Applications Received
Bell Bend Unit 1
Bellefonte Units 3 & 4
Callaway Unit 2
Calvert Cliffs Unit 3
Comanche Peak Units 3 & 4
Fermi Unit 3
Grand Gulf Unit 3
Levy County Units 1 & 2
Nine Mile Point Unit 3
North Anna Unit 3
River Bend Station Unit 3
Shearon Harris Units 2 & 3
South Texas Project Units 3 & 4
Victoria County Station Units 1 & 2
Virgil C. Summer Units 2 & 3
Vogtle Units 3 & 4
William States Lee III Units 1 & 2

River Bend Station, Unit 3 Application

River Bend Station
Who:   Entergy Operations, Inc. (EOI)

What:   Application for a combined license (COL) for a single Economic Simplified Boiling Water Reactor (ESBWR) designated as River Bend Station, Unit 3

When:   September 25, 2008 (date of application submittal)

Where:   EOI's River Bend Station site near St. Francisville, Louisiana

On this page:

Some links on this page are to documents in our our Agencywide Documents Access and Management System (ADAMS). For additional information, see our Plugins, Viewers, and Other Tools.

Reference Documents

To top of page

Applicant Documents

Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Design Control Documents would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.

Date Description
12/21/08 LiDAR Data re Information Provided to Address the First Item of Supplemental Information
11/13/08 RBS Meteorological Data
09/25/08 EOI's transmittal letter for River Bend Station Unit 3 COLA
  • Part 1 - General and Administrative Information
  • Part 2 - Final Safety Analysis Report (FSAR)
  • Part 3 - Environmental Report
  • Part 4 - Technical Specifications
  • Part 5 - Emergency Plan
  • Part 6 - Limited Work Authorization (LWA)/Site Redress Plan
  • Part 7 - Departures Report
  • Part 8 - Safeguards/Security Plans
  • Part 9 - Withheld Information (Proprietary, Sensitive and SUNSI)
  • Part 10 - License Conditions and Inspection, Tests, Analyses and Acceptance Criteria (ITAAC)
  • Part 11 - Enclosures

To top of page

Application Review Schedule

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 09/25/08 - A
Acceptance Review
Acceptance Review Start
10/01/08 - A
Docketing Decision Letter Issued/Acceptance Review Complete
12/04/08 - A
Review Schedule Established/Schedule Letter Issued to Applicant
Mid-February 2009 - T
Safety Review
Phase 1 - Requests for Additional Information (RAIs) Issued to Applicant
 
Phase 2 - SER with Open Items issued
 
Phase 3 - ACRS Review of SER with Open Items Complete
 
Phase 4 - Advanced SER with no Open Items Issued
 
Phase 5 - ACRS Review of SER with no Open Items Complete
 
Phase 6 - Final SER Issued
 
Environmental Review
Phase 1 - Environmental impact statement (EIS) summary report issued
 
Phase 2 - Draft EIS issued to EPA
 
Phase 3 - Response to public comments on draft EIS issued
 
Phase 4 - Final EIS issued to EPA
 
Hearing
Commission or ASLB hold mandatory hearing
 
License
Commission decision on issuance of COL application
 

Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.

To top of page

NRC Documents

Date Description
12/04/08 Acceptance for Docketing of the Entergy Operations, Inc. Application for a Combined License For River Bend Station Unit 3 and Associated Federal Register Notice
11/10/08 Acknowledgment of Receipt of the Combined License Application for River Bend Station Unit 3 and Associated Federal Register Notice

To top of page

Requests for Additional Information

Category RAI Date RAI Letter No. and Subject Applicant Response
Safety   None Issued Yet  
Environmental   None Issued Yet  

To top of page

Public Meetings

Date Description
11/18/08 Public Outreach Meeting
12/11/08 Public Outreach Meeting

To top of page

Contacts

Contacts for the River Bend Station COL Application
Safety Project Manager Mark Tonacci
Environmental Project Manager Andy Kugler
Contact a Public Affairs Officer