1
          1                      UNITED STATES OF AMERICA
          2                    NUCLEAR REGULATORY COMMISSION
          3                                 ***
          4               BRIEFING ON SHUTDOWN RISK PROPOSED RULE
          5                      FOR NUCLEAR POWER PLANTS
          6                                 ***
          7                           PUBLIC MEETING
          8                                 ***
          9                                  Nuclear Regulatory Commission
         10                                  Commission Hearing Room
         11                                  11555 Rockville Pike
         12                                  Rockville, Maryland
         13
         14                                  Wednesday, August 6, 1997
         15
         16              The Commission met in open session, pursuant to
         17    notice, at 2:00 p.m., the Honorable SHIRLEY A. JACKSON,
         18    Chairman of the Commission, presiding.
         19
         20    COMMISSIONERS PRESENT:
         21              SHIRLEY A. JACKSON, Chairman of the Commission
         22              GRETA J. DICUS, Member of the Commission
         23              EDWARD McGAFFIGAN, JR., Member of the Commission
         24              NILS J. DIAZ, Member of the Commission
         25
.                                                           2
          1    STAFF AND PRESENTERS SEATED AT COMMISSION TABLE:
          2              JOHN C. HOYLE, Secretary
          3              STEPHEN G. BURNS, Associate General Counsel
          4              JOSEPH CALLAN, EDO
          5              GARY HOLAHAN, Director, Division of Systems Safety
          6               and Analysis, NRR
          7              TIM COLLINS, Team Leader, Shutdown Rulemaking
          8               Task Force
          9              TIM MARTIN, Acting Associate Director for
         10               Technology
         11              THOMAS KING, Deputy Director, Division of Systems
         12               Technology, RES
         13
         14
         15
         16
         17
         18
         19
         20
         21
         22
         23
         24
         25
.                                                           3
          1                        P R O C E E D I N G S
          2                                                     [2:00 p.m.]
          3              CHAIRMAN JACKSON:  Good afternoon, ladies and
          4    gentlemen.  We are pleased to have the staff here to brief
          5    the Commission on the proposed rulemaking for shutdown and
          6    fuel storage pool operations at nuclear power plants.
          7              In a September 12, 1994, staff requirements
          8    memorandum, the Commission approved the publication of the
          9    proposed rule for shutdown and low-power operations for
         10    public comment.  The staff has expended a considerable
         11    amount of effort to address the public comments as well as
         12    the Commission guidance regarding the use of a risk informed
         13    performance-based approach for this important issue.
         14              During your discussion of the proposed rulemaking
         15    for shutdown and fuel storage pool operation, the Commission
         16    is interested in examples which demonstrate the use of the
         17    risk-informed performance-based approach in development of
         18    this rule.  In addition, the Commission is interested in
         19    hearing any lessons learned that could improve the
         20    rulemaking process in the use of risk.
         21              An initial comment I would make is it is
         22    important, whether it is on your viewgraphs or not, that you
         23    kind of lay out or give some sense of the context in
         24    historical -- the historical context, particularly since
         25    this Commission is not the same as the Commission that
.                                                           4
          1    issued the SRM in 1994.
          2              I understand that copies of the presentations are
          3    available at the entrances to the meeting room so, unless my
          4    colleagues have anything to add to begin, Mr. Callan.
          5              MR. CALLAN:  Thank you, Chairman.  Good afternoon,
          6    Chairman, good afternoon, Commissioners.
          7              With me at the table are Tim Martin, who is
          8    filling in for Sam Collins, who is not available, and Gary
          9    Holahan, the director of the Division of System Safety and
         10    Analysis in the office of NRR.
         11              Gary will introduce the members of the Shutdown
         12    Rulemaking Task Force and then Tim Collins, who is the team
         13    leader of the task force and, I might add, Tim is a very
         14    recent -- very recent selectee as the new branch chief, SES
         15    branch chief for the Reactor Systems Branch --
         16              CHAIRMAN JACKSON:  Are you going to announce
         17    Mr. Martin?
         18              MR. CALLAN:  We have a yellow announcement on
         19    that.
         20              And Tim Martin, it is worth saying for the record,
         21    Tim Martin is the new office director of the Office of AEOD. 
         22    But for this meeting, they are going to be in their old
         23    capacities and Tim Collins will proceed with the balance of
         24    the presentation when Gary Holahan is finished with his
         25    discussion.
.                                                           5
          1              CHAIRMAN JACKSON:  I have to tell you, though this
          2    has no relevance to the meeting, but someone started talking
          3    to me about a Tim Collins, in fact, Mr. Callan, earlier
          4    today.  And I thought he was confusing and lending Tim
          5    Martin and Sam Collins but I see there really is a Tim
          6    Collins.
          7              [Laughter.]
          8              MR. HOLAHAN:  I have had that problem myself.
          9              Back in January of 1997, in response to a number
         10    of internal and external comments on the staff's previous
         11    efforts to develop a shutdown rule related to, Madam
         12    Chairman, as you mentioned, the 1994 SRM.  We recognized
         13    that there were a substantial number of public comments and,
         14    in the time frame between the early '90s and now in the
         15    later '90s, I think we have had some additional time to
         16    think about what do risk-informed and performance-based
         17    approaches to rulemaking mean.
         18              So back in the beginning of this year, we really
         19    stepped back to take a new look at how to address shutdown
         20    rulemaking activities, to take public comments and sort of a
         21    risk-informed approach in mind and we established a task
         22    force and we gave them a due date of July 31 to produce a
         23    rule and supporting data.  In fact, I think they met that
         24    date by one day.  That is a pretty good performance by our
         25    rulemaking standards, I'm afraid.  And Mr. Collins, who is
.                                                           6
          1    the leader of that task force, will present the details of
          2    that package.
          3              But I would also like to present the members of
          4    that team so that you have a feeling for the scope and, in
          5    fact, the level of effort involved in producing this sort of
          6    activity.
          7              Eric Weiss is the -- sort of the associate team
          8    leader.  He is section chief under the Reactor Systems
          9    Branch.  Gary Mizuno, senior attorney from OGC.  We felt it
         10    was important to involve the OGC throughout the process and
         11    not as an add-on at the end.  Warren Lyon from the Reactor
         12    Systems Branch; Bob Tjader from the Tech Spec Branch; Bob
         13    Lata, senior operational engineer in the QA area; Kulin
         14    Desai, who is not here today, in Reactor Systems; Steve
         15    Jones from Plant Systems Branch to deal with the spent fuel
         16    pool issues; John Monninger from the Containment Systems
         17    Branch to deal with the containment issues; and last but
         18    certainly not least, Marie Pahida from the Reliability and
         19    Risk Analysis from the Probabilistic Safety Assessment
         20    Branch.
         21              So I say about half of those people were dedicated
         22    to this activity and the other half were involved as needed
         23    to contribute so it is a broadly thought out rule approach.
         24              CHAIRMAN JACKSON:  Commissioner McGaffigan has a
         25    very deep comment I think he wishes to make.
.                                                           7
          1              COMMISSIONER McGAFFIGAN:  I just have a question
          2    as to what happened after we got the comments?  The Federal
          3    Register notice was October of '94.  You got the comments in
          4    by March of '95, say.  It was a difficult period, a long
          5    period.  And then 21 months passed.  What was the
          6    action-forcing event in January where you finally decided we
          7    better do something and what were -- what happened?
          8              MR. HOLAHAN:  Between the time that comments were
          9    received -- and, in fact, I think Tim will mention it is
         10    something like over a thousand comments were received, we
         11    actually went back and took the version of the rule that we
         12    had developed earlier and tried to accommodate those
         13    comments and to produce a new rule.
         14              There had been some criticisms of the quality of
         15    the regulatory analysis.  So there was a rewrite of the rule
         16    and a regulatory analysis.  In effect, a second version of
         17    the rule was produced in that intervening period.
         18              When we got rather late in that period, I think we
         19    decided I think rightly but perhaps much later than we
         20    should have, that we were not really on a success path, that
         21    taking the approach that we had used and trying to build in
         22    some additional flexibility, to try to patch up some of the
         23    original regulatory analysis, simply wasn't leading us to a
         24    success path and, in effect, it wasn't until we had seen a
         25    rather fully developed second version of the rule that we
.                                                           8
          1    thought that this is not really what the Commission and what
          2    the staff and what the industry would be comfortable with. 
          3    We weren't -- I don't think it represented what I would
          4    consider our more modern thinking on risk-informed
          5    performance-based approaches.
          6              So at that stage, we really decided to go back to
          7    ground zero and start over again and that is what has led us
          8    to sort of a crash program over the last six months to
          9    produce what is, in effect, a third version of the rule.
