[DNFSB LETTERHEAD]
June 12, 2003
The Honorable Spencer Abraham
Secretary of Energy
1000 Independence Avenue, SW
Washington, DC 20585-1000
Dear Secretary Abraham:
The Defense Nuclear Facilities Safety Board
(Board) and its staff have been evaluating the adequacy of the safety bases for
the K-Area Material Storage (KAMS) facility, Building 235-F, and FB-Line at the
Savannah River Site. This review is
part of an overall safety assessment undertaken in response to the Public Law
107-314, Section 3183, Study of Facilities for Storage of Plutonium and
Plutonium Materials at Savannah River Site.
In the enclosed report, the Board’s staff
has identified several issues that require clarification or action by the
Department of Energy (DOE) to ensure that these facilities will be adequate for
their storage mission. The Board is
continuing to pursue the overall safety assessment mandated by Public Law
107-314, Section 3183, but believes these issues merit near-term DOE attention. The presently defined mission and the
associated safety bases for some of these facilities do not appear to be
consistent with the long-term storage activities planned by DOE. In particular, Building 235-F was
anticipated to be shut down in the near future, but now is planned to be used for
long-term storage and related operations.
Future activities will require significant new analysis and physical
modifications to ensure safe operation, as required by DOE directives. Additionally, the enclosed staff report
notes:
The enclosed staff report discusses these
issues in more detail. Pursuant to 42
U.S.C. § 2286b(d), the Board
requests a report within 60 days of receipt of this letter that informs the
Board of actions or further evaluations that DOE may undertake on the above
issues.
Sincerely,
John T. Conway
Chairman
c:
The Honorable Jessie Hill Roberson
Mr. Mark B. Whitaker, Jr.
Enclosure
DEFENSE
NUCLEAR FACILITIES SAFETY BOARD
Staff Issue Report
May 7, 2003
MEMORANDUM FOR: J. K. Fortenberry,
Technical Director
COPIES: Board Members
FROM: R. Kasdorf
SUBJECT: Safety Bases Review of Plutonium Storage and
Support Facilities at Savannah River Site
In Public Law 107-314, Section 3183, Study of
Facilities for Storage of
Plutonium
and Plutonium Materials at Savannah River Site, Congress tasked the Defense Nuclear
Facilities Safety Board (Board) to conduct a study of the adequacy of the
K-Area Material Storage (KAMS) facility and related support facilities, such as
Building 235-F at the Savannah River Site (SRS) for the storage of defense
plutonium and defense plutonium materials in connection with the Department of
Energy (DOE) fissile materials disposition program. This report documents a portion of the ongoing review being
conducted by the Board’s staff to evaluate the adequacy of the safety bases for
this planned plutonium storage mission for KAMS, Building 235-F, and FB-Line.
The DOE contractor at SRS either has
submitted or is in the process of submitting documented safety analyses (DSAs)
to the DOE Savannah River Operations Office (DOE-SR) for these facilities to
comply with Title 10, Part 830 of the Code of Federal Regulations (10 CFR Part 830), Nuclear
Safety Management. These safety bases do not account for some
of the future activities that will be needed to support the planned long-term
storage mission. Building 235-F is
being studied for increased capacity for storing plutonium packaged in
accordance with DOE-STD-3013, Stabilization, Packaging, and Storage of Plutonium-Bearing Materials; addition of a plutonium stabilization and
repackaging capability; and limited sampling activities. None of these activities are addressed in
the approved Safety Analysis Report for Building 235-F. The safety basis for FB-Line does not reflect
the plutonium oxide stabilization process being added, although the staff
expects that the existing safety basis controls will be sufficient. Additionally, the duration of the planned
storage mission for KAMS significantly exceeds the 10 years originally
expected. DOE-SR recognizes that the
safety basis for these facilities must be changed to support the planned
long-term plutonium storage mission.
K-Area Material Storage Facility. The
draft DSA for this facility has been submitted to DOE-SR for approval. The Board’s staff reviewed this draft
document since it was pertinent to the mission of the facility for long-term
storage of plutonium materials. The
facility is currently operating using a Basis for Interim Operation (BIO) as
its safety basis. The BIO does not
authorize storage of the quantity of plutonium that would be required should
DOE decide to consolidate all the excess plutonium from the DOE complex at
SRS. The draft DSA is based on a
presumption that any material release in the facility has unacceptable
consequences.
