[DNFSB LETTERHEAD]

 

September 13, 2004

 

The Honorable Linton Brooks

Administrator

National Nuclear Security Administration

U.S. Department of Energy

1000 Independence Avenue, SW

Washington, DC 20585-070 1

 

Dear Ambassador Brooks:

 

The Defense Nuclear Facilities Safety Board (Board) has followed closely the suspension

of nuclear operations at Los Alamos National Laboratory (LANL) on July 16, 2004, and the subsequent resumption planning effort.  In addition, members of the Board and its technical staff visited LANL on August 18 and 19, 2004, to assess conditions at the laboratory and review the restart approach.  The enclosure to this letter describes several of the Board’s observations and is provided for your information.

 

Several points in the enclosure warrant emphasis.  The National Nuclear Security Administration (NNSA) and LANL need to closely monitor and LANL needs to appropriately adjust plant conditions to maintain safe and stable configuration during the stand-down.  The currently envisioned stand-down of a few months, coupled with appropriate monitoring, appears reasonable, but NNSA and the Department of Energy (DOE) need to anticipate and prepare for the emergence of new nuclear safety issues should the stand-down be protracted.  The LANL Director’s decision to stand down all operations was strongly influenced by an injury on July 14, 2004, that apparently occurred because of a breakdown in the laboratory’s interim work control process.  It would perhaps be beneficial to undertake an effort focused on identifying the necessary work control improvements during the assessments now under way, and then fully and aggressively implementing an improved work control process in parallel with other resumption activities.

 

The stand-down is delaying several NNSA and LANL actions that are necessary to address long-term safety liabilities.  These include aggressively completing nuclear material stabilization activities in response to the Board's Recommendations 94-1, Improved Schedule for Remediation, and 00-1, Prioritization for Stabilizing Nuclear Materials; dispositioning corroding cans of plutonium-238 and completing clean-up of the room contaminated in August 2003 during an event that resulted in plutonium-238 uptakes to workers; resuming characterization and shipment of transuranic waste drums to the Waste Isolation Pilot Plant (WIPP); addressing the large backlog of LANL safety bases that need to be updated, particularly for the Plutonium Facility; and pursuing other longer-term initiatives to improve safety, such as full implementation of DOE Order 420.1A, Facility Safety, and conduct of engineering.  These actions warrant priority.

 

The Board will continue to closely monitor resumption activities at LANL.  In particular, the Board plans to have technical staff members on site during LANL’s readiness assessments for nuclear facilities, expected to start in mid-September 2004.  These staff members will supplement the coverage already provided by the Board’s two full-time site representatives at LANL.  Consistent with the current practice for site representatives, these staff members will work with NNSA’s Los Alamos Site Office and will provide real-time feedback to NNSA and LANL personnel responsible for resumption activities.

 

Sincerely,

 

John T.  Conway

Chairman

 

c:   Mr. Mark B. Whitaker, Jr.

Mr. Edwin L. Wilmot

 

Enclosure

 



Enclosure

 

Defense Nuclear Facilities Observations of Restart Efforts and

Safety Conditions During the Shutdown of Work Activities

 

On July 16, 2004, the Los Alamos National Laboratory (LANL) Director suspended all but essential operations because of safety, security, and compliance issues.  Subsequently, LANL developed a resumption plan, with which the Manager of the National Nuclear Security Administration’s (NNSA) Los Alamos Site Office (LASO) concurred.  LANL plans a staggered resumption of operations in its facilities.  The decision to resume each operation will be based on a series of assessments that evaluate eight functional areas encompassing the competency of management, the behavior of personnel, the risks of the operation, and the adequacy of controls.  These assessments are now expected to be completed by mid-September 2004 for moderate-risk activities and by November or December for higher-risk activities.  The LANL Director is the approval authority for resumptions not involving classified removable electronic media.  The LASO Manager will concur on each resumption based on input from his representatives.

 

The Defense Nuclear Facilities Safety Board (Board) visited LANL on August 18 and 19, 2004.  During this visit, the Board observed restart efforts and held discussions with LANL and LASO representatives concerning the safety conditions during the stand-down and the safe resumption of work activities.  Prior to the visit, the Board received a briefing from the NNSA Administrator, who is responsible for the overall safety and security of NNSA’s weapons laboratories and who had recently returned from LANL.  The Board has also received frequent updates from its technical staff.  As a result of the information thus obtained, the Board has the following observations: