DEFENSE NUCLEAR FACILITIES SAFETY BOARD
December 1, 1993
MEMORANDUM: |
|
G. W. Cunningham, Technical Director |
|
|
|
COPIES: |
|
Board Members |
|
|
|
FROM: |
|
A.K. Gwal |
|
|
|
SUBJECT: |
|
Defense Waste Processing Facility (DWPF) Site Visit, September 1-3, 1993. |
- Purpose: This memorandum provides a report of the DNFSB staff visit-to the
Savannah River Site to review fire protection, electrical, and control systems of the
DWPF.
- Summary: The review identified the following potentially significant issues and
observations:
- Distributed Control System (DCS): Several design modifications to the DCS were
implemented to inhibit lightning strikes, reduce network interference, protect the DCS
from loss of power, and reduce ground resistance. However, the DNFSB staff is concerned
about the design, management, and handling of alarms at DWPF. There are a large number
(approximately 12,000) of monitoring points out of which 2100 are process-alarms, and when
activated simultaneously, may confuse the control room operator and will prevent the
operator from timely assessing and addressing the critical issues.
- Loss of Power: During review of the loss of power incident of July 1993 on DWPF, it was
observed that there is no redundancy in the instrument busses. DWPF is in the process of
correcting this deficiency.
- Battery Room Ventilation System: Design of the ventilation system in the battery room of
the main processing building may not be adequate for the removal of hydrogen as required
by industry standards. DWPF is considering a design modification to resolve this issue.
- Glass Waste Storage Building (GWSB): DWPF performed a calculation for GWSB vault heat-up
versus time and determined that the vault will reach a steady state temperature of 305·F
based on the average of winter and summer conditions and total loss of ventilation.
Analysis results show that reinforced steel and concrete safety factors for stresses are
within allowable limits at 305·F. It was observed, however, that if only summer average
temperatures are postulated, a steady state temperature of 361·F is reached in the vault,
then the safety factor may be less than allowed by code. DWPF will evaluate this case and
submit the analysis to DNFSB for review.
- Fire Protection System: Emergency lighting is neither seismically qualified nor
seismically supported. In addition, WSRC/DOE intends to provide water sprinkler systems in
several areas containing electrical equipment, including the main control room. The DNFSB
staff is concerned that water intrusion into electrical panels could result in electrical
shorts and spurious operations.
- Background: On September 1-3, 1993, DNFSB staff members Ajit Gwal and Dan Ogg
visited the DWPF to review the fire protection system; loss of power incident of July 13,
1993, and station blackout analysis; distributed control system (DCS); and GWSB systems.
The staff also discussed the open technical issues from previous review on April 21-23,
1993 of the facility's electrical system. An expanded listing of the topics and issues
covered is attached to this report (Attachment A).
- Discussion: Attachment B lists the
handouts distributed by DOE/WSRC during the briefing to the DNFSB staff. DNFSB staff
observations and findings are as follows:
- Distributed Control System (DCS): Several design modifications to the
distributed control and monitoring system were implemented at DWPF to improve their
reliability. These included installation of a fiberoptic network, static charge
dissipation system, and uninterruptible power supply (UPS) fed from a set of batteries and
two a-c sources, the addition of a ground ring conductor connected to chemical grounding,
and the isolation of the DCS electrical supply system. These modifications will reduce
network interference, inhibit lightning strikes, protect the DCS from loss of power,
eliminate equipment interference, and reduce ground resistance.
Control of most processes is conducted from the Central Control Room (CCR) in Building
210-S. This building is not a seismic structure. There also exists an Emergency Control
Room (ECR) on the-second level, east corridor of the Vitrification Building in the same
room as the Field Operating Station (FOS) 1. The ECR is located within a seismically
qualified structure. Its purpose is to allow the vitrification process to be shut down in
a safe and orderly manner in an emergency situation, such as the unavailability of the CCR
due to damage done by a tornado or earthquake. All the safety systems have been hardwired
from the CCR to the ECR. A pinch-off circuitry is installed to eliminate any spurious
operation due to hot shorts at the CCR. The function of this circuitry is to electrically
isolate certain DCS components of the CCR from the ECR. This is a very desirable feature
because the entire process can be controlled from the ECR during a tornado or seismic
event.
