Washington State Department of Social and Health Services, DAB No. 1214 (1990)

Department of Health and Human Services

DEPARTMENTAL APPEALS BOARD

Appellate Division


SUBJECT: Washington State
Department of Social and Health Services
Docket No. 90-48
Decision No. 1214

DATE: December 17, 1990

DECISION

The Washington State Department of Social and Health Services (State)
appealed the decision of the Administration for Children, Youth and
Families (ACYF) disallowing $160,710 of $171,562 claimed by the State
for services performed in 1988 by the Institute for Human Services
Management (IHSM) under a contract with the State. The State charged
75% of the contract costs to title IV-E of the Social Security Act (Act)
under section 474(a)(3)(A), which provides for the reimbursement of
training expenditures at the rate of 75% federal financial participation
(FFP). FFP is available at the rate of 50% for other administrative
expenditures which are necessary for the proper and efficient
administration of the State plan. Section 474(a)(3)(B).

ACYF found that the State had contracted for a management study rather
than for training and that the State had not obtained prior approval for
a management study as required by Office of Management and Budget (OMB)
Circular A-87, Attachment B, Section C.5. ACYF also found that the
costs should not have been charged directly to title IV-E, but should
have been allocated among benefitting programs through the State's cost
allocation plan. 1/ Based on these findings, ACYF determined that no
FFP was available under the contract, except for $10,852 incurred for
the direct training of State eligibility workers. 2/

Below, we summarize the issues presented and our conclusions. The
record for our decision includes the parties' written briefs, their
written responses to a Preliminary Analysis and Order to Develop Record
issued by the Board, and a telephone conference held to clarify these
responses.

I. Summary of Decision

A principal issue in the case is whether the contract was for a
management study or for training. We conclude that neither the
underlying purpose of the contract nor the contractual language are
entirely dispositive but that the nature of each activity under the
contract ultimately determines whether or not it constituted training.
Specifically, we find that ACYF should have considered whether
activities identified by IHSM as curriculum development constituted
training, and remand the case to ACYF for further consideration of this
issue. We further find that case reviews identified by the State as
delivery of training instead constituted curriculum development which
was properly treated as a training cost under the regulation. In
addition, we find that ACYF properly determined that activities which
IHSM identified as delivery of training but described as meetings,
conversations, or conferences did not constitute training since the
State failed to provide more specific information regarding these
activities. We also find that ACYF correctly determined that the
administration of the contract was not a training activity.

Also at issue is the allowability of the costs associated with
activities which are determined to constitute training. The parties
agreed that allowable training costs are limited to those types of costs
specified in 45 C.F.R. 235.64(b)(3) and (b)(4). Tape recording of
10/31/90 telephone conference. However, the State argued that all of
the costs included in the daily rate specified in the IHSM contract were
allowable under the regulation, while ACYF took the position that
general and administrative (G & A) costs as well as profit were
unallowable. We conclude that ACYF properly excluded these costs from
the daily rate since it cannot be determined precisely what G & A costs
correspond to the types of costs specified in the regulation and since
there is no provision in the regulation for profit.

Another issue is whether the State properly charged the costs of
activities involving the revision of its cost allocation plan and both
State agency and institutional time studies directly to title IV-E. 3/
ACYF took the position that the costs were allocable to programs in
addition to title IV-E and should not have been charged solely to title
IV-E. The State argued that the costs were chargeable solely to title
IV-E because the purpose of these activities was to enable the State to
better identify title IV-E costs. We conclude that, regardless of this
purpose, the activities involving the cost allocation plan and the State
agency time study benefitted other programs in addition to title IV-E
and should have been allocated to them as well. However, we remand the
appeal to ACYF to consider whether the institutional time study
activities constituted "rate setting" within the meaning of the
regulation which provides that rate setting is an allowable
administrative cost under the title IV-E program.

The contract activities allocable to title IV-E which do not constitute
training may nevertheless be reimbursable at the normal 50% rate. We do
not address this matter here, however, since it may be resolved when
ACYF considers the State's request for retroactive approval of the IHSM
contract as a management study. 4/ We provide a detailed summary of what
ACYF needs to do to implement our decision on pages 19 - 20 below.

