Documents
Migration Planning Guidance
A set of migration tools was developed in 2006 and compiled in a document titled "HR LOB Migration Roadmap." This document was presented to the HR LOB Multi-Agency Executive Strategy Committee (MAESC) in September 2006 and approved for use in the Migration Planning Guidance. Its purpose is to:
The document includes tools used for the e-Payroll migration and additional new tools proposed for use in SSC migrations based on best practice research. Each tool falls into one of three types:
The tables that appear in this chapter define each tool, grouped by type, and link the documents to a website that provides the tools.
The following graphical depiction shows the five phase methodology (introduced in Section 6 above) with corresponding practices, inputs, outputs, and roles and duties as assigned to each participant in the transformation process.
Figure 12: Practices, duties, inputs and outputs by Phase
Deliverables - In accordance with the HR LOB Migration Roadmap document, customer agencies and/or SSCs are required to submit these deliverables to the HR LOB PMO during the migration process.
The column titled "Submission Responsibility" denotes which organization is responsible for submission. The columns titled "HR LOB PMO Use" and "Use Description" indicates how the deliverable will be used by the HR LOB PMO during the migration process:
Report - HR LOB PMO will use information in the deliverable to report on migration progress.
Oversight - HR LOB PMO will use information in the deliverable to monitor migration progress and take action as necessary and / or appropriate.
Review - HR LOB PMO will review the information in the deliverable to use in downstream LOB activities (e.g., EA deliverables, requirements gathering, future migrations).
Document |
Document Description |
Submission
|
HR LOB PMO Use |
Use Description |
Submission Schedule |
---|---|---|---|---|---|
Notice of Intent to Conduct a Competitive Migration |
A notice in FedBizOpps of an agency’s intent to conduct a public-private competition for HR management shared services |
Agency |
Oversight |
Inform HR LOB of agency’s intent to conduct a competition |
Five (5) business days before posting to FedBizOpps |
Solicitation to both (public and private) sectors |
An agency solicitation inviting offers from at least three public SSCs and at least three private SSCs on Schedule 738.X |
Agency |
Oversight |
Inform HR LOB of agency’s intent to competitively select an SSC |
Five (5) business days before posting to FedBizOpps |
Exception Business Case |
A full justification developed by agencies that wish to make a selection based on a limited form of competition |
Agency |
Oversight |
Inform HR LOB of agency’s intent to select an SSC using a limited for of competition |
Upon submission to OMB |
Project Plan |
Establishes a schedule of migration activities performed by the agency and SSC. A mechanism to track activities and budget against plan |
Customer agency will work with SSC to complete. The SSC will submit to HR LOB PMO |
Report and Oversight |
Track activities against plan. Report to HR LOB PMO and other external agencies on migration progress. Provide for early detection of migration issues |
60 days after customer kick-off meeting and subsequent periodic updates |
Service Level Agreement |
Outlines the scope of services the SSC will supply to the customer agency |
SSC |
Oversight |
Binding document to hold SSC and customer agency accountable for prescribed roles, responsibilities and cost |
30 days after execution |
Interagency Agreement |
Indicates the terms under which services will be provided to the customer |
SSC |
Oversight |
Binding document to hold provider and customer agency accountable |
30 days after execution and migration start |
Migration Cost Report |
Establishes migration costs for providers and customer agencies |
Customer agency will work with SSC to complete. The SSC will submit to HR LOB PMO |
Report |
Per Memorandum of Understanding, OPM has responsibility to conduct reviews of HR SSC delivery against established measures and metrics. Baseline measures will aid in reporting performance progress in Y1 and out years as well as cost savings against the business case |
10th of each month |
Risk Analysis Report |
Identifies any customer-specific migration risk plus activities that will be initiated to eliminate or mitigate the risk |
Customer agency will work with SSC to complete. The SSC will submit to HR LOB PMO |
Oversight |
Manage migration risk and feed HR LOB Risk Management Report |
30 days after completion of the preparation / analysis phase |
Communications Plan |
Creates a group of integrated activities for planning, developing and issuing project-related communications. It is designed to build stakeholder acceptance and support – both internally and externally – for process and system changes |
Customer agency will work with SSC to complete. The SSC will submit to HR LOB PMO |
Report |
Feeds HR LOB communication plan |
30 days after completion of the initial project plan |
Fit Gap Analysis Report |
Identifies all system or business process changes that will be needed for migration |
Customer agency will work with SSC to complete. The SSC will submit to HR LOB PMO |
Oversight |
Manage migration risk |
60 days after the completion of the preparation / analysis phase |
Summarizes the overall results of the migration and highlights any critical standardization opportunities discovered during the course of migration |
Customer agency will work with SSC to complete. The SSC will submit to HR LOB PMO |
Review |
Incorporate lessons learned into future HR LOB deliverables and activities (e.g., EA deliverables, service delivery model, future migrations) |
45 days after migration |
Table 4: Migration Deliverables
Information - the documents in this section are for information purposes only and include best practices and other helpful resources for potential use by the customer agencies and SSCs. They can be used as reference materials for the facilitation of successful migrations to the selected SSC.
Document |
Document Description |
Audience |
---|---|---|
Change Management Best Practices |
Used to identify and size constituencies impacted by the migration and assesses the magnitude of impact to each key constituency in terms of change in job roles and responsibilities, required skills and knowledge, processes and enabling technologies. |
SSC |
Details key assessment activities for transitioning affected staff to a shared services environment |
Customer Agency |
Table 5: Migration Information
Templates - the documents in this section include recommended templates for customer agencies and SSCs across multiple areas including operational readiness, training, and IT security. These templates can be modified by agencies and SSCs to fit their situation and environment.
Document |
Document Description |
Audience |
---|---|---|
Provides an agenda, objectives and a starter deck for a migration kick-off session |
SSC |
|
Operational Readiness Assessment |
Verifies shared service centers have implemented controls necessary to deliver consistent, efficient services in a secure and effective manner. May serve as input into a go/no go decision for migration of a customer agency. |
SSC |
Training Strategy Template |
Details major components of a training strategy for assessing customer agency training needs and developing and delivering training on processes and systems |
SSC |
Common Rules of Behavior Policy |
Specifies common behavioral guidelines for all SSC systems with respect to IT security. |
SSC |
Addresses the need for the interconnection and the security controls required and implemented to protect the confidentiality, integrity, and availability of the systems and data. |
SSC |
Table 6: Migration Templates