Rapid City Indian Services Council, Inc., DAB No. 835 (1987)

DEPARTMENTAL GRANT APPEALS BOARD

Department of Health and Human Services

SUBJECT: Rapid City Indian Services
Council, Inc.

Docket No. 85-275
Audit Control No. 08-55361
Decision No. 835

DATE: February 6, 1987

DECISION

The Administration for Native Americans (Respondent or ANA) disallowed $12,812 in expenditures
charged to grant funds by the Rapid City Indian Services Council, Inc. (Appellant or Grantee) on grounds
that $12,195 in unauthorized expenditures had been made after the expiration of the grant, and that $617
in unallowable expenditures had been made during the term of the grant. For the reasons discussed
below, we uphold the disallowance subject to a possible adjustment of the amount, as explained in the
Conclusion on page 7 below. 1/

Our decision is based on the record developed during the course of this proceeding. The record included
tapes of telephone conference calls conducted on March 20, 1986 and July 30, 1986.

Facts

Due to internal management problems and an erosion of support for its project within the community, on
February 6, 1985, Grantee's Board of Directors decided to close out its program and elected a new
Executive Director solely for that purpose. (Appellant's February 14, 1986 submission, Atts. 4, 5, 6, 9, 11,
and 16) The grant expired on February 28, 1985. 2/ (Respondent's Appeal File (RAF), Ex. 2) By letter of
March 1, 1985, the new Executive Director requested ANA's approval for the use of the balance of the
funds left in the grant to pay for specified close-out costs. (RAF, Ex. 6; Respondent's November 28, 1986
submission, Att. A, p. 3) ANA disapproved the use of grant funds for close-out activities by telephone on
March 1, 1985 and by letter on March 22, 1985. (Respondent's August 5, 1986 submission, Att. 1;
Respondent's November 28, 1987 submission, Att. A, p. 3)

Nevertheless, Grantee proceeded to spend the remaining grant funds on its close-out activities. Grantee's
expenditures included


1/ During the course of this proceeding Respondent acceded to two possible adjustments, and the record
indicates that another may also be appropriate.

2/ The grant in question, No. 90NAC104/02, was a social and economic development services grant with
a project period from October 1, 1982 to February 28, 1985 and a budget period of March 1, 1984 to
February 28, 1985. The amount of federal funds awarded for the last budget period was $113,972. (RAF,
Ex. 2)



- 2 -

the cost of an independent audit of grant funds. The auditors performed the audit field work in late March
and early April, 1985. The auditors found that Grantee had spent and was continuing to spend grant
funds after expiration of the grant. (RAF, Ex. 7, pp. 14-16) Subsequently, on July 30, 1985, ANA sent
Grantee another letter specifically informing Grantee of its responsibilities with regard to filing reports
and disposing of property for close-out of its ANA grant. (Respondent's November 28, 1986 submission,
Att. B) Thereafter, on December 18, 1985, ANA issued this disallowance based on the audit findings.
(RAF, Ex. 9)

Discussion

In section one, we deal with the amounts expended after expiration of the grant and disallowed for that
reason. In section two, we deal with amounts expended during the term of the grant and disallowed for
various other reasons.

I. Amounts Expended After Expiration of the Grant

A. Whether Grantee had the authority to use grant funds
for its close-out activities

ANA disallowed the $12,195 in grant funds remaining as of February 28, 1985, on the basis that it was
expended by the Grantee after the expiration of the grant. 3/ Respondent argued that the Grantee had no

3/ Respondent originally stated that $9,966 was expended without approval after expiration of the grant,
and that $2,229 was an unaccounted for fund balance. (Respondent's May 15, 1986 submission, p. 3)
Based on statements in the audit report which indicated that the $2,229 may in fact have been spent after
expiration of the grant for purposes of close-out, Grantee's assertion that this amount was spent for grant
close-out, and documentation in support of that assertion, the Board inquired further. (RAF, Ex. 7, p. 16;
Appellant's March 25, 1986 submission, last attachment) Respondent, thereafter, conceded that it was not
disputing that the remaining funds had been spent, but questioned the propriety of the expenditures.
(Respondent's November 28, 1986 submission, p. 8) Accordingly, we here treat the $2,229 as an amount
spent after the expiration of the grant rather than as an unobligated fund balance. In any event, even if we
had treated the $2,229 as an unexpended fund balance, the result in this case would be the same--the
disallowance would be sustained. Section 74.111(b)(2) of 45 CFR specifically states that upon expiration
of a grant the grantee "shall immediately refund or otherwise dispose of, in accordance with instructions
from HHS, any unobligated balance of cash advanced to the grantee." Since ANA gave no instructions to
otherwise dispose of any unobligated fund balance, it would have to be returned anyway. The record also
indicates that Grantee had returned $73.79 of the remaining funds to ANA. (Appellant's March 25, 1986
submission, last attachment, RAF, Ex. 8, p. 2)