         10              Obviously, if we were starting over again, we
         11    would just build this version; we wouldn't have built either
         12    of the previous two.  But I think the history of where we
         13    are and what we learned through sort of the middle '90s has
         14    contributed a lot to where we are now and we probably should
         15    have been smarter in the '94 time frame of sort of skipping
         16    over that middle phase.  But things just didn't come
         17    together at that point.
         18              CHAIRMAN JACKSON:  Okay.  Go on.
         19              MR. HOLAHAN:  Okay.
         20              Tim, you take the --
         21              MR. COLLINS:  Okay.  Could I have slide number 2,
         22    please?
         23              The first thing I want to do is give you an
         24    outline of my presentation and give you a statement of our
         25    overall objective in putting together the proposed rule and
.                                                           9
          1    a little bit of history associated with it.  Then I want to
          2    discuss what we perceive as the need for rulemaking, why we
          3    think there is this need.  In that discussion, I will cover
          4    where we see weaknesses in the existing regulations and what
          5    we think the risk significance of those weaknesses is.
          6              Then I will go through a structure of the proposed
          7    rule and try to describe how it remedies the weaknesses that
          8    we believe are present.  I will also summarize the
          9    regulatory analysis results and then I have a slide which
         10    discusses how we have tried to use risk-informed principles
         11    in the development of this rule.  We tried to make a very
         12    deliberate effort to use the risk-informed principles in the
         13    task force phase of the rule development.
         14              I also have a slide which gives a summary of the
         15    changes to the rule relative to the 1994 version that was
         16    last published.  And my last slide is a schedule of what we
         17    hope to accomplish in the next year with regard to final
         18    rulemaking.
         19              Can I have slide number 3, please?
         20              The objective of the proposed rule is to define
         21    requirements for cold shutdown, refueling and fuel storage
         22    pool operations that are risk informed, clear, coherent and
         23    enforceable.  This is not to say that there aren't any
         24    regulations out there right now which covered different
         25    parts, different phases of this operation.  But I think as
.                                                          10
          1    you will see, as the presentation goes on, there are some
          2    weaknesses and what we have tried to do is to fill in the
          3    important gaps in a risk-informed way.
          4              CHAIRMAN JACKSON:  Let me ask you this question,
          5    is the rule also performance-based or is it primarily risk
          6    informed?
          7              MR. COLLINS:  I would say it is primarily risk
          8    informed.  It does have a performance element in, a specific
          9    performance monitoring element that we have included.
         10              Slide number 4?
         11              This slide discusses the background, some of which
         12    Gary has already touched on.  As was mentioned, this is not
         13    the first time we have gone out for public comment on a
         14    proposed rule for shutdown operations.  The previous rule
         15    was published in October of 1994 and it attracted quite a
         16    bit of interest from the public.  We received over a
         17    thousand comments on the rule.  Many of these focused on the
         18    regulatory analysis, inadequacies in the regulatory
         19    analysis.
         20              The industry indicated that the rule was much too
         21    restrictive and that it would severely impact outages, in
         22    some cases up to as much as nine days' lengthening of
         23    outages.  And the industry said that the rule was really
         24    unnecessary because of voluntary actions that the utilities
         25    have already put in place.
.                                                          11
          1              In the course of working on the resolution of
          2    those comments, the Commission's policy statement on PRA was
          3    also issued.  That was in August of 1995.  So between
          4    comment resolution and incorporating the philosophy of the
          5    PRA policy statement, that drove us toward the revision to
          6    the rule.  And along the way we met with the ACRS for a
          7    status briefing.  That was in May of 1996.
          8              The ACRS wrote a letter following that meeting,
          9    indicating that they agreed there was a significant or
         10    important risk associated with shutdown operations.  They
         11    thought that the rule that we proposed to them at that time
         12    would probably lessen risk.  It was rather a lukewarm
         13    response in that regard.  And they also suggested at that
         14    time that maybe we ought to consider a broader base lining
         15    of shutdown risks.
         16              COMMISSIONER DIAZ:  Excuse me, just out of
         17    curiosity and history of the 1,023 public comments, how many
         18    were in favor of the rule or how many were in disfavor of
         19    the rule?
         20              MR. COLLINS:  I think it was like 1,022 to 1.
         21              COMMISSIONER DIAZ:  That is what I was wondering. 
         22    All right.
         23              [Laughter.]
         24              CHAIRMAN JACKSON:  Commissioner McGaffigan?
         25              COMMISSIONER McGAFFIGAN:  What is your prediction
.                                                          12
          1    about public comments on the new rule if it goes out?  Will
          2    it be 1,022 to 1 again?  I mean, because -- what?
          3              MR. COLLINS:  I believe that this rule is far more
          4    flexible than the previous rule and clearly more risk
          5    informed so I would expect we may still get 1,022 to 1 but I
          6    think that we have addressed many of the comments in the
          7    previous --
          8              MR. HOLAHAN:  It's clear to me I have to send in
          9    more comments next time.
         10              [Laughter.]
         11              CHAIRMAN JACKSON:  That's very good.  Very good.
         12              MR. COLLINS:  During 1996, we also had meetings
         13    with NEI to try to understand industry's positions with
         14    regard to rulemaking and we understood the industry position
         15    to be that they didn't believe there was a need for
         16    rulemaking primarily because of the voluntary actions that
         17    were already in place or commitments that licensees had
         18    made.  But they were willing to work toward the development
         19    of a performance-based rule.
         20              Late in the summer of '96, the staff made a
         21    decision to expand the scope of the rule to include fuel
         22    storage pool operations and to consider external events. 
         23    And following the staff decision, the interactions with NEI
         24    were terminated at that point.  NEI felt that they couldn't
         25    support a rule which included fuel storage pool and external
.                                                          13
          1    events, is our understanding.
          2              COMMISSIONER DIAZ:  Why?  What was the reason to
          3    include fuel storage at the time?  Why did we include fuel
          4    storage with the low power and shutdown?
          5              MR. COLLINS:  Well, it was included with low power
          6    because the fundamental concern is heat removal.  It is just
          7    more distant from the time of shutdown when you are in the
          8    fuel storage pool.  So we thought that, rather than a
          9    separate rulemaking effort on fuel storage pool operations,
         10    we could just attach it to the shutdown rule since shutdown
         11    is primarily concerned with decay heat removal as well.
         12              MR. HOLAHAN:  I would say there were two things. 
         13    One is the commonality of the technical issues.  Many
         14    periods during the refueling, some of the fuel is in the
         15    vessel, some of it is in the spent fuel pool and so we are
         16    sort of a continuity of the treatment of the issues.  The
         17    other was following the experience with Millstone and other
         18    plants it was clear that the staff and the licensees didn't
         19    have a common, clear understanding of what was expected of
         20    the licensees with respect to their requirements in the
         21    spent fuel pool area and we felt that something needed to be
         22    done to clarify what was required, not necessarily that
         23    there were more requirements but that there was sort of an
         24    unacceptable lack of clarity as to what was expected of
         25    licensees.  And in last year's study on spent fuel pools,
.                                                          14
          1    there was a Commission meeting and a Commission paper.  We
          2    had studied a number of plants, we had identified 10
          3    followup areas and in addition we had said that something
          4    needed to be done generically to bring closure to the
          5    understanding of what was expected.  So this is our
          6    mechanism for doing it, although it may have been done in
          7    some other way, this we thought was an efficient way to do
          8    that.
          9              CHAIRMAN JACKSON:  Because of the continuity of
         10    the issue?
         11              MR. HOLAHAN:  Yes.
         12              CHAIRMAN JACKSON:  I note that the ACRS had
         13    recommended a benchmark study on risk during low power and
         14    shutdown operations.  How did this play into this rule or
         15    your schedule for it or how are you intending to address the
         16    ACRS comments?
         17              MR. COLLINS:  We read that letter very carefully
         18    and we had responded to the ACRS indicating that we were in
         19    agreement with many of their recommendations.  That letter
         20    that they sent to us, the April letter, was not drafted in
         21    the context of the review of the shutdown rule.  That was
         22    drafted in the context of the review of risk-based
         23    regulation as a whole.
         24              You could read it to mean that well, maybe we
         25    ought to hold up shutdown rulemaking but it was not drafted
.                                                          15
          1    in response to a review of shutdown rulemaking.
          2              CHAIRMAN JACKSON:  And they plan, I understand, to
          3    comment on this proposed rule again?
          4              MR. COLLINS:  They asked to comment after the
          5    resolution of public comments.
          6              CHAIRMAN JACKSON:  Okay.
          7              Mr. King?
          8              MR. KING:  Yes, we are proceeding to gather
          9    information and lay out our plans for doing these additional
         10    risk studies as suggested by ACRS.  Currently, we would
         11    expect to begin those in about a year and there is a lot of
         12    information that has been developed since the previous risk
         13    studies that we did back in 1992 so both domestically and
         14    overseas and we want to build upon that.
         15              CHAIRMAN JACKSON:  Okay.
         16              COMMISSIONER DIAZ:  Just a comment.  As you
         17    progress in your presentation, I want to make sure that I
         18    get a very distinct idea of why do you think the spent fuel
         19    pools should be considered with the low power and the
         20    shutdown operations, where there is a tremendous difference
         21    in the configuration and lineup.
         22              In one case, the reactor vessel is closed.  You
         23    know, we can only access the reactor vessel through a series
         24    of very well set systems and mechanisms.  In the other case,
         25    the reactor vessel head is not there, it is sitting on the
.                                                          16
          1    side and you have a fuel transfer canal and there are very,
          2    very, very distinctive issues.
          3              We have decay heat all the time when we are at 100
          4    percent power or whether we are at zero power.  So decay
          5    heat is a common denominator for all operations in reactors
          6    and I think there is a very, to me, clear, distinct
          7    difference between low-power operation, shutdown and fuel
          8    storage pool and I hope they will actually --
          9              CHAIRMAN JACKSON:  Why don't we let them go on
         10    with their presentation?
         11              COMMISSIONER DIAZ:  For sure.
         12              MR. COLLINS:  Well, we already discussed the ACRS
         13    letter of April 18 and then in July of this year, we
         14    forwarded the rule to the Commission.
         15              Slide number 5, please.
         16              In the next few slides, I plan to address why we
         17    think there is a need for a rulemaking.  The first step in
         18    assessing the need for rule was a qualitative assessment. 
         19    We looked at the traditional safety functions that are
         20    associated with reactor operation and we looked at how these
         21    functions are protected by current requirements, both at
         22    power and during shutdown operations.  I have listed on my
         23    slide the six functions we focused our study on.
         24              When we reviewed the requirements at power, we
         25    found that such things that the general design criteria, the
.                                                          17
          1    technical specifications, Part 50, Appendix B, very
          2    comprehensively protect these functions.  When we took the
          3    same look -- I'm going to slide number 6.
          4              We took the same look at the protection provided
          5    by current regulations and tech specs during shutdown.  We
          6    found that there were some issues which were not covered and
          7    I have some of these listed on slide number 6.  The
          8    availability of such things as injection capability is not
          9    covered for PWRs during cold shutdown and refueling.  That
         10    is, there are no technical specifications for ECCS in mode
         11    five and mode six.
         12              COMMISSIONER DIAZ:  This is specific technical
         13    specifications?
         14              MR. COLLINS:  Yes, technical specifications.
         15              COMMISSIONER DIAZ:  They are clearly covered by
         16    Appendix A and therefore by Appendix B.
         17              MR. COLLINS:  Yes, the ECCS systems.
         18              COMMISSIONER DIAZ:  Requirements during any normal
         19    conditions which includes, of course, the shutdown.
         20              MR. COLLINS:  The GDC certainly applied.
         21              COMMISSIONER DIAZ:  Okay.
         22              MR. COLLINS:  These are -- I have specifically
         23    listed this as availability to differentiate that from
         24    design requirements.  Typically, availability is controlled
         25    by the technical specifications and we reviewed the standard
.                                                          18
          1    technical specifications to see whether or not these
          2    functions were covered during shutdown.
          3              CHAIRMAN JACKSON:  So that is where the crux is,
          4    having to do with availability?
          5              MR. COLLINS:  It's availability.  We don't have
          6    any concerns with the capability of the systems to perform
          7    their function if they are available.
          8              CHAIRMAN JACKSON:  So that is what brings them
          9    away from the general design criteria?
         10              MR. COLLINS:  Right, the general design criteria
         11    do not address availability.
         12              CHAIRMAN JACKSON:  Okay.  And the only question I
         13    would ask is did you consider revisions to Appendix B or
         14    some other existing regulations?  I guess it really has to
         15    do with your deciding it was better to treat all these
         16    issues in a comprehensive way as opposed to trying to go
         17    back and revise Appendix B?
         18              MR. COLLINS:  That's correct.
         19              MR. HOLAHAN:  In our previous versions of a
         20    proposed rule, for example, we proposed to have individual
         21    technical specifications to control the availability of
         22    equipment.  But what we found is that normal operation is
         23    much simpler than shutdown activities.  During normal
         24    operation, most all systems are available and perhaps only
         25    one at a time is taken out of service.  And so it is
.                                                          19
          1    relatively straightforward to write requirements calling for
          2    all the equipment to be available and then giving outage
          3    times if one piece is.
          4              A more complicated situation, I think, exists in
          5    shutdown when there are numerous pieces of equipment taken
          6    out of service and the combinations of those, I think, got
          7    too complicated or overly conservative in trying to write
          8    those into specific specifications.
          9              COMMISSIONER DIAZ:  I just was trying to get a
         10    nomenclature.  I don't know whether I have to change but
         11    since I was a kid when I started in this business, you know,
         12    I don't want to say how long ago, but it was a long time
         13    ago, normal operations including shutdown and low power so
         14    you can't call shutdown, you know, a different type of
         15    normal operations.
         16              MR. HOLAHAN:  Yes.
         17              COMMISSIONER DIAZ:  Normal operations includes
         18    shutdown and that is part of normal operations and they are
         19    clearly addressed by Appendix B.  It says operating
         20    conditions and all operating conditions are covered.  So
         21    whether they are low power or shutdown, those are all normal
         22    operating conditions.  So we cover them in different ways
         23    but now if we want to specifically address them in a better
         24    fashion, I understand that.  But they have always been
         25    normal operating conditions, including shutdown.
.                                                          20
          1              MR. CALLAN:  Commissioner, if I might add, the
          2    point that you are making is a point that OGC has made
          3    repeatedly in the discussions and during the pre-brief I
          4    had, OGC made that very point, that there are regulations
          5    that apply and your clarification is correct, that we are
          6    improving or enhancing our ability.
          7              COMMISSIONER McGAFFIGAN:  Could I follow up on
          8    that?  One of the things you all do in this new rule,
          9    though, is somebody must see some vulnerability there
         10    because you add a definition in 50.2 of shutdown operation
         11    and the last sentence of which, shutdown operation is part
         12    of normal operations.  So somebody felt constrained in this
         13    rulemaking package to make that crystal clear in regulation. 
         14    Is that because it may have been less than crystal clear
         15    previously?
         16              CHAIRMAN JACKSON:  We just wanted to be sure it
         17    was perfectly clear.
         18              MR. HOLAHAN:  Perfectly clear.
         19              CHAIRMAN JACKSON:  This just came out of OGC's
         20    comments.
         21              COMMISSIONER DIAZ:  If I may comment on that, I
         22    don't think there is anybody in the industry that has a
         23    question that shutdown is part of normal operation.  If you
         24    want to add clarity for some additional purpose, that's
         25    fine.  But the NRC and the industry, correct me if I am
.                                                          21
          1    wrong, we all call shutdown power normal operations,
          2    correct?
          3              MR. CALLAN:  Yes.
          4              CHAIRMAN JACKSON:  But I think the point is not so
          5    much to get hung up as to whether or not some existing
          6    regulations include shutdown operations within the scope. 
          7    But if there are specific issues that you mentioned,
          8    availability number one, that this rule specifically allows
          9    us to deal with.  And, secondly, a sentence that maybe
         10    states the obvious, if it really is obvious, and if it is
         11    not obvious, either way, it doesn't hurt to have it.
         12              COMMISSIONER DIAZ:  It doesn't hurt, but it is
         13    obvious.
         14              CHAIRMAN JACKSON:  This makes it obvious to all.
         15              Okay, let's go on.
         16              MR. COLLINS:  Some other functions that we found
         17    were lacking in the current requirements, the availability
         18    of BWR venting.  That is the ADS system we are referring to
         19    there.  In BWRs, ECCS is required during cold shutdown. 
         20    However, the ADS is not required and the ECCS required is
         21    low-pressure systems.  And should you have a pressurization
         22    event, you wouldn't be able to use the ECCS anyway.
         23              Containment is required under very limited
         24    conditions right now in the standard technical
         25    specifications.  There are other areas where the current
.                                                          22
          1    requirements are what we would describe as maybe partial,
          2    they don't fully address some functions.  Fire protection
          3    for cold shutdown equipment is an important area.  50.48,
          4    Appendix R and GDC-3 all treat fire protection.  When we
          5    looked carefully at them, it was clear that they focused on
          6    a fire that started during power operations.  It requires
          7    protection of equipment to a safe shutdown condition which
          8    has been interpreted as hot shutdown.
          9              If you have a fire that starts at cold shutdown,
         10    that hot shutdown equipment would not be available.  You
         11    typically need the reactor coolant system to be closed.  If
         12    you are in refueling, the cooling system is not closed.
         13              The only requirement for cold shutdown equipment
         14    in the existing regulations is that it be recoverable
         15    following a fire within 72 hours.  Well, should a fire begin
         16    in cold shutdown, 72 hours is far too long to wait to
         17    recover that equipment.
