skip navigation links 
 
 Search Options 
Index | Site Map | FAQ | Facility Info | Reading Rm | New | Help | Glossary | Contact Us blue spacer  
secondary page banner Return to NRC Home Page

Quehanna (Commonwealth of PA)

1.0 Site Identification

Location: Harrisburg,PA
License No.: 37-17860-02
Docket No.: 030-29288
License Status: Decon
Project Manager: Sarah Michonski (NRC Decommissioning Contact)

2.0 Site Status Summary

The Commonwealth of Pennsylvania owns the site and had leased it to Permagrain Products, Inc. (PPI) for the operation of a Co-60 irradiator. After PPI declared bankruptcy in 2002, the license was transferred to the Commonwealth of Pennsylvania in December 2002. Sr-90 is the main contaminant of concern at the facility, and was used in the manufacture of thermoelectric generators. Sr-90 contamination is found in buildings as well as in surface and subsurface soil. Contaminated groundwater is not present at the site. The decommissioning, which started in July 1998 is being performed by Energy Solutions (formerly Scientech). Areas which do not meet NRC criteria for unrestricted use were identified as the six hot cells, their respective isolation rooms, two ventilation systems, an overhead crane system, a number of ancillary rooms, and the wastewater treatment building. Decontamination and demolition of the cell structures was completed in 2004. Decontamination of the service area floor is complete. FSS was initiated and was completed in December 2004. The licensee's FSS Report along with a request to terminate the license was submitted in February 2005. An ORISE confirmatory survey of the facility was conducted in May 2005 after the licensee submitted the FSSR. The ORISE survey identified numerous areas of contamination in excess of the NRC approved limits for unrestricted release. Based on these survey results, the licensee performed additional surveys and concluded that some type of migration of radioactive material is taking place in the concrete at the facility. The licensee plans to monitor this situation until the spring of 2006 before deciding upon a course of action for decontaminating and releasing the site for unrestricted use. On March 13, 2006 NRC received a revised DP from PADEP in which PADEP will depart from their previous RG 1.86 approach and complete site closure under 10 CFR 20, Subpart E. The revised DP was approved by NRC in October 2006. In December 2006, ORISE conducted a confirmatory survey of the above grade structure and confirmed that the above grade structure met the release limits of the DP. The licensee plans to demolish the above grade structure and dispose of the demolition debris in a commercial land fill. The licensee is evaluating disposal options.

3.0 Major Technical or Regulatory Issues

The regulatory authority for the site has been turned over to the Commonwealth of Pennsylvania after it became an Agreement State.

4.0 Estimated Date For Closure

03/31/2008



Privacy Policy | Site Disclaimer
Friday, September 26, 2008