Download WordPerfect File [TR5JA17B.WP5]
DEFENSE NUCLEAR FACILITIES SAFETY BOARD
January 17, 1995
MEMORANDUM FOR: |
|
G. W. Cunningham, Technical Director |
COPIES: |
|
Board Members |
FROM: |
|
J. T. Arcano, Jr. |
SUBJECT: |
|
Savannah River Site (SRS) - In-Tank Precipitation (ITP) Order Compliance
Review (November 30-December 2, 1994) |
- Purpose: This trip report documents a Defense Nuclear Facilities Safety Board
(DNFSB) technical staff (T. Arcano, M. Merritt, Outside Expert R. West) November
30-December 2, 1994, review of the Westinghouse Savannah River Company (WSRC) In-Tank
Precipitation Facility Order compliance program.
- Summary: The ITP facility is in the early stages of implementing continuing
adherence assessments into its Order compliance program. Several weaknesses in the program
were identified by DNFSB staff:
- Senior facility management appears knowledgeable of, but uninvolved in, Order
compliance efforts. This lack of involvement appears to have contributed to uneven
performance across the Order compliance functional areas reviewed by DNFSB staff. However,
the recently assigned WSRC ITP facility manager indicated that he will be more directly
involved in the Order compliance effort.
- The majority of the adherence Order compliance assessments sampled were not
adherence-based and in some areas were incomplete. Guidance for conducting assessments is
fragmented and is inadequate regarding the conduct of adherence assessments, especially in
view of the training provided.
- No adherence Order compliance assessment was conducted or is planned for U.S.
Department of Energy (DOE) Order 5480.31, Startup and Restart of Nuclear Facilities,
despite the fact that a Readiness Self-Assessment (RSA) and WSRC Operational Readiness
Review (ORR) had just been conducted.
- WSRC does not plan to assess compliance to DOE Order 5481.1B, Safety
Analysis and Review, despite the fact that ITP safety analysis documentation was
prepared to this Order.
- A review of the DOE Savannah River Office (SRO) Order compliance package for
DOE Order 5700.6C, Quality Assurance, revealed an incomplete and inadequate
product.
- Background: The ITP facility will separate high-level waste supernate into
concentrated high-level waste and low-level waste fractions. ITP is currently scheduled to
start up in June 1995. WSRC conducted its initial administrative (phase 1) Order
compliance assessment at SRS on a facility-by-facility basis from mid-1992 to mid-1993.
This approach was found to not be cost-effective since many common procedural controls are
used sitewide. A revised plan was established in the summer of 1993 to require assessment
of a mix of facility specific and sitewide requirements. This revised compliance effort
was accomplished at ITP in late 1993. As a prerequisite to ITP startup, an RSA was
conducted by ITP line management between June - July 1994 and serves as the baseline for
the ITP adherence (phase 2) Order compliance assessment. In May 1994 guidance was provided
to accomplish adherence assessments using the WSRC SCD-4 Manual, Operational Readiness
Functional Area Requirements. A comparison was made between the RSA and SCD-4
requirements, and additional "delta" assessments were conducted to satisfy the
new direction. Delta assessments were completed in August 1994. The SCD-4 Manual is the
source for the continuing adherence assessment program at ITP.
- Discussion: WSRC High Level Waste (HLW) Management personnel indicated that they
have assessed compliance to 45 of the 52 Orders of interest to the DNFSB which they
believe are applicable to ITP. (Discussion of the 7 Orders not assessed is provided in
Attachment 1.) This DNFSB staff review focused on the WSRC ITP Order compliance program
and sampled the resulting compliance packages for DOE Orders concerning training and
qualification, conduct of operations, quality assurance, radiological protection and
occurrence reporting.