The staff is concerned about the design, management, and handling of alarms at DWPF. Of
the approximately 12,000 monitoring points (measurement points, interlocks, and alarms) at
the DWPF about 2,100 are process alarms. The high number of alarms activated
simultaneously may confuse the control room operators during certain accident scenarios.
For example, during the loss of power event of July 13, 1993, approximately 300 alarms
were activated simultaneously and there was a great deal of confusion among control room
operators, thus preventing the operators from assessing and addressing the critical issues
in a timely manner. DWPF has since instituted an Alarm Management Program based on short,
intermediate, and long-term needs. They have used outside experts (e.g., Dr. Cecil Smith)
to prepare alarm selection/validation guidelines and to provide direction and assistance
in handling and managing alarms. However, it was observed that the recommendations by
outside experts had not been systematically implemented. No documents exist to confirm the
implementation of outside experts' recommendations. The DNFSB staff will continue to
monitor the Alarm Management Program.
- Station Blackout Analysis and Loss of Power Incident of July 13, 1993: WSRC at
DWPF has performed an analysis for power loss accidents and determined that loss of power
alone would not cause accidents and that no credible accident sequences would result in a
station blackout. During power outages the cooling water, steam, air purge, CO2 purge, and
ventilation systems would be lost. However, backup purging systems and a backup system are
available to safely shutdown the process and plant.
The DNFSB staff reviewed the effect of the loss of power incident of July 1993 at DWPF. It
was observed that the redundant instrument busses are fed from the same load center.
Therefore, when this load center lost power, flow instrumentation for both HVAC supply
units and both chillers were lost. DWPF had previously discovered this design flaw, and is
in the process of correcting this deficiency as a priority item.
The DNFSB staff also reviewed the engineering and operations lessons-learned and
recommendations from the July 13, 1993 power loss incident. The staff will continue to
follow the implementation of recommendations.
- Battery Room Ventilation System: Design of the ventilation system in the
battery room of the main processing building may not be adequate for the removal of
hydrogen as required by industry standards. The staff is concerned that hydrogen generated
by the batteries may accumulate and create a potential for explosion when HVAC is
non-operational in the battery room. There is neither a local or remote indicator nor an
alarm or a flow switch to alert plant operators to a failure of battery room exhaust. WSRC
is considering a design modification to resolve this issue. DNFSB staff will review the
design modification when available.
- Glass Waste Storage Building (GWSB): The Glass Waste Storage Building is
designed for safe handling and interim storage of filled glass waste canisters while they
await transfer to a permanent storage location. The GWSB is designed to store 2,300
stainless steel canisters. There are four major areas inside the GWSB; the storage vault,
the operating area, the air inlet shafts, and the air exhaust shafts. The storage vault
and the below grade portion of the air inlet and exhaust shafts are designed to withstand
seismic events; the remaining system above grade (e.g., HVAC, electrical system, and
offices) is a non-seismic design. The GWSB vault has been designated a safety class item.
The safety function of the vault is to maintain its integrity following a design basis
earthquake to preclude damage to the stored waste canisters. It is also required that the
vault must perform this safety function with long-term loss of cooling. WSRC has performed
a calculation for GWSB vault heat-up versus time assuming total loss of ventilation and
determined that the vault will reach a steady state temperature of 305·F based on the
average of winter and summer conditions. Analysis results show that the safety factor
above code stress for reinforced steel and concrete are 1.06 and 2.26, respectively.
It was observed, however, that if only summer average temperatures are postulated, a
steady state temperature of 361·F would be reached in the vault and the safety factor
will be less than allowed by code. In this case the vault may not remain intact and may
not perform its safety function. This was discussed with DWPF representatives and they
have committed to evaluate this condition and submit the results to the DNFSB for review.
- Emergency Lighting: In the event of an earthquake, emergency lighting is needed
for personnel egress from the facility. The DNFSB staff made the observation that
emergency lighting equipment is neither seismically qualified nor seismically supported.
WSRC will evaluate this condition.
