[DNFSB
LETTERHEAD]
September 13, 2004
The Honorable Linton Brooks
Administrator
National Nuclear Security
Administration
U.S. Department of Energy
1000 Independence Avenue, SW
Washington, DC 20585-070 1
Dear Ambassador Brooks:
The Defense Nuclear Facilities
Safety Board (Board) has followed closely the suspension
of nuclear operations at Los
Alamos National Laboratory (LANL) on July 16, 2004, and the subsequent
resumption planning effort. In addition,
members of the Board and its technical staff visited LANL on August 18 and 19, 2004,
to assess conditions at the laboratory and review the restart approach. The enclosure to this letter describes several
of the Board’s observations and is provided for your information.
Several points in the enclosure
warrant emphasis. The National Nuclear
Security Administration (NNSA) and LANL need to closely monitor and LANL needs
to appropriately adjust plant conditions to maintain safe and stable
configuration during the stand-down. The
currently envisioned stand-down of a few months, coupled with appropriate
monitoring, appears reasonable, but NNSA and the Department of Energy (DOE)
need to anticipate and prepare for the emergence of new nuclear safety issues
should the stand-down be protracted. The
LANL Director’s decision to stand down all operations was strongly influenced
by an injury on July 14, 2004, that apparently occurred because of a breakdown
in the laboratory’s interim work control process. It would perhaps be beneficial to undertake an
effort focused on identifying the necessary work control improvements during
the assessments now under way, and then fully and aggressively implementing an
improved work control process in parallel with other resumption activities.
The stand-down is delaying
several NNSA and LANL actions that are necessary to address long-term safety
liabilities. These include aggressively
completing nuclear material stabilization activities in response to the Board's
Recommendations 94-1, Improved
Schedule for Remediation, and
00-1, Prioritization for
Stabilizing Nuclear Materials; dispositioning
corroding cans of plutonium-238 and completing clean-up of the room
contaminated in August 2003 during an event that resulted in plutonium-238
uptakes to workers; resuming characterization and shipment of transuranic waste
drums to the Waste Isolation Pilot Plant (WIPP); addressing the large backlog
of LANL safety bases that need to be updated, particularly for the Plutonium Facility;
and pursuing other longer-term initiatives to improve safety, such as full implementation
of DOE Order 420.1A, Facility
Safety, and
conduct of engineering. These actions
warrant priority.
The Board will continue to
closely monitor resumption activities at LANL. In particular, the Board plans to have
technical staff members on site during LANL’s readiness assessments for nuclear
facilities, expected to start in mid-September 2004. These staff members will supplement the
coverage already provided by the Board’s two full-time site representatives at LANL.
Consistent with the current practice for
site representatives, these staff members will work with NNSA’s Los Alamos Site
Office and will provide real-time feedback to NNSA and LANL personnel responsible
for resumption activities.
Sincerely,
John T. Conway
Chairman
c: Mr. Mark B. Whitaker, Jr.
Mr.
Edwin L. Wilmot
Enclosure
Enclosure
Defense
Nuclear Facilities Observations of Restart Efforts and
Safety
Conditions During the Shutdown of Work Activities
On July 16, 2004, the Los Alamos
National Laboratory (LANL) Director suspended all but essential operations
because of safety, security, and compliance issues. Subsequently, LANL developed a resumption
plan, with which the Manager of the National Nuclear Security Administration’s
(NNSA) Los Alamos Site Office (LASO) concurred. LANL plans a staggered resumption of
operations in its facilities. The
decision to resume each operation will be based on a series of assessments that
evaluate eight functional areas encompassing the competency of management, the
behavior of personnel, the risks of the operation, and the adequacy of controls.
These assessments are now expected to be
completed by mid-September 2004 for moderate-risk activities and by November or
December for higher-risk activities. The
LANL Director is the approval authority for resumptions not involving
classified removable electronic media. The LASO Manager will concur on each
resumption based on input from his representatives.
The Defense Nuclear Facilities
Safety Board (Board) visited LANL on August 18 and 19, 2004. During this visit, the Board observed restart
efforts and held discussions with LANL and LASO representatives concerning the
safety conditions during the stand-down and the safe resumption of work
activities. Prior to the visit, the Board
received a briefing from the NNSA Administrator, who is responsible for the
overall safety and security of NNSA’s weapons laboratories and who had recently
returned from LANL. The Board has also
received frequent updates from its technical staff. As a result of the information thus obtained,
the Board has the following observations:
- The Board’s first concern following the stand-down is
for the safe and stable configuration of the nuclear operations and
facilities. There are numerous
examples of accidents or hazardous conditions elsewhere resulting from
improperly planned and executed stand-downs. The Board has learned that LANL took such
actions as categorizing compliance with safety basis requirements as an
essential activity that must continue through the stand-down, prioritizing
maintenance of vital safety systems, and implementing periodic monitoring
and inspection of facility equipment. Overall, it appears that LANL achieved an
orderly stand-down of its nuclear facilities.
- LANL needs to closely monitor and appropriately adjust
plant conditions to maintain safe and stable conditions during the
stand-down. During its recent
visit, the Board observed that, while LANL had taken many appropriate
actions, some personnel responsible for programmatic equipment were still
confused about the frequency and scope of inspections they should be
conducting during the stand-down and about the actions to take if abnormal
conditions were found. The Board
and its staff communicated this observation to DOE and LANL management.