         18              There are other requirements with regard to fire
         19    protection that are tied to inerting.  BWR Mark I and Mark
         20    II containments operate in an inerted condition when they
         21    are at power and, because of that, there has been a
         22    relaxation in the equipment protection requirements relative
         23    to fire.  When you are shut down, these containments would
         24    not be inerted.
         25              Finally, Appendix B, which addresses things like
.                                                          23
          1    procedures, corrective actions and QA, Appendix B applies to
          2    safety-related functions and the cold shutdown equipment is
          3    not always classified as safety-related equipment.  Many
          4    plants, the cold shutdown equipment is not classified as
          5    safety related.  So the applicability of Appendix B is kind
          6    of tenuous there.
          7              COMMISSIONER DIAZ:  I'm sorry, I have to argue
          8    with that.
          9              Appendix B clearly says that QA will be
         10    commensurate with the degree of safety.  So even if they are
         11    not in the Q list, now, you might be right they are not in
         12    the Q list, but they still have been QA to whatever degree
         13    or measure of safety is.  So that doesn't mean they're
         14    not --
         15              MR. CALLAN:  Let me give you a specific example
         16    that I have been involved with over the years.  At even
         17    newly licensed plants, the pressurized or the pneumatic seal
         18    that provides a pressure fit around the gate on a refueling
         19    canal is not -- frequently not captured by a licensee's QA
         20    program.  When those seals fail, it causes a fairly dramatic
         21    drop in water level.  It is failsafe, in a sense, that it
         22    won't go below a certain level that provides adequate
         23    protection but, nevertheless, it is a fairly dramatic event
         24    when it happens and results in a lot of water in the
         25    containment building during refueling outages.
.                                                          24
          1              That has happened a number of times around the
          2    country.  Relatively recently, there has been I think at
          3    least two generic communications out on that.  Just one
          4    example of a fairly important component that is not captured
          5    by an Appendix B program, it is not considered safety
          6    related.  And I think there are arguments why it shouldn't
          7    be.
          8              And there are several other examples of that
          9    nature.
         10              COMMISSIONER DIAZ:  Well, it was not because if it
         11    fails, it would have no consequences.  It is just messy and
         12    transfers a lot of water --
         13              MR. CALLAN:  Right, but you do get elevated
         14    radiation levels depending on what's going on at the time
         15    and that sort of thing.
         16              CHAIRMAN JACKSON:  Mr. Holahan, you wanted to make
         17    a comment?
         18              MR. HOLAHAN:  Well, I think that although Appendix
         19    B could be read in some respect to apply to some of this
         20    equipment, that is not the standard interpretation used in
         21    the industry and since our objective was to reach some clear
         22    understanding as to what was expected, I think we want to be
         23    clear on how Appendix B ought to apply to such --
         24              COMMISSIONER DIAZ:  But we already have, you know,
         25    a guidance, I will say, in that we are going to go using
.                                                          25
          1    risk assessment and everything we have available to do
          2    graded QA and I am sure that that graded QA will eventually
          3    involve all of these systems.  So we are ready to do actions
          4    in that respect.
          5              MR. HOLAHAN:  Yes.  But I think where a licensee
          6    chooses to do the risk-informed graded QA, this would be
          7    taken care of.  But we are approaching that as a voluntary
          8    program so if a licensee doesn't choose to do this, I think
          9    it would be different at that plant.
         10              COMMISSIONER DIAZ:  Thank you.
         11              MR. COLLINS:  All right, moving to slide number 7,
         12    please.
         13              The second step of our analysis was to make a
         14    quantitative assessment of the significance of the
         15    weaknesses that we found in our qualitative assessment.  And
         16    the first step we took in this was to try to make an
         17    estimate of risk of plants that are operating, in normal
         18    operation today.  The way we did that was we took NUMARC
         19    91.06, which is an industry-sponsored guidance document for
         20    shutdown operations management and we said, if we were
         21    implementing this guidance, what equipment would we make
         22    available during different phases of shutdown operation. 
         23    And then we did a risk estimate based on the availability of
         24    that equipment.
         25              That is the first line that you see on slide
.                                                          26
          1    number 7 where it says, estimate of industry practice.  I
          2    just want to make it clear that this is not a number that
          3    the industry has provided to us, this is a number that we
          4    have estimated ourselves.  You see that it comes up with
          5    numbers that are in the vicinity of the Commission's safety
          6    goal guidelines, quantitative guidelines.
          7              Then the next step in our analysis was, what
          8    happens if we remove from that things which are voluntary,
          9    things which are not strictly required by the regulations,
         10    and we remove things that are not included in technical
         11    specifications, anything that was not specifically called
         12    out in the regulations, and we also removed commitments made
         13    in response to generic letters.  So it is really a stripped
         14    down analysis.
         15              If you took the tech spec requirements which were
         16    our minimum during these modes of operation and only what
         17    the strict regulations require, what happens then?  And that
         18    gives us numbers which are well removed from the safety goal
         19    guidelines.  Which was not surprising to us when you looked
         20    at the safety functions involved.
         21              I think the primary message from this, this
         22    viewgraph here, is that the existing level of safety is very
         23    heavily dependent on voluntary measures.  That is the
         24    message we got from this analysis.
         25              CHAIRMAN JACKSON:  What would the numbers look
.                                                          27
          1    like with the requirements of the rule?
          2              MR. COLLINS:  They come a lot closer to where the
          3    industry is right now.  That is on a slide a couple slides
          4    down.
          5              COMMISSIONER DIAZ:  But again, let me see if I can
          6    try to understand these numbers.  What you have, and let me
          7    see if I understand what numbers apply, the numbers will be
          8    different for, say, mid-loop operations in a BWR?
          9              MR. HOLAHAN:  Yes, yes.
         10              COMMISSIONER DIAZ:  Than they will be when we are
         11    refueling.  So, in a certain way, the table, it is too much
         12    of an average and we conclude --
         13              MR. COLLINS:  These numbers are driven --
         14              MR. HOLAHAN:  It's not an average.  It is an
         15    integral.  It takes each of those situations but obviously
         16    the dominant contributor is just the mid-loop operations.
         17              COMMISSIONER DIAZ:  Right, it is an integral.  And
         18    therefore, you know, it gives us a very, to me, I mean, I
         19    look at it, I almost fell out of my chair, look at it,
         20    flip-flop, had to be given salts and all of that.
         21              [Laughter.]
         22              COMMISSIONER DIAZ:  As you know, it is a kind of
         23    very, very distinct difference.  I think it is important to
         24    realize that, and that is what I was talking about,
         25    refueling operations and separating it from mid-loop in a
.                                                          28
          1    BWR, that these numbers probably only apply to a very narrow
          2    range of normal operations that were called mid-loop, going
          3    from mode five to mode six.
          4              MR. COLLINS:  To a degree, yes.
          5              COMMISSIONER DIAZ:  And that really, you know, it
          6    represents the risk in that area.  While the risk, when the
          7    fuel transfer canal is open and everything is at atmospheric
          8    pressure, you know, a hose from the sanitary sewer can
          9    provide enough cooling, you know, if we get into extreme
         10    cases.
         11              MR. COLLINS:  Yes.
         12              COMMISSIONER DIAZ:  So I think it is important
         13    that we come out and separate them.  And now, having said
         14    that, let me try to understand how we arrive at the, let's
         15    call it the first column, the mid-loop operations of BWRs
         16    and probability of core damage frequency of two to 10 to the
         17    minus two per reactor year.  Is this the worst, worst, worst
         18    case scenario?  Meaning, you have taken the fact that the
         19    system is sitting there and also you take the receivable
         20    heat removal system out completely?
         21              MR. HOLAHAN:  No.
         22              COMMISSIONER DIAZ:  No?
         23              MR. COLLINS:  No, we have used initiating event
         24    frequencies that are historical data or are best estimates
         25    at initiating event frequencies.  What happens is mitigation
.                                                          29
          1    equipment is gone and --
          2              COMMISSIONER DIAZ:  So the receivable heat removal
          3    system is gone?
          4              MR. COLLINS:  No, not necessarily.  Things like
          5    the CVCS would not be present, okay?  The ECCS is not
          6    present.  Containment does not affect the core damage
          7    frequency but it is not present either, okay?
          8              And if you take a simple example, you have a loss
          9    of level control in a PWR, which is not infrequent from our
         10    perspective, and you don't have a makeup capability, you
         11    can't recover even if you have two-hour HR systems
         12    available, neither one of them can recover without first
         13    having some water makeup, okay?  So something like a
         14    loss-of-level control event occurring during mid-loop, you
         15    can't recover from it.  All you need is the initiating event
         16    frequency to get you these types of numbers.
         17              CHAIRMAN JACKSON:  Why don't we go on.  We
         18    can't --
         19              COMMISSIONER McGAFFIGAN:  Could I ask just one
         20    question?