- 3 -

authority to expend grant funds after that date without approval from ANA. Respondent contended that it
did not approve the expenditure and, in fact, specifically advised Grantee by telephone and in writing that
ANA would not approve Grantee's March 1, 1985 request to use unobligated grant funds for close-out.
Respondent argued further that the Grantee never established that any of the post-expiration close-out
costs were necessary and that many were excessive.

Grantee argued that it never received a response from ANA to its March 1, 1985 letter requesting
approval of a close-out budget and, thus, reasonably thought that ANA had approved the proposed plan.
Grantee also argued that the record shows that all its expenditures after expiration of the grant were for
legitimate close-out costs.

The Grantee did not dispute that the expenditures in question were made after February 28, 1985 (but see
our discussion at pages 7-8 below). (RAF, Ex. 2) The only issue is whether the Grantee had the authority
to charge its close-out costs to grant funds

Under the applicable provisions for administration of the grant, a grantee has the authority to incur close-
out costs after the expiration date for the final budget period where:

the Grants Officer has extended the project and budget periods for some specified period for purposes
of orderly phase-out of federal support (GAM Chapter 1-85-80). 4/

It is undisputed that by letter dated March 1, 1985 Grantee requested approval of the use of the
unobligated balance of funds in the grant for close-out. While the new Executive Director stated that she
had never received ANA's March 22, 1985 denial letter (or the "complete close-out package" which the
letter said would follow), the Director of the Eastern Division of ANA has filed a formal declaration
stating that she had informed the new Executive Director during a telephone conversation on March 1,
1985 that ANA could not approve such a request and that no further grant funds properly could be spent.
That occurred the same day that Grantee mailed its close-out budget request and the day after the grant
expired. It is possible that there was some misunderstanding on the part of the new Executive Director as
to whether with some modification of its proposed close-out budget the unobligated balance could be spent
for close-out. Nevertheless, the auditors found that even earlier, prior to the expiration of


4/ This provision was incorporated by reference as a condition of the grant by the grant award document,
sent to Grantee by letter dated May 7, 1984. (See RAF, Exs. 1, 2, 3)



- 4 -

the grant, ANA had informed Grantee's "fiscal officer" by telephone that no further grant funds should be
spent after February 28, 1985. (RAF, Ex. 7, p. 10) The ANA Director's statement corroborated this and
shed some light on the circumstances. The ANA Director stated that she had spoken with Grantee's
"bookkeeper" on February 18, 1985, and the bookkeeper had informed her that she had "closed the books"
in anticipation of the expiration of the grant. (Respondent's November 28, 1985 submission, Att. A, p. 3)
Grantee did not dispute the statements in the declaration made by the ANA Director. (Grantee's
December 18, 1986 submission)

Given the direct oral instruction from ANA that no further grant funds should be spent, it would not have
been reasonable for Grantee to interpret a failure to receive a written response to its March 1, 1985 request
as approval. Furthermore, the reason Grantee may never have received the written response could have
been because it had changed the location of its office during February of 1985. Confusion attendant with
the move may have caused disruption in mail service. (Appellant's February 14, 1985 submission, Atts.
11 and 16; tape of July 30, 1986 conference call) Grantee should have realized that a failure to receive a
response from ANA could not reasonably be interpreted as approval. The appropriate course of action
would have been to again contact ANA, not spend all the grant funds.

There is no question that ANA did not extend the term of the grant for close-out activities. We conclude
that it was unreasonable for Grantee to spend any funds after February 28, 1985 without affirmative
approval from ANA extending the project period and budget period and approving a budget for close-out
activities.