- The Board is also concerned about the potential for new
nuclear safety issues to emerge should the stand-down be longer than
anticipated. There are examples elsewhere
of idling processes eventually leading to hazardous conditions and accidents,
such as the
hydroxylamine nitrate (HAN) explosion at Hanford. An extended stand-down could possibly
affect operators’ familiarity with the facility and equipment, increase
the probability of equipment failure, or create unexpected or off-normal
conditions. The currently
envisioned stand-down of a few months, coupled with aggressive monitoring,
appears reasonable in this regard.
- While the resumption planning effort is impressive, the
extensive reviews required could result in a protracted stand-down if they
are n t managed closely and every aspect of operations in a short time. For example, the Plutonium Facility and the
Chemistry and Metallurgy Research (CMR) Facility have identified about 200
processes within scope, each to be evaluated against 53 lines of inquiry,
possibly resulting in about 10,000 point assessments. To keep this effort manageable, these facilities
and others are screening processes and pursuing risk-based sampling. The challenge for LANL is to achieve
proper balance in all these reviews between being too superficial to
satisfy the objectives of the stand-down and being too detailed, leading
to protracted facility shutdowns that create new and potentially more
serious safety issues.
- The LANL Director’s decision to stand down all
operations was strongly influenced by an injury on July 14, 2004, that
apparently occurred because of a
breakdown in LANL’s
interim work control process. Early
in 2004, several near-misses at LANL indicated that the process was
incompletely implemented, and the laboratory made some adjustments. Early observations from LANL reviews now
under way suggest that the interim work control process is still
implemented incompletely or inconsistently in many nuclear and nonnuclear
facilities. LANL’s commitment to implementing
major process improvements in September 2004 has been impacted by the
stand-down. The laboratory might
achieve maximal benefit from a priority effort focused on identifying the
necessary work control improvements during the assessments now under way
and then fully and aggressively implementing them in parallel with other
resumption activities.
- In 1989, several DOE sites suspended nuclear operations
but failed to resume operations within a short period as originally
intended. In Recommendation 94-1 to
the Secretary of Energy (May 26, 1994), the Board observed that the halt
in the production of nuclear weapons and materials had frozen the
manufacturing pipeline in a state that, for safety reasons, should not be
allowed to persist unremediated. The subsequent effort to address the
emergent safety issues across the DOE complex has been massive and remains
incomplete. LANL lags behind nearly
all other DOE sites in this regard, and has a significant inventory of
nuclear material that has not been properly stabilized and packaged or
otherwise dispositioned. During its
visit, the Board learned that the stand-down will further delay the
nuclear material stabilization effort. It is imperative that stabilization of
nuclear materials not be excessively delayed and that when it resumes, it
be assigned priority.
- Relatedly, the LANL stand-down, as well as unresolved
safety basis issues, has delayed the laboratory’s efforts to disposition
corroding cans of plutonium-238 residues and to clean up the room in the
Plutonium Facility that was contaminated in August 2003 during an event
that resulted in plutonium-238 uptakes to workers. The clean-up stalled 3 to 4 months ago. The stand-down is also delaying other NNSA
and LANL commitments made in response to the NNSA’s Type B investigation
of the uptakes, completed last December. Plutonium Facility personnel recognize
that the contaminated room and the residues constitute a safety liability
that should not be allowed to persist. They need the full support of NNSA and
LANL management to resume this activity safely and quickly as a priority.
- The stand-down has delayed LANL’s efforts to
characterize and resume shipment of higher-activity transuranic waste
drums to the Waste Isolation Pilot Plant (WIPP) under the Quick-to-WIPP
Program. This program is aimed at
reducing the risks associated with the highest-consequence accident
postulated at LANL in approved nuclear safety analyses. Its resumption warrants priority.
- The stand-down has delayed NNSA and LANL efforts to
address the large backlog of LANL safety bases that need to be updated. The safety bases constitute the LANL proposed
and NNSA approved set of analyses and requirements for safe operation of nuclear
facilities. NNSA has not enforced
the annual update requirements for LANL safety bases. Several nuclear facilities (e.g., the
Plutonium Facility) are operating now with safety bases that are more than
5 years old. In
particular, processes in the Plutonium Facility that were judged
acceptable in accordance with the 1996-era safety basis and were
subsequently started up within the last few years may not meet today’s DOE
safety requirements. NNSA and LANL
efforts to quickly review and update the safety basis for the Plutonium
Facility proposed 2 years ago have been delayed by the stand-down and
warrant priority.
- The stand-down has also delayed longer-term improvement
initiatives at LANL, including those being pursued in response to issues
raised by the Board. For example,
NNSA has proposed a second 90-day slip in issuing its report on LANL’s implementation
of DOE Order 420.1A, Facility
Safety, and application of uniformly sound design and engineering
practices. The Board’s staff has
identified many instances in which NNSA and LANL have provided inadequate
assurance that the engineered controls selected have clearly defined
safety functions, that they will fulfill those functions, and that they
constitute a complete set. Significant effort remains to finalize
the implementation plan for Order 420.lA, particularly for the application
of engineering practices to nonfacility work. Another example may be LANL addressing
training issues described in the recent NNSA training assessment, which
was done in response to a Board letter dated July 9, 2003.
- The stand-down has the potential to significantly
impact design and construction planning efforts, such as the replacement
for the CMR Replacement Facility. Certain of these efforts will enhance
nuclear safety in the long term and should not be delayed.
- Finally, it would be advisable to attempt to limit the
effect of this stand-down on the laboratory’s analytical work in support
of the Pantex Plant’s efforts to assemble, disassemble, and dismantle
nuclear weapons safely.