         21              CHAIRMAN JACKSON:  Sure.
         22              COMMISSIONER McGAFFIGAN:  NUMARC 91.06, is that
         23    mandatory within NEI framework for its members or is that
         24    voluntary?  Was that a voluntary guideline?
         25              MR. HOLAHAN:  Yes, it met their definition of an
.                                                          30
          1    industry initiative which I think is comparable to mandatory
          2    within the NEI framework.
          3              COMMISSIONER DIAZ:  So that means that 80
          4    percent --
          5              MR. HOLAHAN:  Exactly, yes.
          6              COMMISSIONER DIAZ:  Okay.
          7              CHAIRMAN JACKSON:  Okay.
          8              MR. COLLINS:  Moving on to slide number 8, this
          9    slide is an outline of the rule as we are proposing it.  We
         10    are trying to address each of the weaknesses that we have
         11    identified in our analysis of current requirements.
         12              The first element in the rule is a procedural
         13    element that would require administrative tech specs be
         14    added for all plants which would require that procedures in
         15    quality assurance, training and corrective action be
         16    included for activities that can affect decay heat removal,
         17    for safety function performance monitoring and for
         18    activities associated with maintaining mitigation capability
         19    available.  This is basically to account for the potential
         20    Appendix B weakness.
         21              The second element is the performance monitoring
         22    element that we made reference to earlier.  Here, we have
         23    defined safety function limits associated with water
         24    temperature, reactor coolant system pressure and reactor
         25    coolant system level.
.                                                          31
          1              And we have defined limits.  We have left it to
          2    the licensees to decide how they would monitor those
          3    parameters, what instrumentation they want to use, what
          4    frequency they want to monitor it.  We would review the
          5    methods and criteria used for determining what
          6    instrumentation they were going to use and what frequency
          7    they were going to use.  Should they violate any of the
          8    safety function limits, it would be a reportable event.
          9              The third element in the rule is an administrative
         10    tech spec requirement relating to mitigation capability.  We
         11    have written the rule in very high-level language.  The rule
         12    itself says that the licensees must maintain equipment
         13    available to assure adequate core cooling and protection
         14    against the uncontrolled release of fission products.  In
         15    this statement of considerations and the reg guide, we
         16    discussed that we expect that to mean backup RHR and
         17    injection capability and containment being intact, a
         18    definition of which we provide in the statement of
         19    considerations, or an alternative to the intact containment.
         20              I think it is important to understand that in the
         21    containment alternative, we have made it clear that the
         22    containment provides a defense in depth function.  It is a
         23    diverse type of protection.  And that if a licensee chooses
         24    to use the alternate to containment, they need to recognize
         25    the defense in depth attribute that containment carries with
.                                                          32
          1    it and they can't simply put a second pump in place and say,
          2    well, I don't need a containment now.  They have to be able
          3    to handle a wide range of initiating events just as
          4    containment would be able to handle it.
          5              We also allow the licensee to choose whatever
          6    equipment they want to use.  They must keep it, keep
          7    documentation in a licensee-controlled document, the
          8    document that will need to be identified in the tech specs
          9    for the purposes of inspection and enforcement.  We don't
         10    want to have the requirements spread out in a bunch of
         11    different licensee documents.  We have asked them to put it
         12    in one place so that an inspector can go and understand what
         13    is being relied upon at any given time in a shutdown.
         14              We again would control the criteria and methods. 
         15    We would review the criteria and methods used for the
         16    selection of equipment but the licensee would be free to
         17    change out different types of equipment at different points
         18    in the outage as long as they followed the methods and
         19    criteria that were approved by the staff.
         20              The fourth element of the rule is the fire
         21    protection element.  I think the simplest way to think of
         22    this is that we have tried to bring the protection afforded
         23    at power operation into the cold shutdown regime.  The rule
         24    would require that licensees either protect their cold
         25    shutdown equipment from the effects of fire or if they can't
.                                                          33
          1    do that, they need to provide suppression and detection
          2    equipment and to have contingency plans in place such that
          3    if both trains of cold shutdown should be lost by a fire
          4    that they can maintain core cooling by another mechanism.
          5              CHAIRMAN JACKSON:  Let me ask you a question.
          6              How do you assess the inspectability and
          7    enforceability of the performance monitoring aspects?
          8              MR. COLLINS:  The inspectability, to a large
          9    extent, is very straightforward once we have approved the
         10    methods in the criteria because the licensee will have to
         11    document what instrumentation is being used, what frequency
         12    it is being used.  An inspector can simply go to that
         13    document and say, show me that you have done this, and they
         14    can review the records over the past year or at any moment
         15    in time go in and say, show me.
         16              CHAIRMAN JACKSON:  So that is how you both have
         17    the inspectability and enforceability and consistency in
         18    inspection and enforcement?
         19              MR. COLLINS:  Yes.  It does put some burden on the
         20    headquarters staff in that we will have to review the
         21    methods and criteria in advance.  It should facilitate
         22    inspection and enforcement.
         23              MR. HOLAHAN:  And the office of enforcement has
         24    reviewed the package?
         25              MR. COLLINS:  Yes, they have.
.                                                          34
          1              CHAIRMAN JACKSON:  Commissioner McGaffigan.
          2              COMMISSIONER McGAFFIGAN:  On the fire protection
          3    side, is there anything we are doing here that plays back
          4    into when and if we ever get around to doing Appendix R and
          5    getting rid of words like combustible and whatever, that
          6    have you protected yourself against having to come back and
          7    review this rule when we finally get around to doing that
          8    rule?
          9              MR. COLLINS:  Yes, we have worked with the Office
         10    of Research in the development of this rule and as far as we
         11    know, we are not doing anything contrary to what they plan
         12    to do and as a matter of fact, they plan to incorporate what
         13    we have done in shutdown into their own requirements as well
         14    as they see it fits.  You know, they don't intend to redo
         15    shutdown.
         16              MR. HOLAHAN:  There were a number of discussions. 
         17    I think it was recognized that fire protection for shutdown
         18    was not fully covered in the regulations and there were a
         19    number of discussions about how to address that.  We could
         20    have just taken the 50.48 fire protection regulation and
         21    written shutdown into it or it could have been done here or
         22    it could be done in both.  Through the discussions as to
         23    what looked like a reasonable way to do it and how that
         24    could be referenced in a future change to 50.48 results were
         25    sort of worked out before these words were developed.
.                                                          35
          1              CHAIRMAN JACKSON:  Let's go on.
          2              MR. COLLINS:  Okay, the last element in the
          3    proposed rule is the one that addresses the fuel storage
          4    pool.  The requirements here would be simply to update the
          5    FSAR to incorporate the assumptions which are essential for
          6    the design and safety functions of the pool and to be sure
          7    that those assumptions were incorporated in the plant
          8    operating procedures.
          9              I believe the thrust here is that there is the
         10    perception of misunderstanding of what the expectations were
         11    with regard to fuel storage pool operations, as evidenced by
         12    the problems we have had in the past few years.  And risk
         13    studies didn't indicate a compelling reason to have a rule
         14    for fuel storage pool.  We didn't do any quantitative
         15    assessment which says there is a heavy-duty risk here.  But
         16    it is almost a matter of housekeeping to make it clear not
         17    only to the licensees but also to the NRC staff what is
         18    expected with regard to fuel storage pool operations and we
         19    see this as cleaning the slate and making it clear from here
         20    on out this is what is expected.
         21              MR. HOLAHAN:  I would say that, because of the
         22    decision we have come to, that in fact there are no
         23    technical requirements, there is no real backfitting of
         24    requirements here, this piece, this objective could be
         25    accommodated in other ways.  The FSAR update rule could have
.                                                          36
          1    some specific language with respect to spent fuel pools or
          2    the Commission could just express to the industry that its
          3    expectation that 50.71(e) covers spent fuel pools but -- so
          4    I think it is written in such a way that it is not an
          5    essential element of this rule.  That piece could be taken
          6    out and that issue could be dealt with separately.
          7              CHAIRMAN JACKSON:  But is it written in a way that
          8    is consistent with what is already going on vis-a-vis
          9    50.71(e)?
         10              MR. HOLAHAN:  Well --
         11              CHAIRMAN JACKSON:  It's hard to say?
         12              MR. HOLAHAN:  It's hard to say because I am not
         13    sure exactly where we are going with 50.71(e).  I think it
         14    is not very prescriptive at all.  I think what it really
         15    says is whatever the current licensing basis is for spent
         16    fuel pools, write that into your FSAR.  To the extent
         17    50.71(e) is being pushed in that direction of saying get
         18    that sort of stuff in your FSAR, I think that is consistent.