- Diesel Generator (DG) Loading: Strip chart recorder data for diesel load
sequencing were reviewed to determine diesel generator adequacy for accepting load and
voltage regulation. These data are based on the operation of an existing diesel generator
loaded to approximately 50%. Based on anticipated design modifications, as stated by DWPF
electrical personnel, the DG may be loaded to 99.9% of its full capacity. Therefore, DG
load sequencing and voltage regulations are to be re-tested. The DNFSB will review new
test/calculated data for DG adequacy to accept safety loads and perform its safety
functions.
- Fire Protection System: DWPF is classified as a moderate hazard facility. DWPF
was designed to meet DOE's older General Design Criteria in Order 6430.1 and the recently
revised fire protection Order 5480.7 (now 7A).
- Active systems (e.g., automatic wet pipe sprinkler system, dry pipe sprinkler system,
CO2,. water spring system, deluge sprinkler system, aqueous film forming foam system, and
Halon system), passive systems and components (e.g., fire doors, penetration levels, fire
dampers), and special fire consideration for facility construction are utilized at DWPF.
Fire detection and alarms systems include heat detectors, smoke detectors, infrared and
line detection by thermistor cable.
The fire protection system is deficient in many areas, as indicated in various audits and
independent reviews. DWPF has initiated a design modification project (PS-4620) to resolve
the fire safety audit findings, Fire Hazards Analysis findings, fire protection oversight,
Factory Mutual findings, Halon replacement/decommissioning, and various independent review
recommendations. Implementation is divided into two stages. Stage 1 consists of design
modification and implementation required before radioactive startup, and Stage 2 consists
of modifications not required before radioactive startup. The DNFSB staff will monitor the
modification and implementation activity.
- Fire Pump/Motor (electrical and diesel driven). Technical review could not be performed
due to lack of documents-for cable sizing and motor design and electric circuit breakers.
- Halon versus water in the control room. WSRC intends to provide water sprinkler systems
in lieu of Halon systems in severa1 areas containing electrical equipment, including the
central control room. The staff is concerned that water intrusion into electrical panels
could result in electrical shorts and spurious operations, thereby making it difficult to
control the plant from remote control panels. DNFSB staff will monitor resolution of this
concern.
- Rosemount Transmitters: The DWPF process system utilizes a large number
(400-500) of Rosemount transmitters (RT). Some of the T models used at commercial nuclear
plants were found to be defective and are addressed in NRC IE bulletins. A list of all the
RTs used at DWPF was requested by the DNFSB staff so that an evaluation can be performed
of its adequacy to perform the safety/operational function.
Attachment A
Topics and Issues at DWPF
Distributed Control System:
- System description, hardware, software
- Power supply, cable and raceways
- Alarm and alarm reduction program
Station Blackout Analysis:
- Loss of power incident of July 13, 1993 and root causes
- Any proposed design modification to prevent recurrence of the above loss of power
- Various scenarios of loss of power
Fire Protection System:
- Fire detection system
- Fire pump design details (diesel-driven/electric-driven)
- Water supply system and all its components
- Independent reviews of fire protection program
- DOE Order compliance and any exemption requests
- Factory Mutual Research Corporation reports
- Halon versus water in the control room
Glass Waste Storage Building:
- System description
- Temperature monitoring system
- Hot spots in the building
- Cables and raceway routing
- Alarm systems
Open Items From previous DNFSB Staff Reviews:
- Emergency lighting
- Cable pull-bye
- Blown fuse alarm
- Alarm or a flow switch for loss of battery room ventilation
- Station blackout analysis documentation
Attachment B
Handouts Used by DOE/WSRC During the Briefing on
September 1-3, 1993 at DWPF
- Distributed Control System (DCS) and Improvements to DOE
- DWPF Applications Software
- DWPF Alarm Management Program
- DWPF Electrical Systems
- Power Outage in DWPF Accidents
- DWPF Loss of Power Incident effect on DWPF
- Fire Protection System Description
- Project S-4620 - Fire Improvements and Design Modifications
- DWPF Fire Protection - Independent Reviews
- DWPF Fire Protection DOE Order Compliance
- Glass Waste Storage Building
- Thermal Effects on the Glass Waste Storage Building Pollowing Long-term Loss of Cooling