Senior WSRC ITP line management is not directly involved in assessing Order compliance,
but rather, has delegated this effort to the Order compliance coordinator. This became
apparent during DNFSB staff discussions with management and their lack of participation
during the review. This lack of involvement by senior line management appears to have
contributed to uneven performance of assessments across the functional areas. However, the
recently assigned facility manager indicated that he will be more directly involved in the
Order compliance effort. Key issues noted by DNFSB staff are summarized below and the
details are provided in Attachment 1:
- WSRC Order Compliance Assessment Program Administration: Direction for
conducting compliance assessments is contained in two procedures in the WSRC DOE
Directives Administration Manual 8B, two procedures in the S4 Manual and one procedure in
the WSRC Management Requirements and Procedures Manual 1B. The guidance for conducting
administrative assessments is adequate. However, the guidance for conducting adherence
assessments lacks details for conducting assessments. Training requirements are lacking
for managers and assessors. The DNFSB staff believes these requirements may be necessary
based on the quality of many of the assessments reviewed, and the fragmentation of
assessment guidance. SCD-4 Manual criteria have been used to develop HLW Management
Division "Self-Assessment Cards" which form the basis of the continuing
adherence assessment program.
- Review of WSRC Order Compliance Assessment Results: A sampling of the Order
compliance packages revealed that:
- Phase 1 administrative Order compliance packages appeared to be in order, except for DOE
Order 5700.6C, Quality Assurance.
- The majority of the Phase 2 adherence Order compliance assessments sampled were not
adherence-based, but rather, were administrative in nature. In the areas of training and
quality assurance, these assessments did not fully address key requirements of DOE Orders
5480.20, Personnel Selection, Qualification, Training, and Staffing Requirements at DOE
Reactor and Non-Reactor Nuclear Facilities, and 5700.6C.
- No adherence Order compliance assessment was conducted or is planned for DOE Order
5480.31, Startup and Restart of Nuclear Facilities, despite the fact that an RSA
and WSRC ORR had just been conducted.
- The WSRC ITP continuing adherence assessment program has not yet been fully implemented.
The limited sample of six conduct of operations assessments available in the areas
reviewed was mostly not adherence-based.
- WSRC has indicated that DOE Order 5481. 1B, Safety Analysis and Review, is not
applicable since the Order has been cancelled by DOE Order 5480.23, Nuclear Safety
Analysis Reports, for nuclear facilities. However, the ITP safety analysis report, Additional
Analysis For Defense Waste Processing Facility (DWPF) Feed Preparation by In-Tank
Processing, WSRC-SA-15, Revision 5 of October 1994, is written in accordance with DOE
Order 5481.1B. Because no Basis for Interim Operation (BIO) has been written per DOE Order
5480.23, it appears that WSRC should either produce a BIO or assess compliance to DOE
Order 5481.1B.
- WSRC Oversight of ITP Order Compliance Effort The DOE SRO Program Plan for
High Level Waste Order Compliance Program, issued in March 1994, calls for WSRC to
conduct oversight and independent verification of the High Level Waste Order compliance
process. Further, it calls for the WSRC Quality Assurance organization to conduct and
document a formal assessment which evaluates the process, procedure adherence, and the
basis and validity of conclusions. WSRC personnel indicated that the only oversight of the
Order compliance program was conducted by the WSRC ORR board, and that this did not meet
the requirements of the Program Plan.
- DOE SRO Oversight of WSRC Adherence Order Compliance: No DOE program exists or
is planned to oversee WSRC ITP continuing adherence assessments.
- DOE SRO Order Compliance Program: DNFSB staff conducted a limited sampling of
the SRO Order compliance program. Compliance assessment data for DOE Order 5700.6C, Quality
Assurance, was reviewed and discussed with the DOE person responsible for the
assessment. The person responsible was unable to describe the difference between a phase 1
administrative assessment and a phase 2 adherence assessment. This person was also unable
to describe the contents of the DOE Order 5700.6C compliance package, which was confusing
at best. (It should be noted that this package had been fully approved, to the level of
DOE SRO Assistant Manager for High Level Waste.) The DOE SRO HLW Order compliance
coordinator indicated that DOE personnel would be retrained on Order compliance, and that
all DOE SRO Order compliance packages would be reviewed again for adequacy. DNFSB staff
will sample the DOE packages after DOE SRO has convinced itself of their adequacy.