         19              CHAIRMAN JACKSON:  Okay.
         20              MR. COLLINS:  There are a couple other conforming
         21    changes that go along with the rule which are not listed on
         22    the slide.  Equipment which licensees wish to credit for the
         23    shutdown rule would need to be included in the maintenance
         24    rule program and for license renewal, any equipment which a
         25    licensee wishes to credit for shutdown rule would also need
.                                                          37
          1    to be covered in the license renewal.
          2              Slide number 9.
          3              Slide number 9 is the regulatory analysis results. 
          4    We have already seen the first two lines, the estimate of
          5    industry practice and what is the base case in the
          6    regulatory analysis.
          7              The bottom line is where we would be -- an
          8    estimate of where we would be if this rule was in place,
          9    okay?  And, again, the rule basically raises the floor from
         10    several orders of magnitude away from the safety goal to
         11    right in the vicinity of the safety goal guidelines.
         12              COMMISSIONER DIAZ:  Subsidiary guidelines.
         13              MR. COLLINS:  Subsidiary guidelines, yes. 
         14    Subsidiary objectives, sorry.
         15              There is just one -- we have used the frequency of
         16    unmitigated release as if it was a large early release.  In
         17    fact, shutdown is slightly different because the short-term
         18    products would all be decayed away before you would get to a
         19    release in a shutdown accident.  Typically it takes a couple
         20    days to get to cold shutdown.
         21              CHAIRMAN JACKSON:  Does the rule accommodate
         22    having NUMARC 91.06 being an acceptable methodology for
         23    meeting the requirements of the rule?
         24              MR. HOLAHAN:  Not directly, although I think the
         25    way the rule is structured, a licensee could propose the
.                                                          38
          1    program that they have under --
          2              CHAIRMAN JACKSON:  91.06?
          3              MR. HOLAHAN:  NUMARC 91.06 as their approach and I
          4    think that could be reviewed and approved separately.  I
          5    think 91.06 is not really a program, it is really a test of
          6    how good is your program.  It is not really a definition
          7    itself.  But I would think a program developed and
          8    consistent with 91.06 --
          9              CHAIRMAN JACKSON:  Would most likely meet the
         10    requirements of this rule?
         11              MR. HOLAHAN:  I think if you look at the risk
         12    numbers --
         13              CHAIRMAN JACKSON:  The risk numbers are very
         14    similar?
         15              MR. HOLAHAN:  Yes.  I think what it would do is it
         16    would move that from a voluntary program into a more
         17    structured regulatory approach.
         18              MR. COLLINS:  Yes, NUMARC 91.06 is very high
         19    level.  It is hard to answer the question directly, I mean
         20    depending on how you implemented it.
         21              CHAIRMAN JACKSON:  Okay.
         22              MR. HOLAHAN:  I think it is fair to say the same
         23    program and the same general use of equipment and its
         24    availability would apply to both cases.
         25              CHAIRMAN JACKSON:  Okay.
.                                                          39
          1              What do you mean by intact containment and does
          2    the reg guide include definitions of these kinds of less
          3    prescriptive areas?
          4              MR. COLLINS:  We include a definition of the
          5    intact containment.  It allows certain penetrations to be
          6    open, provided that they can be closed automatically from
          7    the control room.  It requires, though, that the closure be
          8    able to withstand full design pressure.  We have given an
          9    explicit definition in the statement of considerations and
         10    in the reg.
         11              MR. HOLAHAN:  And correct me if I am wrong but I
         12    believe it calls for one barrier as opposed to two?
         13              MR. COLLINS:  Yes, one barrier, right.
         14              CHAIRMAN JACKSON:  Okay.  Let's go on.
         15              MR. COLLINS:  Just one more comment, though, while
         16    we are on this slide.  That is the ACRS letter talking about
         17    the need for a benchmarking study.  If we look at the
         18    results and the insights to be gained from the studies we
         19    have done, I think it tells us that we really don't need to
         20    have a big, comprehensive benchmarking study of low power
         21    and shutdown to see that there is some weaknesses in our
         22    existing regulations and we can address those weaknesses
         23    very directly with the proposed rule we have.
         24              The base case I don't think would change one iota,
         25    regardless of how much of a comprehensive benchmarking study
.                                                          40
          1    you have done.  Once you take away important safety
          2    functions, it becomes a very simple problem.  And the rule
          3    case would be fine tuned.  But we are talking about a
          4    thousand-to-one value impact ratio in this cost/benefit
          5    analysis.  We can't see how the overall insight is going to
          6    be changed.
          7              MR. HOLAHAN:  The one area that might be somewhat
          8    different is I think that there hasn't been much research on
          9    core melt in an oxygen environment for a shut down reactor. 
         10    I think in most cases, you know, we think of an at-power
         11    case and core melt in a superheated steam environment.  So I
         12    think some of the chemistry and some of the release
         13    mechanism might be somewhat different and I think that
         14    deserves a comprehensive thought.  In this case, I don't
         15    think it changes the answers but I think it would bring a
         16    better understanding of what sort of real risks are
         17    associated with these shutdown conditions.
         18              MR. COLLINS:  In addition to that, the way we have
         19    written the rule, you know, it requires things like
         20    adequate -- equipment for adequate core cooling and
         21    uncontrolled release of fission products, protection against
         22    that.  We wouldn't necessarily need to have a rule change to
         23    implement insights from such a study and research anyway. 
         24    They would be plant-specific implementation if it is found
         25    that certain equipment is particularly beneficial or certain
.                                                          41
          1    equipment is particularly vulnerable, those could be --
          2    those insights could be incorporated without any change to
          3    the rule.
          4              CHAIRMAN JACKSON:  Okay.
          5              MR. COLLINS:  Slide number 10.
          6              The regulatory analysis numbers do not include
          7    fire.  We didn't believe that we had the capability to do a
          8    generic fire PRA for the purposes of the regulatory
          9    analysis.  So, instead, we performed what I will describe as
         10    a qualitative risk assessment and I have listed five factors
         11    we believe are important in an assessment of risk from fire
         12    during shutdown operations.
         13              What we did is we looked at how these factors are
         14    protected by regulations at power, how they are protected by
         15    regulations at shutdown and how the conditions associated
         16    with these risk factors are different during shutdown as
         17    opposed to power.  Our objective was, let's try to bring the
         18    shutdown protection into the same regime as the power
         19    operation protection.
         20              We found the first factor is frequency of fires
         21    during shutdown, there was an AEOD study.  We used the data
         22    from that study that showed that the frequency of fires was
         23    rather high during shutdown, on the order of 10 to the minus
         24    two per reactor year.  So initiating event frequency is
         25    relatively high, comparable to power operation.
.                                                          42
          1              All the other factors, we found that the
          2    conditions were either the same as at power or worse and the
          3    protection afforded by the regulation was the same or less.
          4              COMMISSIONER DIAZ:  Excuse me.
          5              Could you be a little more specific?  Fires where,
          6    in any --
          7              MR. COLLINS:  Oh, right.  It was fires in areas
          8    that could affect the safe shutdown equipment or the cold
          9    shutdown equipment, I'm sorry.  That's right.
         10              For example, if you look at the probability of
         11    combustible loadings to allow fire to propagate, during
         12    shutdown that is the time when you've got a lot more welding
         13    equipment on site, you are doing combustible fluid changes,
         14    you've got a lot of wood around to help with projects.  It
         15    is just -- the conditions on all these factors were either
         16    the same or worse from a risk perspective, which led us to
         17    the conclusion that we could use some additional
         18    requirements to bring these, the protection, more up to the
         19    standard at current power operation.
         20              Slide number 11.
         21              This is where we have assessed what the cost to
         22    the industry would be from implementation of the rule. 
         23    These costs are from today to the end of plant life.  For
         24    the shutdown portion of the rule, we estimate it will be a
         25    little under $2 million per plant.  These are primarily
.                                                          43
          1    paper costs.  It is just a matter of bringing something
          2    which is currently in the voluntary regime into the
          3    regulatory arena just costs some money.  We have included
          4    some costs for instrumentation upgrade which some plants
          5    could possibly need to do the performance monitoring portion
          6    of the rule.
          7              The fire protection, again, it is a largely paper
          8    cost.  There is some equipment, we have included a cost for
          9    some equipment which may be needed to enhance fire
         10    suppression and detection equipment for cold shutdown
         11    equipment.
         12              A fuel storage pool operation is strictly a paper
         13    exercise and it is about $50,000 a plant to update the FSAR
         14    and modify procedures so the total cost for the entire rule
         15    we would estimate to be less than $3 million per plant for
         16    the lifetime of the plant.
         17              CHAIRMAN JACKSON:  Is this above and beyond what
         18    the licensees may already be doing to update their FSARs? 
         19    So this is kind of as if they have done nothing to this
         20    point?
         21              MR. HOLAHAN:  Yes, I think that's correct.
         22              COMMISSIONER DIAZ:  Have you had some feedback on
         23    this number from industry?  Has anybody said it's low?
