Power Uprates
Approved Applications
Pending Applications
Expected Applications

Pending Applications for Power Uprates

The following power uprates are currently under review by the NRC. The licensees for the following plants have not been authorized by the NRC to operate the plants at power levels that reflect the following increases.

(TYPE -- S = Stretch; E = Extended; MUR= Measurement Uncertainty Recapture)
(TBD = To Be Determined)

NO. PLANT % UPRATE MWt SUBMITTAL DATE PROJECTED COMPLETION
DATE
TYPE
1 Browns Ferry 2 15 494 06/25/2004 Spring 2009 E
2 Browns Ferry 3 15 494 06/25/2004 Spring 2010 E
3 Browns Ferry 1 15 494 06/28/2004 Spring 2009 E
4 Calvert Cliffs 1 1.4 37 08/29/2008 March 2009 MUR
5 Calvert Cliffs 2 1.4 37 08/29/2008 March 2009 MUR
6 Monticello 12.9 229 11/05/2008 December 2009 E
  Total MWt   1785
     
  Total MWe   595      