- Future Staff Action: The DNFSB staff will:
- Follow-up on the implementation of the WSRC continuing adherence assessment
program.
- Sample DOE SRO Order compliance packages after DOE SRO has assured itself of
their adequacy.
- Continue to review other Order compliance packages in conjunction with ongoing
DNFSB staff functional area reviews.
Attachment 1 - Detailed Comments on WSRC ITP Order Compliance Program
- Assessment Program Administration: The basic documents for
conducting compliance assessments are WSRC DOE Directives Administration Manual 8B,
Procedures DAP-5, Conduct of WSRC Compliance Assessment - Phase I and DAP-6, Conduct
of WSRC Compliance Assessment - Phase II. DAP-5 provides a methodology for conducting
administrative assessments and is supplemented at the High Level Waste (HLW) Division
level by S4 Manual Procedure ADM 30, Regulatory Requirements Compliance Control
Procedure. The DAP-6 procedure is general in nature while specific guidance for the
assessment program is contained in the WSRC Management Requirements and Procedures (MRP)
Manual 1B, Procedure MRP 5.15, Self-Assessment. MRP 5.15 is also supplemented by a
HLW S4 Manual Procedure ADM-40, Continuous Self-Assessment Program.
SCD-4 Manual criteria have been used to develop HLW Management Division
"Self-Assessment Cards" which form the basis of the continuing adherence
assessment program.
The WSRC ITP Order compliance program addresses 45 of the 52 Orders of Interest to the
DNFSB. WSRC sitewide Order compliance efforts have resulted in the development of
administrative Compliance Assessment and Implementation Reports ("CAIR
Packages") for the majority of these 45 Orders. The 7 Orders which WSRC believes are
not applicable to ITP include: DOE Orders 5400.3- Hazardous and Radioactive Mixed Waste
Program (cancelled), 5480.5- Safety of Nuclear Facilities (cancelled), 5480.6- Safety
of DOE-Owned Reactors, 5480.25- Safety of Accelerator Facilities, 5480.30- Reactor
Design Criteria, 5481.1B- Safety Analysis and Review (superseded by DOE Order
5480.23 for nuclear facilities), and 5632.11- Physical Protection of Unclassified,
Irradiated Reactor Fuel in Transit (cancelled).
ITP "Order compliance upgrade reports" were to be developed to amplify the site
compliance CAIR packages with information specific to ITP. However, for DOE Orders for
which there were no company generic CAIR packages developed, ITP facility was to develop
"stand alone" administrative Compliance Assessment Packages (CAPs).
- DOE Order 5480.20, Personnel Selection, Qualification, Training, and Staffing
Requirements at DOE Reactor and Non-Reactor Nuclear Facilities: The Training
Implementation Matrix (TIM) has scheduled ITP compliance with DOE Order 5480.20 except for
continuing training (December 31, 1994) and management and supervisory personnel training
requirements (December 31, 1996). There are no outstanding Requests For Approvals (RFAs)
(formally indicating noncompliance) for this Order. The DNFSB staff Order compliance
review focused on the following areas:
- Certification Program. The facility intended to certify
operators and supervisors after the completion of the self-assessment. A decision was made
in August 1994 as to the method and positions to certify. As a result, no RSA assessment
was made of this topic and no delta assessment was conducted although it would have been
appropriate.
- Qualification Program. A WSRC assessment to verify that
requirements are met before qualification is granted only checked that the qualification
cards contained this requirement and did not verify that it was being adhered to. Another
WSRC assessor did make a thorough review of qualification cards to ensure that they were
completed properly and found only one deficiency. A third WSRC assessor interviewed
operators and supervisors and made appropriate remarks about the level of knowledge.