Accordingly, the draft DSA requires
plutonium to be stored in DOE-STD-3013 containers enclosed in Type B shipping
containers meeting 10 CFR Part 7 1, Packaging and Transportation of Radioactive Materials, such as 9975 shipping containers. The safety basis of this facility does not
allow opening containers in the facility, nor does it provide for any
inspection of the contents other than for Material Control and Accountability,
which does not require container seals to be broken.
The event with the greatest offsite
consequences is postulated to be a major fire that jeopardizes the integrity of
the shipping containers, potentially releasing plutonium to the
environment. The majority of the controls
identified in the draft DSA relate to protection against such fires. The fire thermal analysis performed in
support of the draft DSA postulates two bounding fire scenarios that determine
the safety controls.
Building 235-F. The
safety basis for Building 235-F was prepared in 1989 using then-applicable DOE
requirements. This document has been
revised several times and was supplemented by a hazard analysis performed in
December 2002. The combined set was
approved by DOE-SR in January 2003 as a rule-compliant DSA.
The original 1989 safety basis used
Management Oversight Risk Tree methodology for identification and analysis of
the hazards. This approach is not
consistent with the methodologies recommended by the safe harbor of 10 CFR Part
830 (i.e., DOE-STD-3009-94, Preparation Guide for Nonreactor Nuclear Facility
Safety Analysis Reports), nor
is it consistent with current SRS standards.
Although this document was supplemented by a hazard analysis, the
combined safety basis is still based on a methodology that is inconsistent with
the safe harbor because it does not analyze operational occurrence using a
deterministic approach. Instead, a
frequency-based cutoff is used to screen out accident scenarios. Additionally, the unmitigated accident
analysis used for identification and classification of safety controls calculates
consequences using “average” or “best estimate” values of the parameters
crucial to the dose estimates. Finally,
the consequences to the public are calculated in terms of person-rem as opposed
to the maximum dose to a member of the public at the site boundary for
unmitigated releases. Presenting
consequences in this manner was consistent with the DOE guidance in 1989 but is
not consistent with current requirements provided in the safe harbor of 10 CFR
Part 830.
The fire suppression system in the facility
has been deactivated and removed. Only
a small portion of the facility is covered by a tire detection and alarm system
(mainly the storage vaults). During a
walkdown in the facility, the staff observed a significant amount of
combustibles (contaminated high-efficiency particulate air filters, plastic
boxes, and cables) adjacent to a material storage vault. Reducing or eliminating extraneous
combustible materials in the facility would reduce the likelihood and
consequences of a fire.
The staff was informed that a significant
amount of plutonium-238 (more than 700 grams) is deposited in ducts or cells in
the Plutonium Fuel Form facility and could be subject to release during a tire
or seismic event. The contractor
considered the plutonium-238 holdup the most significant hazard in the
facility. Consideration should be given
to decontaminating the areas with plutonium-238 holdup to reduce the risks
associated with its potential release.
The ventilation system exhaust is designated
as safety significant to confine airborne contaminants and direct them away
from the facility workers. As noted
above, there are many areas of the facility that are not covered by a tire
detection and alarm system. Workers
would be notified of a fire in the facility by the alarm annunciation
system. However, the facility’s Fire
Hazards Analysis identifies areas that are not covered by an audible alarm
annunciation system (i.e., the public address system). The Nuclear Incident Monitors (also known as
the Criticality Alarm System), which will likely be required for future
plutonium operations, have been removed.
FB-Line Facility. The
safety basis for FB-Line activities is documented in a Safety Analysis Report
that the contractor considers to meet the requirements of 10 CFR Part 830 and
its safe harbor provisions. This
document, however, has weaknesses similar to those discussed earlier for the
Building 235-F safety basis (e.g., it lacks identification of safety controls
for operational events that have a very low probability of occurrence). There is a difference from Building 235-F,
however, in that FB-Line has a short mission and is planned to be deactivated and de-inventoried in 2005.
The entire fire detection and alarm system
for FB-Line was deactivated and removed due to the extensive modifications that
would be needed to meet applicable standards.
Because of the relatively short operational life expectancy of the
facility, the contractor decided not to pursue such upgrades, and has instead
taken other compensatory measures in an effort to avoid fires. A senior fire inspector monitors shiftly to
identify conditions (e.g., excessive transient combustibles, fire initiating
activities) which need to be corrected or controlled to prevent fires from
becoming a significant hazard to the public and the workers.