II. Background


The State awarded the contract in question to IHSM after finding IHSM's
proposal responsive to the State's Request for Qualifications (RFQ).
The RFQ specified as the project title "Title IV-E Consultation and
Training" and stated that bidding was open to "management consulting
firms." State's ex. 3, p. 1. The RFQ described the general purpose of
the contract as the provision of "in-depth management consultation,
technical assistance and staff training on cost allocation plans for
Child Welfare Services and implementation of the Title IV-E Foster Care
Program." Id., p. 2.

The contract between the State and IHSM incorporated IHSM's proposal
(with some modifications not pertinent here). State's ex. 13, p. 3.
The introduction to the proposal stated in part that --

the major task for the successful bidder is to design and
implement a Title IV-E policy and procedure system that
maximizes Federal Financial Participation (FFP) . . . . This
technical assistance proposal will address the problems known to
exist in the Title IV-E program and will define an approach to
resolving those problems through changes in policy and
procedures, training, and the development of a more responsive
management information system.

State's ex. 4, pp. 2-3. The proposal also stated that IHSM "proposes to
provide training for staff of Washington's Department of Social and
Health Services (DSHS) to effect improvements in the management of the
Title IV-E program. . . ." It further specified that "IHSM will provide
training to designated State agency staff in a number of Task Areas
where improvements in the state's management capability are deemed both
desirable and necessary." State's ex. 4, page 57 of proposal. The
proposal identified seven training areas, or modules, as follows:

Training module 1: Development of a charge structure and a
revised cost allocation plan

Training module 2: The development of time measurement systems

Training module 3: Develop institutional time study

Training module 4: Assessing current state practice in IV-E
eligibility policy and procedure

Training module 5: Develop accurate and clear policy material
for the IV-E program

Training module 6: Develop organizational structures and
procedures to support the IV-E program

Training module 7: Statewide training on new IV-E eligibility
policy and procedures

Each module is described in detail in the proposal. The record also
includes a log kept by IHSM of the hours charged under the contract
which breaks down each module into a number of different activities, for
a total of several hundred activities. State's ex. 13, pages 8 - 27
(unnumbered). (Another version of the log which sorts the activities
differently and includes the codes referred to below appears in the
State's submission dated 10/5/90 at pages 33-48.) The log gives the
date of each activity, the number of hours devoted to the activity, and
a one-line description of the activity. In addition, the log shows a
letter code for each activity, explained in the key as follows: A =
administrative activities supporting training; C = curriculum
development: preparation of content, materials, procedures; and T =
delivery of training in verbal, written or practicum form.

III. What contract activities constituted training

ACYF took the position that since the purpose of the contract was to
improve the management of the State's title IV-E program, it was
properly considered a contract for a management study except for time
spent in the actual delivery of training. ACYF allowed as training only
those activities which were both specifically described in the
contractor's log as "training" and coded in the log as training. 5/

The State acknowledged that the purpose of the contract was to improve
the management of the State's title IV-E program, but took the position
that the contract was entirely for training because it provided for
achieving this purpose by training State staff. Citing several
references to training in the IHSM proposal, the State argued that the
"contractual agreement was clear and should prevail." State's
submission dated 10/1/90, p. 3. The State also noted in this regard
that it had received a bid protest objecting to the award of the
contract to IHSM on the ground that IHSM's proposal was limited to
training. The State argued further that training should not be limited
to activities which were both coded and described in the log as training
since the log was intended by IHSM only for internal purposes.
Specifically, the State argued that activities coded as curriculum
development constituted training because they involved preparation for
delivery of actual training. The State also argued that activities
described as discussions, meetings and conversations involved delivery
of training because training can take place outside of a formal
classroom setting in small group sessions or on a one-to-one basis.
Finally, the State argued that activities coded as administration
constituted training because "the management of . . . any contract
necessarily involves administrative activity." Id., p. 5.

