DEFENSE NUCLEAR FACILITIES SAFETY BOARD
August 13, 1996
MEMORANDUM FOR: |
|
G. W. Cunningham, Technical Director |
COPIES: |
|
Board Members |
FROM: |
|
J. Sanders |
SUBJECT: |
|
Review of the Renovations for the Nuclear Materials Storage Facility (NMSF), Los
Alamos National Laboratory (LANL) |
- Purpose: This report documents the Defense Nuclear Facilities Safety Board
(Board) staff review of the renovations for the Nuclear Materials Storage Facility (NMSF)
at Los Alamos National Laboratory (LANL) conducted on July 30 - August 1, 1996, by Joseph
Sanders, Joel Blackman, Albert G. Jordan, and Lani Miyoshi.
- Summary: The NMSF, as it is currently constructed, is not acceptable for handling
and storing special nuclear material (SNM) for reasons recognized by LANL and detailed in
Appendix A. As a result, NMSF is undergoing a substantial upgrade that will involve almost
entire reconstruction. LANL is dedicating substantial and effective internal resources to
support this design upgrade. In addition, LANL has developed a Preliminary Hazards
Assessment (PHA) to identify and eliminate or mitigate hazards as early as possible in the
design.
LANL had the concrete strength and reinforcing steel placement surveyed to verify the
construction quality of the original facility without complete construction records.
Results indicate that the concrete strength meets construction specifications in the areas
surveyed. However, the thickness of concrete cover above the reinforcing steel was found
to exceed code requirements in several locations, resulting in a possible reduction in the
moment resisting capacity (out-of-plane resistance) of the concrete section. LANL
representatives are aware of these issues and are developing a plan for resolution.
Thermal analyses for the proposed vault passive cooling system indicate that the design
margin in meeting temperature limits is not large. As a result, the final design of the
holding fixture for the SNM container will need to be sufficiently robust to satisfy
maximum SNM temperature limits. Relatedly, consideration should be given to monitoring air
and drywell temperatures and vault air effluents.
- Background: The preliminary design of the existing NMSF commenced in 1984, and
construction was completed in 1987 under supervision of the U.S. Army Corps of Engineers.
However, NMSF has never operated as a nuclear facility because of major design and
construction deficiencies detailed in Appendix A.
Based on current projections, existing storage space for SNM (primarily plutonium) at LANL
will be loaded to capacity in 2002, which could adversely impact LANL's ability to meet
its mission requirements. As a result, the decision was made to renovate the NMSF. The
conceptual design for the upgrade was completed in late 1995 by ICF Kaiser Engineers, Inc.
(Kaiser), and a draft version of the Functional and Operational Requirements was completed
in early 1996. Representatives of LANL intend to select an architect/engineer by September
30, 1996, as a subcontractor to perform activities including the Title 1 (Preliminary) and
Title 2 (Final) Design, and LANL has requested funding for FY97 to complete Preliminary
Design. Facility readiness for operations is scheduled for late 2002.
This facility will be designed to store up to 6,600 kg of plutonium metal or oxide, or
provide for the dissipation of 20 kilowatts from heat generation (whichever is more
limiting). It will likely be classified as a Hazard Category 2 facility consistent with
the applicable Department of Energy (DOE) Standard. The total cost of the upgrade project
is estimated to be $56.6 Million. A more detailed description of the proposed renovation
is provided in Appendix B.
- Discussion:
- Hazards Identification and Risk Reduction: NMSF's primary
hazards stem from handling and storing SNM, particularly plutonium. In conjunction with
the preparation of the Conceptual Design Report for NMSF, LANL prepared a draft PHA. The
risks to the public, the workers, and the environment were addressed in a manner
appropriate to the current stage in design.
- Criticality: A criticality event would present a serious hazard to
the facility worker. Conservative analyses indicate that a criticality could occur if five
canisters are placed in an optimal configuration. Therefore, extra precautions will need
to be taken during canister handling, placement in the basket assembly, and insertion into
the storage drywells. The baskets holding the canisters in the drywells and the drywells
themselves will need to resist the Design Basis Earthquake (DBE) in order to prevent
critical configurations from developing.
- Plutonium Release and Dispersal: Stabilized plutonium metal and
oxide (packaged in accordance with the current DOE Standard) and pits (packaged in AT400A
containers) will be accepted for storage in the vault. This packaging will provide primary
and secondary confinement barriers. The drywell walls will provide the tertiary
confinement barrier for release to the cooling air, while the structure and HEPA
filtration system provide tertiary confinement during handling activities. The vault
structure, storage drywells, and canister holding fixtures will be designed to sustain a
DBE. Furthermore, the thermal design of the vault system should prevent the a-phase
plutonium metal from heating to the a-d phase transition temperature of 225·F, causing
expansion and possibly resulting in failure of the inner canister or pit cladding.
