Little
         19    Harbor in conduct of its NRC approved audit plan.  You know,
         20    this is very similar to what we are doing, evaluating
         21    Sargent & Lundy and Parsons.
         22              CHAIRMAN JACKSON:  It is useful that, if your own
         23    folks are on kind of a -- you know, as you go about, you do
         24    have the opportunity to observe.  Typically, when people
         25    know there are inspections, there are various things.  And
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         154
          1    programs are as programs do.  You know, my mantra.  So --
          2              [Laughter.]
          3              COMMISSIONER DICUS:  Based upon these observations
          4    that you have, do you generally concur at this point with
          5    what Little Harbor and the licensee are saying?
          6              DR. TRAVERS:  Yes, we do.  Particularly, -- well,
          7    in just about everything Little Harbor said, they provided a
          8    very detailed assessment of the situation.  Improvements in
          9    the ECP program, for example, with needed improvements yet. 
         10    But a significant effort still remaining in the area of
         11    safety conscious work environment.  And we certainly do
         12    concur with that assessment.
         13              Now, we are going to be getting this week, and in
         14    our second team inspection week, a little bit better
         15    assessment, from our own perspective, on these things. 
         16    Right now we generally track with the findings you have
         17    heard from Little Harbor.
         18              I'll move to the next slide.  In the next three
         19    months, similar to what we have been doing, we expect to
         20    continue to monitor both the licensee and Little Harbor.  We
         21    are attending meetings that are again observable to the
         22    public to discuss these issues including some of the major
         23    missteps that have occurred, the MOV issue and so forth.
         24              We expect to carry out the second week of the team
         25    inspection that I mentioned at Unit 3.  This is really a
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         155
          1    site issue, by the way, even though today we are mostly
          2    focusing on Unit 3.  We believe that this issue certainly is
          3    one which needs to be considered in a site-wide sense.
          4              In addition to that focused team inspection on ECP
          5    and safety-conscious work environment and in recognition of
          6    the importance of effective corrective action programs, we
          7    are also going to include in our conduct of the 4500
          8    inspection, that inspection again focuses on the corrective
          9    action program, a particular focus on safety-conscious work
         10    environment and the resolution of concerns raised by
         11    employees.  So we think there is a good fit there to get an
         12    even better assessment of this issue in the context of that
         13    team inspection.  That is upcoming.
         14              Of course, we will continue to track the program
         15    measures that we have identified in our program planning.
         16              In the licensing arena, we have identified here
         17    sort of a rollup of a number of issues that have been
         18    identified as important, and the only thing I will say about
         19    this is that we believe today that based on what we have
         20    in-house and where we stand with these reviews that we don't
         21    see a major pitfall to March or April kind of a timeframe
         22    for our assessment and completion.
         23              In some cases some of these license amendments
         24    need to be done in January timeframe, I guess, to support
         25    Mode 4 operations.
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         156
          1              DR. TRAVERS:  Mode 4 operations.
          2              DR. TRAVERS:  But we don't see a major problem
          3    with what the licensee today thinks it can do by virtue of
          4    its programs.
          5              CHAIRMAN JACKSON:  The only question I really have
          6    in terms of your project planning schedule, which is the
          7    next slide -- I'm jumping ahead -- I see that in the -- all
          8    right.
          9              When you talk about these calendars, these
         10    quarters, and these are calendar year quarters --
         11              DR. TRAVERS:  Yes, they are.
         12              CHAIRMAN JACKSON:  For instance, I note that you
         13    have, you know, a Commission briefing, this is for Unit 2 --
         14              DR. TRAVERS:  Oh -- Unit 3 I think is scheduled
         15    similar to the --
         16              CHAIRMAN JACKSON:  Well, yes, the schedules are
         17    basically similar except that what is on the planning
         18    schedule tracks a little bit more.
         19              I am looking, for instance, at license amendments
         20    for Unit 2, and you have those tracking all the way out
         21    till -- you know, in the summer.
         22              I guess --
         23              MR. THOMPSON:  In May, end of May.
         24              CHAIRMAN JACKSON:  End of May, so you nonetheless
         25    feel that this is a reasonable tool to support the projected
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         157
          1    Commission briefing in June of '98 --
          2              DR. TRAVERS:  With a caveat, always a caveat, and
          3    that caveat simply is that we recognize the possibility in
          4    the midst of some of the discovery that still is continuing
          5    of the need for as yet an unidentified license amendment.
