No. 01-123 October 16, 2001

NRC APPROVES POWER UPRATE
FOR SHEARON HARRIS NUCLEAR POWER PLANT


The Nuclear Regulatory Commission has approved a request by Carolina Power & Light Co. to increase the generating capacity of the Shearon Harris nuclear power plant by about 4.5 percent, or 51megawatts.

The power uprate at the plant, near Raleigh, North Carolina, will increase the generating capacity of the reactor to about 968 megawatts of electricity. The facility intends to implement the power increase in December. The application for the increase in power was submitted to the NRC on December 14, 2000.

The NRC's safety evaluation of the requested power uprate for the plant focused on several areas, including nuclear steam supply systems, instrumentation and control systems, electrical systems, accident evaluations, radiological consequences, operations and technical specification changes. The NRC staff determined that the licensee could safely increase the power output of the reactor primarily by using more new fuel in the core and by replacing the steam generators.


NRC news releases are available through a free listserv subscription at the following Web address: http://www.nrc.gov/public-involve/listserver.html. The NRC Home Page at www.nrc.gov also offers a Subscribe to News link in the News & Information menu. E-mail notifications are sent to subscribers when news releases are posted to NRC's Web Site.