Date | Event | Description |
08/05 |
Employer Symposium |
MA CSE senior management first saw the presentation for e-IWO |
09/02/05 - Present |
OCSE Conference calls |
Systems staff began attending calls. |
09/05 - 09/06 |
Management Prioritization / Assessment of needs |
- Several large projects were going on at the same time so we had to wait for resources.
- Began to assess what changes needed to be made to compliment eIWO on our system
- Needed to tighten security to our Employer Table and allow limited staff update abilities.
- Clean up of multiple/erroneous entries for DFAS on our Employer Table
|
Date | Event | Description |
05/01/06 - 09/07/06 |
Requirements Design document |
The requirements gather expanded to include other changes so requirements took a little longer.
- Made forms changes for IWO and Income Levy process.
- Removal of several forms from packages
- Modification of Income Levy threshold
- Expanded ability to print IWO/ Income Levy forms to specific areas (i.e. locally, centrally, overnight or immediately)
|
10/05/06 - 12/13/06 |
Solution Design document |
More detailed than a requirements document and identified areas
needing further clarification of changes requested. |
Date | Event | Description |
12/13/06 - 02/23/07 |
Technical Specifications document |
Technical description of how and what changes were to be done.
Including what coding was to be changed. |
02/23/07 - 05/14/07 |
Programming / Coding |
- Coding changes began to be done.
- Test files with DFAS began on 3/28/07, which allowed any
issues to be identified and corrected.
- Environment issues cause some additional delays.
|
05/14/07 - 06/08/07 |
Systems / QA Testing |
Testing for all other changes made during this project:
forms, threshold amounts, printing locations. |
June 13, 2007 Implementation !!!
- Massachusetts began exchanging with DFAS on a daily basis.
- Post production monitoring was conducted for one month which allows us to
identify any additional issues that were not caught or anticipated during testing.