We conclude ACYF was not justified in concluding that the contract was
primarily for a management study simply because its purpose was to
improve the management of the State's title IV-E program. ACYF relied
on Attachment B, section C.5., of OMB Circular A-87, which requires
prior approval of "[t]he cost of management studies to improve the
effectiveness and efficiency of grant management for ongoing programs. .
. ." However, this purpose can also be achieved through training, as
indicated by the regulation defining a "training program" as "the method
through which the State agency carries out a plan of educational and
training activities to improve the operation of its programs." 45
C.F.R. 235.61. 6/ Thus, the overall and general purpose of the contract
is not determinative of whether specific contract activities constituted
training or a management study.

We further conclude that the contractual language does not establish
that all of the contract activities constituted training, as the State
contended. While the IHSM proposal, which was a part of the contract,
referred to training, it indicated that IHSM would also engage in other
activities. Similarly, the RFQ, to which the IHSM proposal was deemed
responsive, requested management consultation and technical assistance
as well as staff training. Moreover, the bid protest has no probative
value since the State's response to the bid protest indicates that the
State did not share the protester's view of the IHSM contract. (The
State responded by stating that "[t]he fact that the . . . [IHSM]
response focused on a training strategy does not suggest that they are
unqualified to provide in-depth management consultation or technical
assistance." State's ex. 6, p. 1.).

Thus, we must also look at the activities in which the contractor
actually engaged, rather than only the contract language or the
underlying purpose of the contract, in order to determine how the
activities should be reimbursed.

A. Curriculum Development

As noted previously, the State claimed that all of the activities in the
contractor's log, including those coded as curriculum development,
constituted training. In the State's view, curriculum development
consisted of all research, planning, and gathering and organization of
material necessary for IHSM to deliver the training. Tape recording of
10/31/90 telephone conference. ACYF did not dispute that curriculum
development could properly be considered a part of training. (Thus,
ACYF clearly did not regard the codes in the log as dispositive.)
However, ACYF argued that curriculum development was limited to the
development of training materials. Id. ACYF asserted that there was no
evidence that training materials were developed here, noting that the
State staff development manager had stated in response to ACYF's request
that there were no written curricula developed under the contract.
ACYF's submission dated 8/3/90, p. 3; tape recording of 10/31/90
telephone conference. 7/

We see no basis for requiring that written curricula be produced in
order for an activity coded as curriculum development to be considered
training. The applicable regulations do not refer specifically to
curriculum development, but instead provide for FFP in certain costs of
"experts engaged to develop or conduct special [training] programs." 45
C.F.R. 235.64(b)(3) (emphasis added). This authorizes development of
training as a reimbursable activity without regard to whether
development results in written training materials.

We are not persuaded, however, that training includes all research and
planning necessary to deliver the training. If training were viewed
that broadly, title IV-E funds could be used to pay the "expert" to
acquire expertise in the subject matter on which the expert is engaged
to provide training. Thus, IHSM's efforts to acquire an "understanding
[of] current DSHS operations," or to become "aware of OHDS regional
offices' particular interpretations of IV-E rules" (State's reply brief,
p. 10), cannot reasonably be considered training. Instead, an activity
coded as curriculum development must contribute directly to the training
actually delivered in order for the activity to be considered training.
Moreover, although a written product is not required, ACYF is clearly
entitled to evidence which establishes what each activity coded as
curriculum development involved, to the extent that the description in
the log is unclear.


As indicated previously, ACYF did not consider the specific activities
coded as curriculum development because it believed that written
curricula were required. Accordingly, we remand the appeal to ACYF to
consider whether the activities coded as curriculum development
constituted training, based on the descriptions in the log and such
additional information as the State may provide.

B. Delivery of Training

As noted previously, ACYF determined that only the activities which the
log both coded as delivery of training and described using the word
"training" constituted training. 8/ Thus, ACYF declined to treat as
training activities such as those described as meetings, conversations
and conferences. This position seems justified to the extent that ACYF
had only the log to rely on. We do not see any reason, however, why the
lack of the word "training" in the description should be fatal if there
is other evidence that the activity constituted training. Nevertheless,
there is insufficient information in the record to conclude that
activities coded as delivery of training but not described as such
constituted training.

