Combined License Applications for New Reactors
Location of Projected New Nuclear Power Reactors
Applications Received
Bell Bend Unit 1
Bellefonte Units 3 & 4
Callaway Unit 2
Calvert Cliffs Unit 3
Comanche Peak Units 3 & 4
Fermi Unit 3
Grand Gulf Unit 3
Levy County Units 1 & 2
Nine Mile Point Unit 3
North Anna Unit 3
River Bend Station Unit 3
Shearon Harris Units 2 & 3
South Texas Project Units 3 & 4
Victoria County Station Units 1 & 2
Virgil C. Summer Units 2 & 3
Vogtle Units 3 & 4
William States Lee III Units 1 & 2

Levy County Nuclear Site, Units 1 and 2 Application

Levy County Nuclear Site
Who:   Progress Energy Florida, Inc. (PEF)

What:   Application for a combined license (COL) for two Westinghouse Advanced Passive 1000 (AP1000) Pressurized Water Reactors (PWRs) designated as Levy County Units 1 and 2

When:   July 30, 2008 (date of application submittal)

Where:   PEF’s site in Levy County, Florida

On this page:

Some links on this page are to documents in our our Agencywide Documents Access and Management System (ADAMS). For additional information, see our Plugins, Viewers, and Other Tools.

Reference Documents

To top of page

Applicant Documents

Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Design Control Documents would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.

Date Description
07/28/08 Progress Energy Florida, Inc. transmittal letter for Levy County Nuclear Plant Units 1 & 2 COLA
  • Part 1 - Administrative and Financial Information
  • Part 2 - Final Safety Analysis Report (FSAR)
  • Part 3 - Environmental Report
  • Part 4 - Technical Specifications
  • Part 5 - Emergency Plan
  • Part 6 - Limited Work Authorization (LWA)
  • Part 7 - Departures and Exemption Requests
  • Part 8 - [This Part contains safeguards information which is withheld from public availability]
  • Part 9 - [This Part contains other information which is withheld from public availability]
  • Part 10 - License Conditions and Inspection, Tests, Analyses and Acceptance Criteria (ITAAC)
  • Part 11 - Information Incorporated By Reference

To top of page

Application Review Schedule

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 07/30/08 - A
Acceptance Review
Acceptance Review Start
08/04/08 - A
Docketing Decision Letter Issued/Acceptance Review Complete
10/06/08 - A
Review Schedule Established/Schedule Letter Issued to Applicant
01/30/09 - T
Safety Review
Phase 1 - Requests for Additional Information (RAIs) Issued to Applicant
 
Phase 2 - SER with Open Items issued
 
Phase 3 - ACRS Review of SER with Open Items Complete
 
Phase 4 - Advanced SER with no Open Items Issued
 
Phase 5 - ACRS Review of SER with no Open Items Complete
 
Phase 6 - Final SER Issued
 
Environmental Review
Phase 1 - Environmental impact statement (EIS) summary report issued
 
Phase 2 - Draft EIS issued to EPA
 
Phase 3 - Response to public comments on draft EIS issued
 
Phase 4 - Final EIS issued to EPA
 
Hearing
Commission or ASLB hold mandatory hearing
 
License
Commission decision on issuance of COL application
 

Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.

To top of page

NRC Documents

Date Description
12/08/08 Notice of Order, Hearing, and Opportunity to Petition for Leave to Intervene
10/24/08 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping
10/06/08 Notification of Docketing and Federal Register Notice
09/15/08 Acknowledgement of Receipt of Application and Federal Register Notice

To top of page

Requests for Additional Information

Category RAI Date RAI Letter No. and Subject Applicant Response
Safety 11/25/08 RAI Letter No. 01 SRP Section 15.00.03  
11/25/08 RAI Letter No. 02 SRP Section 10.04.06  

To top of page

Public Meetings

Date Description
12/04/08 Levy County Public Scoping Meeting
08/21/08 Levy County S-COLA Orientation
07/28/08 Levy County Geotechnical Topics
06/05/08 Public Outreach

To top of page

Contacts

Contacts for the Levy County Nuclear Site COL Application
Safety Project Manager Brian Anderson
Sr. Environmental Project Manager Douglas Bruner
Environmental Project Manager Jessie Muir
Contact a Public Affairs Officer