NRC Docketing Review and Hearing Opportunity Schedule
The U.S. Nuclear Regulatory Commission (NRC) has established the following schedule for its docketing review and hearing opportunities associated with the license application that the U.S. Department of Energy (DOE) submitted on June 3, 2008, seeking authorization to construct a high-level waste geologic repository at Yucca Mountain, Nevada:
Hearing Process
Schedule for the Proceeding on Consideration of Construction Authorization for High-Level Waste Geologic Repository (Before SER is Issued)
Schedule for the Proceeding on Consideration of Construction Authorization for High-Level Waste Geologic Repository (After SER is Issued)
Key Milestones |
Completion Date
(days after receipt of application) |
Publication of FRN announcing opportunity for hearings |
10/22/08 |
Deadline for filing petitions for intervention & contentions |
12/22/08 |
Answers to intervention and interested government participant Petitions |
02/10/09 |
Petitioner’s response to answers |
02/24/09 |
First Prehearing Conference |
03/12/09 |
First Prehearing Conference Order identifying participants in proceeding, admitted contentions, and setting discovery and other schedules |
05/11/09 |
Docketing Acceptance Review
Key Milestones |
Completion Date
(days after receipt of application) |
Publication of Federal Register notice (FRN) announcing receipt and availability of DOE application |
06/17/08 |
Publication of FRN announcing (1) NRC decision regarding docketing of the DOE application, and (2) NRC staff position regarding adoption of the DOE Environmental Impact Statement (EIS) |