          6              CHAIRMAN JACKSON:  The only reason I raised that
          7    one, particularly for that plant, is because that is the
          8    older one, where there could be some more design basis
          9    issues --
         10              DR. TRAVERS:  Exactly.
         11              CHAIRMAN JACKSON:  -- that might arise, but okay,
         12    that's fine.
         13              Any other questions?  Comments?  Commissioner?
         14              COMMISSIONER DIAZ:  As the planned start is
         15    getting toward restart and you look at the amount of
         16    resources that we have in Millstone, are you planning to
         17    start phasing out some of those resources into other needs,
         18    or is there a schedule being made of --
         19              MR. THOMPSON:  We are looking at that very closely
         20    right now.  Obviously, we have the resources available. 
         21    It's a very important time that we make sure that we have
         22    the resources available to accomplish it.
         23              Likewise we also look at the operating plant and
         24    we go through and update that, so we will be looking at
         25    those elements and giving back to the Commission, if we see
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         158
          1    a need, to change, increase, decrease or whatever the
          2    appropriate aspect is with respect to those resources, so we
          3    recognize that is a very important element for us to be
          4    sensitive to and to communicate with the Commission on.
          5              CHAIRMAN JACKSON:  Right.  Thank you.
          6              I would like to thank Northeast Utilities, Sargent
          7    & Lundy, Parsons Power, Little Harbor Consultants, and of
          8    course the NRC Staff for briefing the Commission on the
          9    progress in assessing the readiness for restart of the
         10    Millstone units.
         11              Once again I will state on behalf of the
         12    Commission that we recognize how difficult it is, as you can
         13    see from some of our own questions, to condense the
         14    substance of the reviews performed by each of the groups
         15    into briefings like this.  That is why it has been a
         16    marathon session, but this is the primary reason, of course,
         17    that the NRC in November of last year created the Special
         18    Projects Office headed Dr. Travers and to provide for direct
         19    oversight of all licensing and inspection activities and to
         20    tailor the manual chapter 0350 process to specifically
         21    address the issues at these units.
         22              So I was going to ask, but Mr. Thompson, you in
         23    fact preempted me, that the Special Projects Office keep the
         24    Commission informed on a more timely basis, and what you are
         25    suggesting about the monthly reports sounds reasonable.
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         159
          1              I believe the next Commission meeting should be in
          2    the mid-February timeframe in order to better assess the
          3    results of some of the significant inspections, but that can
          4    be adjusted, as appropriate.
          5              MR. THOMPSON:  Okay.
          6              CHAIRMAN JACKSON:  And the Commission values these
          7    sessions to focus all of us on the results to date and to
          8    gauge the effectiveness of the process being utilized,
          9    because that is a big issue, and so I encourage all the
         10    parties to remain steadfast in their various tasks and not,
         11    even though there is a schedule, not to be so schedule
         12    driven that we aren't results-focused, because in the end,
         13    when it comes to coming to the Commission for a decision,
         14    the decision is going to have to rest on what the results
         15    are and the verification of those results by all the parties
         16    involved.
         17              The Commission is appreciative of the insights
         18    from the contractors as well as from the licensee in
         19    obtaining honest feedback on the challenges and successes in
         20    making the Millstone station a safe station with an
         21    effective corrective action program and an environment that
         22    is supportive of raising and resolving safety issues.
         23              As I state at each meeting, the Commission itself
         24    does not presuppose that any of the three plants will
         25    restart by any certain data because it is results-dependent. 
             ANN RILEY & ASSOCIATES, LTD.
                    Court Reporters
            1250 I Street, N.W., Suite 300
                Washington, D.C. 20005
                    (202) 842-0034
                                                         160
          1    However, the Commission must be prepared to assure the
          2    allocation, as you have just heard the discussion of, of
          3    adequate staff resources to the oversight of the facility
          4    and its restart progress, and for that reason the Commission
          5    will continue to assess whether adequate progress is being
          6    made in readiness for restart of the units and whether our
          7    own, the NRC Staff assessment process, is effective, is
          8    comprehensive, and is timely, and so unless there are any
          9    closing comments, which I hope there are none --
         10              [Laughter.]
         11              CHAIRMAN JACKSON:  -- I would like to wish all of
         12    you a safe and wonderful holiday season and a healthy and
         13    happy New Year.
         14              We stand adjourned.
         15              [Whereupon, at 12:44 p.m., the meeting was
         16    concluded.]
         17
         18
         19
         20
         21
         22
         23
         24
         25



Privacy Policy | Site Disclaimer
Thursday, February 22, 2007