IN RESPONSE, PLEASE
REFER TO: M970506
May 22, 1997
MEMORANDUM TO: | L. Joseph Callan Executive Director for Operations |
FROM: | John C. Hoyle, Secretary /s/ |
SUBJECT: | STAFF REQUIREMENTS - BRIEFING ON PRA IMPLEMENTATION PLAN, (SECY-97-076), 2:00 P.M., TUESDAY, MAY 6, 1997, COMMISSIONERS' CONFERENCE ROOM, ONE WHITE FLINT NORTH, ROCKVILLE, MARYLAND (OPEN TO PUBLIC ATTENDANCE) |
The Commission was briefed by the NRC staff on the Probabilistic Risk Assessment (PRA) implementation plan. The Commission encouraged the staff to provide appropriate review mechanisms, utilizing both internal and external reviews, to ensure that NRC makes appropriate and consistent use of PRAs.
Additional staff guidance will be provided in the SRM on SECY-97-077.
cc: | Chairman Jackson Commissioner Rogers Commissioner Dicus Commissioner Diaz Commissioner McGaffigan OGC CFO CIO OCA OIG Office Directors, Regions, ACRS, ACNW, ASLBP (via E-Mail) PDR - Advance DCS - P1-17 |