We note at the outset that the burden is on the State to establish that
the activities constituted training. It is a fundamental principle of
grants administration that the grantee has the burden of documenting its
claim for federal funds. Florida Dept. of Health and Rehabilitative
Services, DAB No. 1031 (1989); 45 C.F.R. Part 74, Subpart H. Moreover,
as noted previously, title IV-E activities other than training are
reimbursed at the rate of 50%. Since the 75% rate is a special,
enhanced rate, it is appropriate to require that a state affirmatively
show that activities constituted training in order to qualify for
reimbursement at that rate. Cf. Missouri Dept. of Social Services, DAB
No. 391 (1983), where the Board stated that "Congress, when it set up a
separate funding category for training, did not intend to pay a higher
than usual rate of FFP for every meeting in which the Title IV-A program
is discussed."

The State clearly failed to carry its burden of proof here. In response
to the Board's request for further information regarding the nature of
the disputed activities, the State stated that it had no information
other than the contractor's log and the affidavits of State staff and
the contractor which it submitted with its initial brief. State's
submission dated 10/1/90; tape recording of 10/31/90 telephone
conference. We find that the descriptions provided by the log of the
activities in question are inadequate. The one-line descriptions are
not in sentence format, and in some instances use abbreviations which
are not explained, or refer to persons whose positions are not
identified. Moreover, they simply do not provide the level of detail
which the Board indicated in a prior decision was necessary to establish
that an activity constituted training. In Missouri Dept. of Social
Services, DAB No. 391 (1983), the Board listed the following as factors
which might be determinative of whether an activity identified in the
record as a "meeting" constituted training: (1) a written agenda which
did more than simply set aside hours for open discussion; (2) the use of
written materials; (3) trainees who came from more than one office; (4)
a trainer who was qualified as an expert; (5) the exercise of tight
control of the agenda by the trainer; (6) substantive information rather
than purely managerial topics addressed; and (7) length in excess of a
few hours. Many of these factors are simply not addressed by the log.
Accordingly, the log does not establish that the activities in question
constituted training.

The affidavits also fail to establish that the activities in question
constituted training. The affidavit of the supervisor of the State
agency's Federal Funding Unit, Dick Anderson, briefly describes two
types of training provided by IHSM (training of child welfare casework
supervisors regarding the new IV-E eligibility procedures, and special
case review training), but does not relate the descriptions to the
activities in IHSM's log. State's ex. A. (In any event, if these
activities are described in the log using the word "training," then they
were considered training by ACYF.) The affidavit of Gordon McDougall, a
community services program manager with the State agency, deals only
with the reasons for entering into the IHSM contract. State's ex. B.
The affidavit of IHSM trainer Rocco D'Amico merely discusses the general
approach used by IHSM. State's ex. C. The affidavit of Marian Demas,
former supervisor of the State agency's Federal Funding Unit, describes
the IHSM contract by module. State's ex. D. However, the descriptions
are too general to relate to the specific activities in the IHSM log. 9/
Finally, the affidavit of Junzo Nakagawa, also a community services
program manager with the State agency, states that he received training,
in both "one-on-one and lecture sessions by IHSM trainers," on the
preparation of a cost allocation program and the development of time
studies. State's ex. E. However, this affidavit too fails to identify
the specific activities in the log to which it pertains. The record
also includes several agendas together with a copy of the log which is
annotated to show the activities covered by each agenda. However, the
agendas do not clearly correspond to the annotated activities and thus
cannot be used as evidence that the activities in question constituted
training. 10/ For example, in one instance, the agenda addresses a
subject matter different from that involved in the training module with
which the log associates the activity. (See agenda "a".) In other
instances, staff as well as individual training activities are covered
by the same agenda. (See agenda "d" and agenda "f".) In still other
instances, the date on the agenda or the number of hours of training for
which it provides does not match the dates or hours of the activities in
the log. (See agenda "g" and agenda "h".) 11/

Since the State had ample opportunity to establish that the activities
coded as delivery of training but not specifically described as such in
fact constituted training, but failed to do so, we conclude that these
activities were not properly claimed at the 75% training rate. Our
conclusion does not apply, however, to the 22 hours the State alleged
were spent on training in the use of software, which ACYF agreed the
State should have a further opportunity to document. (See note 8.)