- Routine Radiation Hazards: Radiation exposure hazards from material
stored in the vault will also be limited by design. A thick, concrete charge deck with
shield plugs capping the storage drywells and borated concrete-thickened vault sidewalls
will ensure annual worker doses do not exceed 500 mrem. Extensive shielding analyses have
been performed to support the conceptual design, and the conservative results indicate
that the radiation dose to a person over the charge deck with a shield plug removed will
be less than 0.25 mrem/hr if standing at least 1.5 meters away from the hole.
- Facility Structural Adequacy: A review of the construction
records for the NMSF by LANL personnel revealed that quality control documents for
concrete strength and reinforcing steel placement could not be located. Since the
structure will perform a safety class function, a condition survey was undertaken to
establish in situ concrete strength and confirm that the reinforcing steel was properly
installed. The survey of the building was conducted by Concrete Technology Laboratories
(CTL) and the results assessed by ICF Kaiser. Based on testing of concrete cores, it was
determined that the in situ concrete strength exceeds required design strength (average
concrete strength is 7662 psi versus required design strength of 4000 psi). Therefore, the
concrete strength appears to be adequate.
The placement of reinforcing steel was measured by magnetic sensing and impulse radar
testing which revealed that the center-to-center spacing of the reinforcing steel
generally conformed to the design drawings. While not specifically stated in the report,
the Board staff understands that the cross-sectional dimensions were determined to be
within design tolerances. However, the depth of concrete cover above the reinforcing steel
significantly exceeded specified allowable tolerances. The effect of the increased cover
is to reduce the moment resisting capacity of the concrete section. In-plane shear
capacity is not affected by this problem. ICF Kaiser used an average value of 2.6 inches
versus 0.75 inches required cover to assess the significance of the deficiency in the
exterior walls and concluded that the deficiency was not detrimental to the overall
integrity of the structure. However, a review of the test report by the Board staff
revealed that the variation of cover ranged from 0.5 to 5 inches, and that an average
cover significantly exceeding 2.6 inches extended over entire wall panels. The Board staff
believes that the use of an overall building average to evaluate concrete section capacity
reduction is not appropriate for a safety class structure and that reductions in capacity
should be based on actual panel reductions.
In addition, the actual cover of the reinforcement closest to the exterior surface of the
wall was not measured in the original CTL study. Due to moment reversal during a seismic
event as well as changes in curvature, the Board staff believes that the location and
amount of cover for the exterior reinforcement should also be determined by field
measurement.
Due to the potential significance of the problems discussed above, the DNFSB staff
believes that a very thorough condition survey and structural adequacy assessment of the
structure should be performed to validate its adequacy as a safety class structure.
During a tour of the NMSF, the Board staff was shown a tunnel that is intended to
facilitate transfer of SNM between PF-4 and NMSF. This tunnel, which is a safety class
structure, had not been examined as part of CTL's testing program. The concrete in an
approximately 30-foot section of the tunnel appeared to be degraded. Numerous hairline
cracks in this section, discoloration of the concrete finish, and efflorescence
(indicative of water seepage through the concrete) were present and are indications of
poor concrete quality. Based on this observation as well as the reinforcing steel
placement issue previously discussed, the DNFSB staff believes that a thorough assessment
of the structural integrity of the tunnel is warranted.
- Effluent Monitoring: DOE Order 6430.1A, General Design
Criteria, specifies that "all exhaust outlets that may contain plutonium
contaminants shall be provided with two monitoring systems. These monitoring systems shall
[ensure that] all exhaust ducts or stacks that may contain radioactive airborne effluents
shall be provided with effluent monitoring systems." However, monitoring of the air
stream exiting the vault to the environment is not currently planned because it would be
expensive to maintain and releases are not expected during the facility operating
lifetime. If this monitoring is ultimately determined to be unnecessary, alternative means
for rapidly identifying any releases of plutonium to the cooling air should be identified,
or persuasive reasoning for why it is unnecessary would appear prudent. Furthermore, the
staff believes it would also be prudent to evaluate the need for and practicality of
monitoring for plutonium within individual drywells to prevent a worker exposure event
during removal of a shield plug.