B. Whether the funds were spent on "allowable" costs

Close-out costs incurred by a grantee are reimbursable, even when authorized, only to the extent that they
are allowable. 5/ In general, allowable costs must be necessary and reasonable for the proper and efficient
administration of the grant program, and must be documented. (Marshalls Community Action Agency,
Decision No. 206, August 28, 1981; Yonkers Community Action Program, Inc., Decision No. 755, May
22, 1986; OMB Circular A-122, Att.A, sections A2, A3, and A4.)

Respondent argued that even if it had approved the expenditure of grant funds for close-out, the costs at
issue, in general, were not allowable, reimbursable close-out costs. Respondent relied on

5/ Section 74.110 of 45 CFR defines "Grant closeout" as:

The process by which a granting agency determines that all applicable administrative actions and all
required work of the grant have been completed by the grantee and the granting agency.



- 5 -

the lack of supporting documentation or explanation for the proposed close-out expenditures.
(Respondent's November 28, 1985 submission, pp. 3-4) Respondent also argued that the high level of
expenditures proposed for close-out (ten percent of the total grant) was never justified by Grantee, and
that, in particular, the expenditures for staff salaries and storage of documents were not considered
necessary or reasonable for grant close-out. Thus, Respondent argued, it had appropriately denied
Grantee's March 1, 1985 request for approval of the close-out budget.

The record indicates that Grantee allotted from 90 to 120 days for close-out activities and spent all
unobligated funds remaining in the grant (except for $73.79 apparently returned to ANA on August 20,
1985) on salaries, space rental for offices, storage of documents, telephone service, postage, photocopying,
and an audit. (RAF, Ex. 7, pp. 14-16; Appellant's March 25, 1985, submission, last page; Appellant's
February 14, 1986 submission, Atts. 4 and 21) Nowhere in the record has Grantee explained why these
costs were necessary and reasonable for close-out of the ANA grant. 6/ Most of the expenditures were
never justified or documented at all beyond naming the individual or corporation to whom payment was
made. (RAF, Ex. 7, pp. 15-16; Appellant's March 25, 1986 submission, last page.)


6/ The record indicates that Grantee's object was not solely the close-out of the ANA grant at issue here,
but included the close-out of the Grantee organization's own operations. The declaration of the ANA
Director, who had been involved in the administration of the grant, stated:

. . . ANA is not responsible as a general rule for core administration costs of a grant. This is true
with respect to Rapid City's grant at issue in this case. Core administration refers to basic costs of
operating an organization that exists apart from our grants. These organizations are supposed to be
independently existing entities, which was ANA's understanding with respect to Rapid City. The fact that
the corporation was dissolved or otherwise ceased operating did not entitle it to charge routine core costs,
such as maintaining an office after expiration of the grant, or retaining grant records.

(Respondent's November 28, 1985 submission, Att. A, p. 4.) Grantee never refuted the ANA official's
declaration concerning the scope of proper close-out costs (these costs are stated below on page 6).
Moreover, the record shows a history of Grantee mismanagement and improper expenditures which the
Respondent cited as further support for its decision not to approve the proposed close-out budget.



- 6 -

As Respondent explained in its brief, close-out costs typically include such items as: (1) the costs of
preparing the necessary program reports; (2) the costs of preparing fiscal reports; and (3) the costs of a
final audit. (Respondent's November 28, 1986 submission, p. 2 and Tab A) Clearly, this all could be
accomplished with minimal expense. Moreover, with the exception of the audit, it could have been
accomplished either prior to the actual expiration of the grant or shortly thereafter. Clearly, the limited
types of costs properly associated with close-out of a grant cannot reasonably be considered to warrant
spending the full ten percent of the total budget spent here over a period of several months. Accordingly,
we conclude that the Grantee has failed to demonstrate that the costs were necessary, reasonable, or
properly documented, and thus allowable.

II. Amounts Expended Prior to Expiration of the Grant

The Agency disallowed three expenditures made during the term of the grant.