         24              MR. COLLINS:  No, they haven't seen these numbers. 
         25    They have not seen these numbers.
.                                                          44
          1              CHAIRMAN JACKSON:  That is what the new comment
          2    period will do.
          3              Yes?
          4              COMMISSIONER McGAFFIGAN:  Could I ask, are these
          5    numbers front loaded?  I mean, if you use paper exercise, in
          6    the year after the rule goes into effect would most of this
          7    cost be incurred?
          8              MR. COLLINS:  Yes, it would.  Yes.
          9              MR. HOLAHAN:  In some cases, all of it is just a
         10    one-time cost.
         11              MR. CALLAN:  Just anticipating some comments from
         12    the industry, there is a hidden cost here that is not
         13    reflected and that is, I guess, what you could call the
         14    regulatory impact or the regulatory cost.  Now that what was
         15    voluntary is now enforceable, that means that from time to
         16    time, probably every outage, there will be issues that will
         17    be raised by the inspection staff that will have to be dealt
         18    with and at no small cost in some cases in terms of staff
         19    time and paper.  So there is that expense that is not
         20    reflected here that would be ongoing.
         21              CHAIRMAN JACKSON:  Okay.
         22              MR. COLLINS:  Slide number 12.
         23              Slide number 12 discusses how we tried to take
         24    into account the risk-informed principles in the development
         25    of the rule.  There was a very deliberate effort to use risk
.                                                          45
          1    insights throughout the development of the rule.  We used
          2    PRA technology where we thought we had the capability.  We
          3    did the quantitative assessment for the shutdown portion. 
          4    We didn't think we had the capability to do a meaningful,
          5    generic fire PRA and for the spent fuel pool there was no
          6    need to do a PRA at all.  There were some previous studies
          7    which showed that the risk of fuel damage was very low to
          8    start with.
          9              We tried to maintain defense in depth philosophy
         10    in dealing with containment.  Obviously, the containment
         11    can't always be closed during refueling operations. 
         12    However, we didn't want to give up totally on defense in
         13    depth so we wrote into the rule that the defense in depth
         14    attribute had to be considered when a containment alternate
         15    was being used.  In the analysis, we tried not to use any
         16    DBA assumptions at all.  We tried to be as realistic using
         17    information that was available to us in all our analyses.
         18              Treatment of uncertainties, we did a qualitative
         19    assessment of the uncertainties.  We used point estimates
         20    for all the risk values and when we looked at the value
         21    impact ratio being a thousand to one, we concluded that a
         22    detailed uncertainty analysis is very unlikely to make any
         23    changes to that conclusion so we didn't do anything further
         24    after we did our qualitative assessment.
         25              Finally, the safety goal subsidiary objectives
.                                                          46
          1    were used throughout.  We used that to assess where the
          2    current regulations put us, where the new regulations would
          3    put us and where we thought the industry was today.
          4              CHAIRMAN JACKSON:  Okay.
          5              MR. COLLINS:  Slide number 13 is a summary of what
          6    has changed since the rule last went out for public comment
          7    in 1994.  The hot shutdown and low power modes are no longer
          8    within the scope of the rule.
          9              We did a more rigorous regulatory analysis where
         10    we broke out the early phases in hot shutdown and low power,
         11    looked at the regulatory requirements applicable to them and
         12    concluded that, in fact, the safety functions were pretty
         13    well protected by existing requirements.  So we withdrew hot
         14    shutdown and low power from the scope of the rule.
         15              The previous rule also had a requirement for the
         16    containment closure was always required, containment closure
         17    capability.  In this rule, we try to be more flexible by
         18    allowing alternatives to containment, provided that the
         19    defense in depth consideration was maintained.
         20              The previous rule also made broad use of the
         21    single failure criterion.  It was very reminiscent of
         22    traditional design basis accident analysis type approach and
         23    we have tried to use risk insights to limit the scope of the
         24    single failure criterion and basically it now is a
         25    requirement for a backup RHR.
.                                                          47
          1              The licensee is allowed to set performance
          2    monitoring limits in this rule.  We simply define safety
          3    function limits related to water temperature, level and
          4    pressure.  The licensee is free to decide how they want to
          5    monitor those.  If they want to correlate some other
          6    parameter to those particular parameters, they are free to
          7    do that provided that we have approved the methods and
          8    criteria they are using.
          9              The fuel storage pool was not addressed in the
         10    previous version of the rule at all and the regulatory
         11    analysis which supports this rule, we think, is much more
         12    rigorous than supported the 1994 rule.  In summary, we think
         13    that it is much more flexible and risk informed than the
         14    1994 version.
         15              Slide 14 is the schedule that we are hoping to
         16    accomplish for rule implementation.  We would love to have
         17    Commission approval by the end of the month to go out for
         18    public comment.
         19              CHAIRMAN JACKSON:  We will work on that.
         20              MR. COLLINS:  Given that, it will take us a few
         21    days to get the rule actually published.
         22              CHAIRMAN JACKSON:  I've got the fast commissioner
         23    over here anyway.  It shouldn't be a problem on that side.
         24              MR. COLLINS:  We have allowed a 75-day comment
         25    period which traditionally manages to get extended to 90
.                                                          48
          1    days so we have shown 90 days on the schedule.  We plan to
          2    meet with the ACRS then in next April following resolution
          3    of public comments and we would have to go back to CRGR
          4    again.  We would anticipate doing that in May and then
          5    bringing the final rule to the Commission in August of next
          6    year.
          7              CHAIRMAN JACKSON:  Okay.  Any further comments or
          8    questions?
          9              Commissioner?
         10              COMMISSIONER DIAZ:  Should the other commissioner
         11    go first?
         12              CHAIRMAN JACKSON:  No, you're the senior
         13    commissioner.
         14              COMMISSIONER DIAZ:  Let's see if I can organize a
         15    couple of comments in here.
         16              First, I think it is very important that the staff
         17    focus attention in an area where I think we have been
         18    working up and down and I think that has been going on for
         19    years.  I think it is important that we realize where are
         20    the risks and that follows the philosophy that the present
         21    Commission is emphasizing in the area of risk assessment.
         22              I do want to have something clear.  That is that I
         23    believe that the fuel storage pool does not belong in this
         24    role.  I think that that is an issue --
         25              CHAIRMAN JACKSON:  That is going to be something
.                                                          49
          1    that the Commission will have to decide since it is in the
          2    paper.
          3              COMMISSIONER DIAZ:  That's correct.  That's it
          4    absolutely.  And the Commission will look at it.
          5              But I think we are mixing apples and grenades and
          6    I don't think we should do that.
          7              In the area of the overall -- in the rest of the
          8    rule, I think we need to give a little bit more
          9    consideration, or I will give consideration to the fact that
         10    we have been trying to be less prescriptive, trying to work
         11    in developing, you know, an environment in which things are
         12    done because they are right and this might be going the
         13    wrong way, although it might be necessary.  I think we need
         14    to put those two objectives and bring them together.  There
         15    is a long history now of we, the NRC, and the industry
         16    providing licensees with requirements that make the plants
         17    work better.  Those requirements that you have not taken
         18    into consideration, I understand the base for it, actually
         19    have made nuclear power plants safer through a long history
         20    of time now and, of course, we really never have a
         21    "accident" or release during shutdown.  That is a major
         22    issue.
         23              We actually have been allowing the industry to
         24    determine which systems are operable or must remain operable
         25    during certain conditions and which they can actually remove
.                                                          50
          1    from service.  So we have actually been making allowance in
          2    determining can you take this system out, can you do
          3    in-service inspection.  Essentially, this rule comes in and
          4    restricts that area significantly as a rule rather than as a
          5    voluntary process or as a process that might be really
          6    required through other means which could be generate letters
          7    and so forth.
          8              I just want to bring up one major thing that the
          9    NRC did many years ago, which is called ALARA, and which has
         10    served this Commission and this Commission has used for many
         11    years in assuring that we have minimal impact due to -- you
         12    know, from radiation to personnel, the public and the
         13    environment and that has worked well.  So I believe that we
         14    should take these things into consideration as we go into
         15    the rulemaking.
         16              But I want to thank the staff for a wonderful job.
         17              CHAIRMAN JACKSON:  I want to thank you for
         18    outlining your vote.
         19              [Laughter.]
         20              CHAIRMAN JACKSON:  Commissioner McGaffigan.
         21              COMMISSIONER McGAFFIGAN:  I am actually going to
         22    ask a question.
         23              I would comment that your earlier answer to the
         24    Chairman's question about where does this fall in
         25    prescriptive versus performance-based space, I actually
.                                                          51
          1    reading the rule find it quite far towards performance based
          2    and there are things that you have done since the last time
          3    in terms of alternatives to containment and it is very broad
          4    language.  The licensee shall minimize the frequency of
          5    fires during shutdown operations.  I mean, you are not
          6    telling them how to do it, you are telling them they shall
          7    do it and there may be some prescription in the reg guide
          8    but in looking at that continuum, I think they have made a
          9    larger step than perhaps the answer indicated towards
         10    performance-based rule.
