Home > Nuclear Reactors > New Reactors > Combined License Applications > River Bend Station, Unit 3 Application
River Bend Station, Unit 3 Application
|
Who: |
Entergy Operations, Inc. (EOI)
|
What: |
Application for a combined license (COL) for a single Economic Simplified Boiling Water Reactor (ESBWR) designated as River Bend Station, Unit 3
|
When: |
September 25, 2008 (date of application submittal)
|
Where: |
EOI's River Bend Station site near St. Francisville, Louisiana |
|
On this page:
Some links on this page are to documents in our our Agencywide Documents Access and Management System (ADAMS). For additional information, see our Plugins, Viewers, and Other Tools.
Reference Documents
![To top of page](https://webarchive.library.unt.edu/eot2008/20090118072508im_/http://www.nrc.gov/images/navigation/go-top.gif)
Applicant Documents
Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Design Control Documents would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.
Date |
Description |
12/21/08 |
LiDAR Data re Information Provided to Address the First Item of Supplemental Information |
11/13/08 |
RBS Meteorological Data |
09/25/08 |
EOI's transmittal letter for River Bend Station Unit 3 COLA
- Part 1 - General and Administrative Information
- Part 2 - Final Safety Analysis Report (FSAR)
- Part 3 - Environmental Report
- Part 4 - Technical Specifications
- Part 5 - Emergency Plan
- Part 6 - Limited Work Authorization (LWA)/Site Redress Plan
- Part 7 - Departures Report
- Part 8 - Safeguards/Security Plans
- Part 9 - Withheld Information (Proprietary, Sensitive and SUNSI)
- Part 10 - License Conditions and Inspection, Tests, Analyses and Acceptance Criteria (ITAAC)
- Part 11 - Enclosures
|
![To top of page](https://webarchive.library.unt.edu/eot2008/20090118072508im_/http://www.nrc.gov/images/navigation/go-top.gif)
Application Review Schedule
Key Milestones |
Completion Date Actual - A Target - T |
Application Tendered |
09/25/08 - A |
Acceptance Review |
Acceptance Review Start |
10/01/08 - A |
Docketing Decision Letter Issued/Acceptance Review Complete |
12/04/08 - A |
Review Schedule Established/Schedule Letter Issued to Applicant |
Mid-February 2009 - T |
Safety Review |
Phase 1 - Requests for Additional Information (RAIs) Issued to Applicant |
|
Phase 2 - SER with Open Items issued |
|
Phase 3 - ACRS Review of SER with Open Items Complete |
|
Phase 4 - Advanced SER with no Open Items Issued |
|
Phase 5 - ACRS Review of SER with no Open Items Complete |
|
Phase 6 - Final SER Issued |
|
Environmental Review |
Phase 1 - Environmental impact statement (EIS) summary report issued |
|
Phase 2 - Draft EIS issued to EPA |
|
Phase 3 - Response to public comments on draft EIS issued |
|
Phase 4 - Final EIS issued to EPA |
|
Hearing |
Commission or ASLB hold mandatory hearing |
|
License |
Commission decision on issuance of COL application |
|
Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.
![To top of page](https://webarchive.library.unt.edu/eot2008/20090118072508im_/http://www.nrc.gov/images/navigation/go-top.gif)
NRC Documents
Date |
Description |
12/04/08 |
Acceptance for Docketing of the Entergy Operations, Inc. Application for a Combined License For River Bend Station Unit 3 and Associated Federal Register Notice
|
11/10/08 |
Acknowledgment of Receipt of the Combined License Application for River Bend Station Unit 3 and Associated Federal Register Notice
|
![To top of page](https://webarchive.library.unt.edu/eot2008/20090118072508im_/http://www.nrc.gov/images/navigation/go-top.gif)
Requests for Additional Information
Category |
RAI Date |
RAI Letter No. and Subject |
Applicant Response |
Safety |
|
None Issued Yet |
|
Environmental |
|
None Issued Yet |
|
![To top of page](https://webarchive.library.unt.edu/eot2008/20090118072508im_/http://www.nrc.gov/images/navigation/go-top.gif)
Public Meetings
Date |
Description |
11/18/08 |
Public Outreach Meeting
|
12/11/08 |
Public Outreach Meeting
|
![To top of page](https://webarchive.library.unt.edu/eot2008/20090118072508im_/http://www.nrc.gov/images/navigation/go-top.gif)
Contacts
Contacts for the River Bend Station COL Application |
Safety Project Manager |
Mark Tonacci |
Environmental Project Manager |
Andy Kugler |