- Maintenance Personnel Qualifications. No assessment
requirement could be found for technician and maintenance personnel qualification and
maintenance personnel training on safety-related systems which are considered to be
significant areas of training requiring assessment.
- On-The-Job (OJT) Performance. WSRC adherence assessment
consisted of only observing OJT for a general operator (the initial qualification position
which cannot perform any system operations). The line of inquiry for the assessment
required observation of the training to ensure that it is related to job duties. There
were no comments concerning the performance of the training and therefore, the assessment
was not adherence-based.
- Classroom Training. Similar to the OJT assessment, the
line of inquiry for classroom training required observation to ensure training is job
related. The assessor found the observed training to support job responsibilities. Again,
there was no indication of evaluation of the effectiveness of the training; his assessment
was not adherence-based either.
- Continuing Training. No WSRC assessment was conducted
during the RSA because the continuing training program had not started. However, a delta
package was generated in this area which reflected the observance of chemical cleaning
training and found that there was continuity between the initial and the continuing
training program. This review of one training session does not constitute a review of the
continuing training program. The WSRC ongoing assessment program is to be in place by the
end of December and a review of the elements of this program by WSRC would be appropriate
to ensure the planned program meets DOE requirements.
- Continuing Adherence Assessment Program. Despite a
briefing that the continuing assessment program for training had been initiated, it was
found that the functional area manager did not have a smooth copy of the assessment
requirement cards and had only a rough draft of an assessment schedule without all of the
required information filled in.
- DOE Order 5480.19, Conduct of Operations Requirements for DOE Facilities:
There are no outstanding RFAs for this Order.
- Equipment Control/System Status. An RSA assessment of
status change authorization and reporting did not comment on the specific criteria
provided, but instead commented on other aspects of the task observed. A review of
checklists commented on the availability of the lists but did not indicate that the
performance of a checklist had been observed. Both of these reviews had been done by
personnel subcontracted to WSRC.
- Round Sheets. Although there were multiple evaluations of
roundsheets, most reviews were not adherence-based. One review contained comments about
the availability of the sheets but no observation of use of the sheets. Another line of
inquiry required verification of proper supervisory review of completed round sheets. This
assessment did not comment about the lack of operator or supervisor comments about
out-of-specification readings which were apparent when DNFSB staff reviewed copies of
logsheets attached to the compliance assessment. These assessments had been conducted by
subcontractor personnel.
- Continuing Adherence Assessment Program. A continuous
assessment program for the conduct of operations functional area had begun in September.
Only six assessments were scheduled to be completed at the time of the visit. The
lockout/tagout assessment card sets forth the monthly inspection requirements of the 8Q
Safety Manual Procedure 32 basic program direction. The assessment had not recorded all
the data required by the card and reference procedure. No card had been developed for the
annual inspection required by the basic procedure.
The assessment of shift routine relied excessively on paperwork review. This review noted
problems with the tagging of four activated alarms. The corrective action was to correct
the noted deficiencies, but no action was taken to determine the full extent of the
problem or to develop programmatic corrective action.
A review of equipment and piping labeling had lines of inquiry to interview personnel, but
did not include an inspection of the facility so that it was not adherence based.
A review of temporary modifications required verification of numerous items but it was
unclear what action the assessor took to perform the verification and whether it was
adherence based. The card required the review of 3 modifications which found problems with
each. The corrective action was to correct the specific problems found, but no action was
taken as a result of a 100% noncompliance rate found during the assessment.
- DOE Order 5480.31, Startup and Restart of Nuclear Facilities: A
phase 1 assessment, conducted in early 1993, compared the Order with two company
documents, WSRC Procedure Manual 12Q, WSRC Operational Readiness Review Manual, and
WSRC Procedures Manual E, WSRC Startup and Restart Manual. Two Compliance Schedule
Approvals were submitted, approved and completed. Subsequent to this review the two
Manuals were combined into the 12Q Manual. The High Level Waste Management Manual S4
Procedure ADM 30, High Level Waste Management Regulatory Requirements Compliance
Control Procedure, requires a review if a site level manual is revised to determine if
there is any impact of the changes on DOE Order administrative compliance. However, no
evidence of the required review was produced. No adherence assessment was conducted or
planned for this Order despite the fact that a self-assessment had just been completed and
the WSRC ORR was conducted in October-November 1994. There are no outstanding RFAs.