C. Administration

As noted previously, the State argued that all activities coded in the
log as administration constituted training. We find no basis for this
position. That administrative activities were required in order for the
training to take place does not make administration part of training.
The State's point that any kind of contract requires administrative
activity clearly demonstrates the generic nature of administration.
Accordingly, ACYF was justified in denying reimbursement at the 75% rate
for activities coded as administration.

Our conclusion that administrative activities did not constitute
training does not mean that there were no administrative costs which
could be reimbursed at the 75% rate, however. As discussed below, the
State was entitled to be paid for training activities at a daily rate
which included some administrative costs.

IV. What costs of training activities are allowable

We discussed above whether certain activities constituted training.
There is a further question, however, as to the allowability of the
costs associated with the activities which constitute training. Section
235.64(b) of 45 C.F.R. provides in pertinent part that for agency
training sessions, FFP is available for --

(3) Salaries, fringe benefits, travel and per diem for experts
outside the agency engaged to develop or conduct special
programs; and

(4) Costs of space, postage, teaching supplies, purchase or
development of teaching material and equipment, and costs of
maintaining and operating the agency library as an essential
resource to the agency's training program.

As noted previously, the parties agreed that allowable training costs
are limited to those types of costs specified in the regulation. 12/
The State took the position that all of the costs included in the daily
rate specified in the IHSM contract were allowable under the regulation.
A letter from IHSM to the State stated that the daily rate consisted of
salaries, travel, overhead, general and administrative costs (G & A),
and profit. State's submission dated 10/31/90, attached letter dated
12/2/88. In calculating allowable training costs, however, ACYF
excluded G & A and profit from the daily rate. See State's ex. 1,
attachments to letter dated 1/29/90. (To calculate allowable training
costs, ACYF multiplied the reduced daily rate by the number of 8-hour
days shown in the log which ACYF determined represented training.)

We conclude that ACYF was justified in excluding G & A and profit in
calculating an allowable daily rate for IHSM's activities. There is no
provision in the regulation for profit. IHSM explained that G & A
represented "general costs of doing business which are not directly
related to our on-going projects," including "indirect labor, fringe
benefits, rent, utilities, phone, equipment rental, repairs and
maintenance, insurance, copying, postage and freight, etc." Letter
dated 12/2/88. Of these costs, fringe benefits, rent, utilities,
postage and freight correspond to the types of costs specified in the
regulation. However, the State indicated that it had no information
which would identify the amount of G & A costs represented by these
costs. Tape recording of October 31, 1990 telephone conference.
Accordingly, we cannot find that either profit or G & A costs were
allowable. 13/

The problem here thus lies primarily with the way the State structured
its reimbursement to IHSM under the contract. The State had notice of
the training regulations and should have ensured that it could document
the allowability of its costs, consistent with the regulation. See
Connecticut Dept. of Human Resources, DAB No. 406 (1983). Had the State
structured the contract differently, many of the costs in question might
have been allowed.

Accordingly, we conclude that the cost of training activities identified
in this decision or on remand should be calculated using a daily rate
which excluded G & A and profit. In addition, we conclude that ACYF
properly used this reduced daily rate to calculate the cost of
activities which it identified as training prior to taking the
disallowance.

V. Whether the costs are allowable as direct charges to the title IV-E
program

In its disallowance determination, ACYF stated that the costs of the
IHSM contract should not have been charged directly to the title IV-E
program, regardless of whether the costs were incurred for training or
for a management study, because other programs administered by the State
agency benefitted from the IHSM contract. ACYF later conceded that the
costs of modules 4 through 7 benefitted solely title IV-E and were
properly charged directly to that program. Tape recording of 10/31/90
telephone conference.