The first was $62 for interest and penalty expenses related to federal unemployment taxes. The
Respondent argued that it disallowed this amount on grounds that the cost principles in OMB Circular A-
122, Att. B, section 14 (45 Fed. Reg. 46022, July 8, 1980) expressly designate such costs as unallowable
unless they are incurred in accordance with specific instructions from the granting agency, and that ANA
gave no such instructions in this case. Appellant's sole response was that it did not have any funds with
which to repay the amount.

We sustain the disallowance of this item. Appellant never argued that ANA agreed to this expense. The
applicable provision clearly requires approval for such a cost to be allowable. Further, the Board cannot
overlook a clearly unallowable cost solely because Grantee lacks funds with which to repay the federal
government. (Office of Human Concern, Decision No. 590, October 31, 1984; American Foundation of
Negro Affairs, Decision No. 73, December 28, 1979)

The second item was a $25 bank overdraft charge. The Respondent argued that it disallowed the amount
because, under OMB Circular A-122, Att. A, sections A2 and A3, only reasonable costs are allowable and
a bank overdraft is not a reasonable cost of doing business. The Appellant again argued that it did not
have funds with which to repay the amount. Appellant also argued by way of explanation that it did not
have qualified personnel in charge of the grant.

We sustain the disallowance of this item. Grantee has not stated any circumstances which would support
a finding that the bank overdraft was a reasonable expense. Moreover, we have already stated that lack of
funds with which to repay a disallowance is



- 7 -

not a sufficient basis on which to reverse the disallowance. Similarly, lack of qualified personnel is not a
basis for reversal. A grantee is responsible for assuring that funds are properly spent, and having
qualified personnel is an integral part of that responsibility. (See Hualapai Tribal Council, Decision No.
597, November 26, 1984; Chinle Arizona School District No. 24, Decision No. 64, August 16, 1979)

The third item was a $530 expenditure for the rental of office space. Grantee had leased this space while
it still was renting other space. Respondent argued that the duplicate rental cost could not be considered a
"reasonable cost" of the grant. (The duplicate rental cost also covered a time period beyond the February
28, 1985 expiration of the grant.) Appellant's sole response was that there were "circumstances beyond the
control" of the Executive Board which made it "imperative" that Grantee move offices quickly. (RAF, Ex.
8, p. 2) When we inquired further about this during the July 30, 1986 conference call, the new Executive
Director explained that Grantee had been forced to move because certain individuals with access to the
ANA office were creating disturbances and removing items from the office.

We sustain the disallowance of this item. Grantee's explanation does not justify a reversal of the
disallowance. Grantee offered no explanation why it could not have dealt with the disruptions in some
manner short of leasing additional space. Certainly less costly alternatives could have been attempted
first. Such alternative: might have included changing the locks or calling the police. Accordingly, the
Board concludes that the duplicate rental was not a reasonable cost.

Conclusion

Based on the foregoing, we uphold the disallowance, except to the extent modified in accordance with the
following:

1. Respondent agreed to withdraw "up to $1,000 of the disallowance with respect to audit costs
to the extent the Grantee provides documentation of the costs." (Grantee's proposed close-out budget had
included $1,000 for an audit.) (Appellant's November 28, 1985 submission, p. 7)

2. Respondent agreed to withdraw the disallowance to the extent it included any amounts
already returned to ANA. (See tape of July 30, 1986 conference call.) The record indicates that Grantee
returned $73.79 on August 20, 1985. (Appellant's March 25, 1986 submission, last attachment; RAF, Ex.
8, p. 2)

3. Respondent should also withdraw the disallowance to the extent it includes allowable costs
incurred during the term of the grant but not actually paid



- 8 -

until after February 28, 1985. (See 45 CFR 74.111 (b)(l).) The record indicates that such costs may
have been included in the disallowed amount. (For example, see RAF, Ex. 8, p. 14, check nos. 2054,
2062, 2066 and 2067).

If Grantee chooses to pursue the reduction of the disallowed amount in accordance with the above three
items, Grantee should submit supporting documentation to Respondent's representative in this appeal
within 30 days of receipt of this decision. If no documentation is submitted, the amount disallowed will
stand in full. If documentation is submitted and the parties cannot agree on a reduction, Grantee may
return to the Board on that limited question.

________________________________
Donald F. Garrett
________________________________
Judith A. Ballard
________________________________
Cecilia Sparks Ford
Presiding Board Member