Licensing Schedule for the Mixed Oxide Fuel Fabrication Facility
The schedule in the following table is subject to change. It is based on the assumption that the Shaw AREVA MOX Services (MOX Services) application meets all applicable regulations.
Date |
Action |
1/31/05 |
NRC issued the Final Environmental Impact Statement (NUREG-1767) |
3/31/05 |
NRC issued the Final Safety Evaluation Report on the Construction Authorization Request for the Mixed Oxide Fuel Fabrication Facility at the Savannah River Site, SC (NUREG-1821) |
3/30/05 |
NRC issued the Construction Authorization |
9/27/06 & 11/16/06 |
MOX Services submits the License Application and the Integrated Safety Analysis Summary to possess and use radioactive material |
12/20/06 |
NRC accepts license submittal for docketing |
4/12/2007 |
Public meeting in Aiken, SC to discuss NRC’s role, responsibilities, and the licensing process; inspection and enforcement; and public participation related to the review of the License Application for the MFFF |
12/20/10 |
NRC staff to complete review and prepare Safety Evaluation |
|