The State maintained, however, that the costs of modules 1 through 3
were also properly charged directly to title IV-E. Module 1 involved
the development of a revised cost allocation plan to distribute the
costs incurred by the Department of Social and Health Services to
benefitting programs. Module 2 involved the development of a system for
measuring the time spent by social service and other personnel on
various programs. Module 3 involved the development of a time
measurement system for out-of-home care providers.

In support of its position that the cost of these modules benefitted
solely title IV-E, the State pointed out that the impetus for revising
its cost allocation plan and the time measurement systems was the need
to clarify what costs were reimbursable under title IV-E. The State
argued that since it would not have been necessary to make any changes
in the cost allocation plan or the time measurement systems but for
title IV-E, the cost of these modules should be paid by the title IV-E
program alone. The State also pointed out that the amount of funding
received from federal programs other than title IV-E was unchanged
despite the changes in the cost allocation plan and the time measurement
systems.

We conclude that the cost of modules 1 and 2 should have been charged
through the State's cost allocation plan because the modules benefitted
programs in addition to the title IV-E program. The applicable cost
principles provide that, in order for a cost to be allowable as a grant
cost, it must be allocable to the grant. OMB Circular A-87, Attachment
A, C.1.a. The cost principles further provide that "[a] cost is
allocable to a particular cost objective to the extent of benefits
received by such objective . . . ." Id., C.2.a. 14/ In a prior
decision, the Board elaborated on the concept of "benefit" as it is used
in the cost principles, stating that it "requires that there be an
equitable relationship between the cost and the program or programs to
which it is charged." New York State Dept. of Social Services, DAB No.
1102 (1989), p. 8. An equitable relationship with multiple programs
existed in the case of the cost allocation plan and the State agency
time study since their sole purpose was to distribute costs attributable
to more than one program.

Moreover, this relationship existed even if the revisions to the cost
allocation plan or the State agency time study were prompted by the
desire to identify title IV-E costs more accurately. The State implied
that only title IV-E costs were affected by the revisions. However,
assuming that the total costs distributed through the cost allocation
plan remained the same, a change in the amount of title IV-E costs
necessarily affected the amount distributed to other programs
administered by the State agency.

While the State asserted that the amount charged to two other federal
programs -- title IV-B and title XX -- remained unchanged, it
acknowledged that this was due to the existence of a cap on the amount
of federal funding available for these programs. Tape recording of
10/31/90 telephone conference. Simply because a change in title IV-B or
title XX costs may not have affected federal claiming does not mean that
there was no change in the costs charged to those programs, however.
.Accordingly, any allowable costs associated with modules 1 and 2 of the
contract, whether for training or for a management study, must be
allocated to title IV-E and other programs through the State's cost
allocation plan.

Although the considerations discussed above also apply to the
institutional time study activities in module 3, it is possible that a
different result is required under 45 C.F.R. 1356.60(c)(1). This
regulation provides that "rate setting" is an allowable cost of the
title IV-E program and "may not be claimed under any other . . . Federal
program." It is not clear from the record whether the institutional
time study activities were related to rate setting. The State alleged,
on the one hand, that "[t]he sole purpose [of the institutional time
study] was to measure allowable IV-E maintenance costs in group homes
and institutional placements," which would in turn permit the State to
develop more accurate rates for these providers. On the other hand,
however, the State asserted that it "is not the case" that "the
Institutional Time Study and Cost Reporting procedure was developed to
allow better rate setting." State's submission dated 10/1/90, pp.
10-11. Neither ACYF nor the State specifically addressed the
applicability of the regulation, to which the Board referred in the
Preliminary Analysis and Order to Develop Record. Accordingly, we
remand the appeal to ACYF to determine whether the activities in module
3 constituted rate setting, within the meaning of the regulation, so
that their costs were properly charged directly to title IV-E. A
previously indicated, however, we conclude that the allowable costs in
modules 1 and 2 should be allocated to benefitting programs through the
State's cost allocation plan.