- DOE Order 5700.6C, Quality Assurance
- Phase 1 Administrative Compliance Assessment. No WSRC SRS
sitewide administrative Compliance Assessment and Implementation Report (CAIR) was
generated for DOE Order 5700.6C, nor is one planned for development. A WSRC HLW Management
Division Compliance Assessment Package (CAP) was generated. However, it only provided the
sitewide implementation plan for DOE Order 5700.6C; WSRC did not present administrative
compliance information for this Order although this effort had apparently been conducted.
The implementation plan called for sitewide implementation of the Order by September 30,
1994, including the verification of compliance. However, DOE-SRO advised WSRC that with
the advent of 10CFR830.120, Quality Assurance, "...another assessment to the
Order would be neither beneficial nor cost effective." There are no RFAs for this
Order.
- Phase 2 Adherence Assessment Baseline. ITP readiness-self
assessment quality assurance criteria were structured around the 18 basic requirements of
NQA-1, Quality Assurance Program Requirements for Nuclear Facilities: The adherence
baseline was formatted to assess DOE Order 5700.6B, rather than the 10 criteria of DOE
Order 5700.6C. As a result, the baseline assessment was very inefficient in addressing the
10 criteria of DOE Order 5700.6C.
The majority of the assessments sampled were administrative in nature, rather than
adherence-based. A discussion of the administrative Order compliance effort follows:
- Personnel Training and Qualification. Assessments performed were
either extremely limited in their scope or were not adherence-based. Although 14
self-assessment criteria were used to assess compliance to Criterion 2 of DOE Order
5700.6C, only one of these criteria actually addressed the Order requirement that
"Personnel shall be trained and qualified to ensure they are capable of performing
their assigned work." However, the scope of this assessment was extremely limited,
and as a result appears to have fallen short of adequately representing the status of the
facility population.
In general, the assessments looked at the procedural aspects of training and qualification
(e.g., did personnel attend training) rather than its product (e.g., knowledgeable and
capable watchstanders). One assessment criterion called for a training and indoctrination
program to be established per DOE Order 5480.20. This was assessed by WSRC to be
acceptable by determining that "WSRC procedures have established a training and
indoctrination program that fully incorporates the requirements of DOE Order 5480.20 for
ITP," without any review of the training program indicated.
- Management Assessment. DOE Order 5700.6C requires that
"management periodically assess the integrated quality assurance program and its
performance such that problems that hinder the organization from achieving its objectives
be identified and corrected." However, the only RSA assessments in this area were
administrative in nature: one assessment verified that a management assessment program was
procedurally required; the other determined that management assessments were being
performed on a periodic basis, based on management assessment record review. The WSRC
administrative compliance baseline did not establish that management assessments were
identifying and providing the catalyst for correcting problems.
- Independent Assessment. The majority of assessments sampled in this
area were administrative-based vice adherence-based and were very limited in their
sampling. For example, the self-assessment criteria that "Independent assessments
should focus on improving items and processes by emphasizing the line organizations
quality achievements" was performed by sampling only one assessment report and found
that this one report focused on improving items and processes. However, the assessment did
not look to see if the effect of the report was to stimulate improvement.
c. |
|
Continuing Adherence Assessment Program. The
Continuing assessment program has not yet been implemented for quality assurance. |
- DOE Order 500.3B, Occurrence Reporting and Processing of Operations
Information: The Phase 1 administrative Order Compliance Assessment
appeared to be satisfactory; The phase 2 adherence assessments were a mix of interviews,
document and record reviews, and observation of critiques which appeared appropriate for
this Order. There are no outstanding RFAs.