- Thermal Design and Monitoring: The thermal limits used in
the conceptual design are 176·F and 149·F, respectively, for plutonium metal and pits
under normal conditions, and 212·F under loss-of-cooling conditions. Thermal analyses
have been performed to support the conceptual design of the drywell and holding fixture
for the individual containers within the drywell, termed "baskets." The analyses
are decoupled into two calculations. The first calculates the maximum temperature of the
air cooling the external drywell surface. This is derived from the ambient air temperature
and the overall heat output in the vault. From this maximum air temperature, the second
calculation evaluates the maximum temperature of the material. The results of these
evaluations indicate that thermal limits can be satisfied under normal and accident
conditions. However, the degree of margin available is significantly less than the Fort
St. Vrain Facility, a model for the NMSF design. Furthermore, the final design of the
baskets will need to be robust from a thermal perspective. Given the limited margin
available and uncertainties associated with passive cooling systems, it may be valuable to
consider monitoring for the outlet air and drywell temperatures to ensure system thermal
performance is adequate.
The DOE Standard for plutonium storage permits a maximum thermal output of 30 watts per
container. However, the current vault design allows a maximum thermal output of only 15
watts per container, creating an inconsistency. The lower limit for the vault should not
impact containers storing weapons-grade plutonium with relatively modest heat generation
of approximately 2.2 watts per kilogram, but it may preclude storage of higher burnup
plutonium from other sources.
- Future Staff Actions: The Board staff plan to continue reviewing the renovation
of the NMSF throughout its design and construction. The staff intends to follow up on
those issues identified in the report and perform the next review following completion of
the Preliminary Design.
Appendix A
Major Design and Construction Deficiencies
in the Existing Nuclear Materials Storage Facility
- Radiological control boundaries: potentially contaminated air plenums in
uncontrolled areas; radiation workers would have to traverse uncontrolled areas en route
to the change rooms; the elevator to be used to transport special nuclear material (SNM)
from the receipt area to the vault area crosses uncontrolled areas.
- Operational security boundaries: the garage, designed to accommodate two safe
secure trailers (SST), is too narrow and would not allow the doors of the SSTs to be
opened and secured; the secure elevator crosses administrative areas.
- Cooling of the storage vault: the vault design would not ensure adequate cooling
of the SNM.
- Fire/explosion hazards: two natural gas boilers are currently located in the
Nuclear Materials Storage Facility. This is prohibited by DOE Order 6430.1A, General
Design Criteria, because it creates an internal explosion hazard.
- Faulty decontamination design: the "Placite" coating applied to the
concrete walls for ease of decontamination, is peeling extensively.
- Vault storage cabinets and retrieval system: vault cabinets were not properly
sized to house packages containing SNM. The retrieval system would not preclude
significant radiation exposure, and is therefore inconsistent with the ALARA principle.
Appendix B
Proposed Renovation to the Nuclear Materials Storage Facility
The renovation to the Nuclear Materials Storage Facility (NMSF) will essentially remove
and replace all building systems, components, and structures. The outer structural walls
and certain internal structural walls will be saved. The project will include construction
of a passive, air-cooled storage vault for special nuclear material (SNM), somewhat
similar in design to the passively cooled spent fuel storage vault at the Fort St. Vrain
Facility in Platteville, Colorado. This system will be designed to provide adequate
cooling for the high density array of vertical drywells to meet material thermal limits
with an overall material heat output of 20 kilowatts. The vault is expected to be
approximately 35 feet high, 30 feet wide, and 130 feet long and comprised of three
subsections, each capable of holding approximately 170 material drywells. The drywells
will be suspended from the horizontal charge deck separating the passive cooling area from
the material loading area. Each drywell is currently designed to hold 14 SNM containers.
Like Fort St. Vrain, the cooling system is a passive, self-regulating, natural
convection cooling system. Ambient air enters the vault and is convectively heated as it
flows past the surface of the storage drywells. Decay heat is transferred from the various
SNM isotopes through the storage canisters and drywells to the air in the vault and
buoyancy-driven flow is induced. The heated air rises up the vertical outlet duct because
of its lower density relative to ambient air. This provides the buoyancy head to sustain
continuous air flow over the drywell surfaces.
All material to be stored, other than pits, will be stabilized as metal or oxide before
placement into the vault. Metal and oxide will be sealed in metal containers consistent
with DOE Standard 3013-94 (or later revisions), Criteria for Long-Term Storage of
Plutonium Metal and Oxides, and pits will be stored in AT400A containers. Three
barriers will exist to prevent the release of plutonium from the system; two qualified
containers will serve as the primary and secondary containment for repackaged metals and
oxides. In the case of pits, the cladding, having been leak-tested prior to insertion in
the AT400A, will provide the primary confinement, while the AT400A containment vessel will
provide secondary confinement. The storage drywell will provide the tertiary barrier.
NMSF upgrades will also incorporate a secure, temporary SNM staging area, SNM unpacking
area, nondestructive assay laboratory, and an intermediate storage area. NMSF will
maintain a tunnel connection with PF-4; this will serve as a secure transport medium
between the facilities. As a result, the Materials Access Area will be continuous through
PF-4 and NMSF (PF-41).