VI. Conclusion

For the foregoing reasons, we conclude that under the particular
contract in question here:

curriculum development may constitute training
under title IV-E if it contributes directly to
the training actually delivered;

activities such as meetings, conversations and
conferences may involve delivery of training,
but the State failed to provide specific
information about the activities in question
which would establish this;

administrative activities do not constitute
training even if they are necessary in order for
training to take place;

profit is not an allowable training cost;

G & A costs which do not correspond to the costs
listed in 45 C.F.R. 235.64(b) are not allowable
training costs; and

the costs of revising a cost allocation plan and
State agency time study are allocable to all
benefitting programs through the applicable cost
allocation plan.

As previously indicated, however, we are unable to resolve this appeal
completely based on the record before us. We therefore remand the
appeal to ACYF for further consideration in accordance with our
decision. Specifically, ACYF should:

(1) determine whether any activities coded as curriculum
development constituted training;

(2) determine whether the State's claim that 22 hours were spent
on training in the use of software can be supported by an
affidavit;

(3) determine the number of hours in module 4 spent conducting
case reviews;

(4) determine the extent to which the costs associated with
management study activities are allowable based on the State's
request for retroactive approval of the IHSM contract; and .
(5) determine whether the activities in module 3 constituted rate
setting and were therefore properly charged directly to title IV-E.

ACYF should issue a new determination which explains the results of the
remand and recomputes the disallowance. The recomputation should take
into account the 115 hours of training referred to in note 2. The State
may appeal any new issues raised by ACYF's determination, pursuant to 45
C.F.R. Part 16.


____________________________ Norval D. (John)
Settle


_____________________________ Alexander G. Teitz


____________________________
Judith A. Ballard Presiding
Board Member.1. In his initial brief, counsel
for ACYF asserted as an additional basis for the
disallowance that the costs were not necessary
for the proper and efficient administration of
the title IV-E program. However, counsel later
stated that the project in question here was
necessary. ACYF's submission dated 10/18/90.

2. ACYF later determined that an additional 115 hours was spent on
training which was reimbursable under title IV-E. ACYF's ex. B.
However, ACYF did not reduce the disallowance to reflect this
determination.

3. Although ACYF initially took the position that the costs of the
entire contract should have been charged through the State's cost
allocation plan, it later agreed that the allowable costs associated
with some of the contract activities would be properly charged directly
to title IV-E at whatever rate of FFP was determined appropriate. Tape
recording of 10/31/90 telephone conference.

4. ACYF conceded that there were no substantive reasons for denying
retroactive approval of the IHSM contract as a management study, but
asserted that a written request for retroactive approval was required
before it could determine the allowability of the contract costs which
related to a study rather than to training. ACYF's submission dated
10/18/90. The State agreed to submit such a request. Tape recording of
10/31/90 telephone conference.

5. ACYF also argued initially that the IHSM contract could not be
considered a training contract since the State did not specifically
refer to the IHSM contract in its title IV-B plan. In support of its
argument, ACYF cited the requirement in 45 C.F.R. 1356.60(b)(2) that
"[a]ll training activities and costs funded under title IV-E shall be
included in the State agency's training plan for title IV-B." The State
asserted that the regulation did not require the plan to specifically
identify all training contracts, and argued that it complied with the
regulation since its title IV-B plan referred generally to the type of
training provided by IHSM. ACYF later acknowledged that the regulation
did not require a specific reference to the IHSM contract, although ACYF
maintained that one would expect a specific reference given the level of
detail in the State plan regarding other contracts. Tape recording of
10/31/90 conference. In any event, since ACYF was willing to allow some
of the contract costs as training, it cannot reasonably rely on any
failure to specifically identify this contract in the title IV-B plan as
a basis for not treating the remaining costs as training.

6. The State asserted that "this regulation does not explicitly apply
to the Title IV-E program . . . ." State's brief, p. 12, n. 33.
However, the parties did not dispute the observation in the Board's
Preliminary Analysis and Order to Develop Record that section 235.61
appears to be applicable to title IV-E to the extent that it defines
terms used in sections 235.63 through 235.66(a), which are made
applicable to the title IV-E program by 45 C.F.R. 1356.60(b)(3).