         11              That is in response to Commissioner Diaz.  Now,
         12    let me ask my questions.
         13              One thing I noticed in the package that I haven't
         14    seen earlier in previous rulemaking packages is this Table 7
         15    safety goal decision guidance that apparently comes from the
         16    safety goal and it -- does this come up in other
         17    rulemakings, just as a matter -- I am just interested
         18    whether you do this matrix every time you propose a rule in
         19    reactor space?
         20              MR. HOLAHAN:  This, the regulatory analysis
         21    guideline, core damage frequency, additional containment
         22    failure probability?
         23              COMMISSIONER McGAFFIGAN:  Right.
         24              MR. HOLAHAN:  That is a screening criteria that is
         25    used for all -- actually for all generic issue screening,
.                                                          52
          1    both for generic letters as well as for things like
          2    rulemaking, and it is built into the regulatory analysis
          3    guidelines.  It is a screening step to identify which are
          4    issues that ought to move forward and then a risk analysis
          5    with a, you know, cost/benefit analysis done sort of as a
          6    second stage, so what Tim was showing was the second stage
          7    results.
          8              COMMISSIONER McGAFFIGAN:  So I should look forward
          9    to seeing this in every -- in almost every package that
         10    comes forward?
         11              MR. HOLAHAN:  Usually, you don't see that
         12    particular piece but that is the screening level.  Usually,
         13    you see the second level results.
         14              MR. KING:  Yes, right.
         15              That piece goes to CRGR when they review rules. 
         16    It doesn't always show up in the statement of
         17    considerations.
         18              COMMISSIONER McGAFFIGAN:  Right.
         19              MR. HOLAHAN:  But it has always been considered at
         20    some stage in the process.
         21              COMMISSIONER McGAFFIGAN:  And then we have been
         22    exploring through the afternoon some of the interactions
         23    between this rule and other rules.  There is a separate
         24    package up to us at the moment on the famous maintenance
         25    rule, Section A(3) and Alternative 3 that is offered in that
.                                                          53
          1    package is something that would not just change the "should"
          2    to "shall" --
          3              MR. HOLAHAN:  Right.
          4              COMMISSIONER McGAFFIGAN:  -- but address other
          5    issues and it doesn't sound unreasonable if we are going to
          6    move in the direction of risk-informed regulation that says
          7    that one of the advantages would be to provide a foundation
          8    on which other risk-informed regulation could build.  But
          9    among the disadvantages, it says such a rule would have
         10    broad impact on other current and proposed rules including
         11    the proposed shutdown rule and should thus be part of a
         12    separate rulemaking that would be used for risk-informed
         13    regulation in general.
         14              Can you explain that, what the impact of the
         15    possible Alternative 3 for the shutdown rule would be?
         16              MR. HOLAHAN:  Well, I think there is clearly an
         17    interrelationship.  I am not sure I would describe it
         18    entirely as negative.  From what Tim has said, you can see
         19    the most important aspects of this rule have to do with
         20    controlling the availability of equipment that is used to
         21    mitigate events and to the extent that the maintenance rule,
         22    the A(3) part of the maintenance rule also addresses
         23    availability of equipment, I think a strong A(3) which
         24    addressed both power operation and shutdown I think could
         25    accomplish that same function as the shutdown rule.
.                                                          54
          1              Now, I think the implications are in order to do
          2    that as part of the maintenance rule, you would have to
          3    build some infrastructure in the sense of, well, how would
          4    you use A(3), what sort of analysis would be done, does it
          5    require that there would be a PRA that was reviewed and
          6    approved?  There are a lot of ancillary questions that we
          7    are not quite ready to answer.
          8              But I think that functionally there is this
          9    overlap in terms of control of the availability of
         10    equipment.  Likewise, I think technical specifications
         11    control the availability of equipment and so there would be
         12    a considerable overlap between an A(3) and the current
         13    technical specifications.  So I think it is a powerful
         14    thought but it has a lot of implications to be sorted out.
         15              CHAIRMAN JACKSON:  Thank you.
         16              MR. HOLAHAN:  Thank you.
         17              MR. CALLAN:  Chairman, I would like to just make
         18    one comment at the end.
         19              You know, a common theme in this presentation is
         20    the Staff's view that there is a problem with our
         21    regulations that needs to be addressed and that the safety
         22    net that our regulations provide for shutdown operations is
         23    not sufficient.  That is the baseline.  What the staff is
         24    not saying is there is a compelling need in terms of
         25    licensing performance for a rulemaking.  You know, my view,
.                                                          55
          1    and somewhat anecdotally, is that the performance of the
          2    industry is actually better than the NUMARC 91.06
          3    guidelines.  I mean, the region I just left, I would say at
          4    least half of the licensees in that region have something
          5    equivalent to a shutdown risk meter concept with a very
          6    sophisticated war room during outages where risk is tracked
          7    almost hour by hour, without exaggerating.  As equipment is
          8    taken out of commission, the range of options are reviewed
          9    and adjustments are made daily.  Quite sophisticated control
         10    of risks during outages.
         11              So in terms of licensee performance, there isn't a
         12    compelling argument.  But none of that -- I shouldn't say
         13    none of that -- very little of that falls within the
         14    regulatory framework and that is the issue here.
         15              MR. HOLAHAN:  Absolutely.  I agree.  And one of
         16    the things we have done in these last six months is
         17    recognized that I think in the past we were in danger of
         18    writing a rule that would have been at odds with even the
         19    better licensee programs.  It would have required them to
         20    keep some set of books on technical specifications and maybe
         21    even distract them from their risk management approach.  So
         22    I think what we have constructed here is a rule which could,
         23    in effect, adopt and bless a program that Mr. Callan has
         24    described.  They wouldn't necessarily have to change that
         25    program.  It would simply draw it through the reference from
.                                                          56
          1    an administrative technical specification.  It would become
          2    the licensee's commitment to continue to carry out that
          3    program.  I think that is a way of taking advantage of the
          4    best features of an existing program.
          5              CHAIRMAN JACKSON:  Yes.
          6              COMMISSIONER DIAZ:  Are you convinced that none of
          7    our requirements, even if they are old, have captured this
          8    or have we actually forgotten to use them?  Because, you
          9    know, there are some that actually I could pick out from the
         10    book that might address this and not very long ago we
         11    actually put out a new one.
         12              CHAIRMAN JACKSON:  Okay, let him answer.
         13              COMMISSIONER DIAZ:  I was still talking.  I wasn't
         14    finished.
         15              So, you know, when you look at it, okay, and you
         16    look at what we just did with PRA and you look at some of
         17    the things, my question always goes back to the definition
         18    that we use in the book of any normal operating condition
         19    and it might have been captured.  I just want to be sure it
         20    was not captured someplace else.
         21              MR. HOLAHAN:  Okay.
         22              What I am convinced of is the Atomic Energy Act
         23    covers shutdown operations.  So the Agency has the power to
         24    regulate it.  There are other areas where the regulation
         25    either suggests or could be interpreted to cover shutdown
.                                                          57
          1    but it is not clear and it is certainly not the current
          2    staff and industry practice to interpret the regulation that
          3    way.  So part of what we would be doing here is, remember,
          4    the original objective is to become clearer on what the
          5    requirements are.
          6              COMMISSIONER DIAZ:  All right, thank you.
          7              CHAIRMAN JACKSON:  I would like to thank the staff
          8    for a very informative briefing today and it is clear from
          9    the quality of the briefing that you and the rest of the
         10    staff that have been associated with this project have spent
         11    many long hours of thought and consideration on this.  And
         12    as the overall safety and reliability of nuclear power
         13    reactors does generally continue to improve but pressures to
         14    improve economic performance continue, it is imperative as
         15    you have outlined here that if, where necessary to ensure
         16    protection of public health and safety and that operating
         17    and safety margins are maintained, that we promulgate
         18    regulations that are as risk informed and performance based
         19    as they can be.
         20              I think it is interesting, coming out of this
         21    discussion, for the staff to review as it is involved in
         22    resolving either other generic issues or other rulemakings,
         23    to review the extent to which voluntary licensee action is
         24    relied upon and where, if regulatory action is warranted,
         25    that it is not something that takes the licensee -- takes us
.                                                          58
          1    away from where that can satisfy what our needs are.
          2              If there is nothing more, we are adjourned.
          3              [Whereupon, at 3:18 p.m., the briefing was
          4    concluded.]
          5
          6
          7
          8
          9
         10
         11
         12
         13
         14
         15
         16
         17
         18
         19
         20
         21
         22
         23
         24
         25


Privacy Policy | Site Disclaimer