Key Milestones |
Completion Date Actual - A Target - T |
Application Tendered |
09/20/07 - A |
Acceptance Review |
Acceptance Review Start |
10/01/07 - A |
Docketing Decision Letter Issued/Acceptance Review Complete |
11/29/07 - A |
Review Schedule Established/Schedule Letter Issued to Applicant |
To be determined* |
Safety Review |
Phase 1 - Requests for Additional Information (RAIs) Issued to Applicant |
|
Phase 2 - SER with Open Items issued |
|
Phase 3 - ACRS Review of SER with Open Items Complete |
|
Phase 4 - Advanced SER with no Open Items Issued |
|
Phase 5 - ACRS Review of SER with no Open Items Complete |
|
Phase 6 - Final SER Issued |
|
Environmental Review |
Phase 1 - EIS Scoping Summary Report issued |
09/26/08 - A |
Phase 2 - Draft EIS issued to EPA |
To be determined* |
Phase 3 - Response to public comments on draft EIS issued |
|
Phase 4 - Final EIS issued to EPA |
|
Hearing |
Commission or ASLB hold mandatory hearing |
|
License |
Commission decision on issuance of COL application |
|
* The NRC will establish a schedule after STPNOC resolves vendor support issues and makes any COL revisions necessary to allow staff’s review of the application in full. See the January 30, 2008 letter below for additional details.