7. The State contended that written curricula had not only been
developed, but had also been forwarded to ACYF, and provided copies of
the documents previously furnished to ACYF. State's submission dated
10/5/90. However, these documents are agendas which allegedly
correspond to activities coded in IHSM's log as training, not as
curriculum development. In any event, the agendas list only topics to
be addressed and do not reflect the effort which was required to develop
these topics. Accordingly, they do not establish that curriculum
development took place.

8. The State noted that ACYF had overlooked one activity which was
coded as training and described in the log as follows: "Install WA IV-E
database system and train users dev/mod F." (Emphasis added.) ACYF
identified this activity in its own codes as "I" for "install database,"
and concluded that it did not constitute training. ACYF's ex. B.
However, the State subsequently asserted that of the 24 hours spent on
this activity, two hours were for installing the system on the State's
personal computers, and 22 hours were for training in the use of the
software, which was developed by IHSM for the State of Maryland for
managing IV-E time studies and was provided to Washington at no cost.
State's submission dated 10/1/90. ACYF stated that, although it was not
apparent from the log that 22 hours were spent on training, ACYF would
accept an affidavit to this effect from the State. Tape recording of
12/31/90 telephone conference. Thus, ACYF should on remand give the
State an opportunity to provide a supporting affidavit and increase the
number of hours of training accordingly.

9. One exception involves activities in module 4 which the log
describes as case reviews or special case reviews. According to the
Demas affidavit, in module 4, "IHSM trainers spent extensive time with
DCFS staff reading sample case records to identify problems encountered
by DCFS in determining eligibility procedures." Id. It is clear from
the description in the affidavit that the case reviews themselves did
not involve the delivery of training despite the fact that they are
coded in the log as training. However, since actual training was based
directly on the case reviews, we conclude that the case reviews
constituted curriculum development and can properly be reimbursed at the
75% training rate. There is some discrepancy in the record with respect
to the number of hours which correspond to the case reviews described in
the Demas affidavit. Compare State's ex. 13, 10th unnumbered page, and
State's submission dated October 5, 1990, p. 40. We therefore remand
this matter to ACYF to determine the number of hours involved.

10. The State did not submit the agendas to the Board for this
purpose. Instead, the State's letter dated 10/5/90 stated that the
agendas were being submitted as evidence that written curricula were
developed under the IHSM contract.

We do not consider the agendas which pertain solely to activities which
ACYF determined constituted training.

11. We assume that agenda "h" is the unmarked agenda between the
agendas marked "g" and "i".

12. This view is amply supported by prior Board decisions involving a
similarly worded provision applicable to the old title XX social
services grants. See New York State Dept. of Social Services, DAB No.
520 (1984), and Pennsylvania Dept. of Public Welfare, DAB No. 451
(1983). The State had argued in its initial brief that all of the costs
of administering a training contract were allowable pursuant to an ACYF
policy issuance, ACYF-PIQ-82-17. However, the State did not pursue this
argument following the issuance of the Board's Preliminary Analysis and
Order to Develop Record, in which the Board stated that --

Since the PIQ was issued after the regulations, it is arguable
that the PIQ, which is general in nature, must be read in light
of the more specific regulations. In any event, to the extent
that the PIQ is inconsistent with the regulations, it appears
that the regulations should govern since they were clearly
binding on the State.

Preliminary Analysis, p. 13.

13. IHSM stated that overhead included the same types of costs as G &
A, except that the former was "specific to all on-going projects."
Letter dated 12/2/88. ACYF did not explain why it allowed all overhead
costs as part of the daily rate while disallowing G & A costs if they
involved similar costs.

14. In addition, the allocation of certain title IV-E costs is
specifically required by an ACYF issuance, ACYF-PA-87-05, which states
in part --

Allowable administrative costs for activities . . . that are not
linked directly to the eligibility of children must be allocated
to title IV-E, State foster care, and other State/Federal
programs in such a manner as to assure that each participating
program is charged its proportionate share of the costs.

State's ex. 12, pp.