Activities Underway

 

Office of Safeguards and Security Evaluations (OA-10)

 

CH/ANL-W Comprehensive Inspection:  The closeout briefing was presented to the Chicago Operations Office on November 4, 2002.  Comments on the draft report and the preliminary corrective action plan are due to OA on November 20, 2002.

 

LANL Inspection: Work continues on the development of the LANL Inspection Plan.  An on-site coordination visit was conducted this week to plan the force-on-force performance test.  The site visits for planning, data collection, and performance testing have been scheduled.

 

Composite Adversary Team:  Solicitation continues for new and replacement Composite Adversary Team (CAT) members.  Planning is underway for the upcoming CAT training scheduled for January 13-17, 2003 at Camp Pendleton, California.

 

CMPC Special Reviews:  The ANL-W special review report has been drafted and is ready for review by the management review board.  The next special review begins next week at Y-12.

 

OA-10 staff met with SO-14 to coordinate the installation of planned enhancements to the OA classified document accountability system.  The enhancements are scheduled to be in place the week of November 18.

 

Office of Cyber Security Evaluations (OA-20)

 

Support to the Office of Energy Assurance:  OA-20 is providing support to DOE’s Office of Energy Assurance (OEA) by conducting an assessment of cyber security vulnerabilities associated with critical infrastructure assets.  This effort is intended to support the transfer cyber security assessment processes to OEA in support the Department’s efforts to protect critical energy infrastructure assets throughout the United States.  Testing and onsite assessment activities have been completed.  The draft report is being prepared.

 

Cyber Security Evaluation of the Los Alamos National Laboratory:  OA-20 personnel have begun planning activities associated with an upcoming inspection of cyber security at the Los Alamos National Laboratory.  The OA-20 Office Director is onsite this week for a scoping visit.  Onsite inspection activities will begin the week of November 18th.

 

Cyber Security Evaluation of the Chicago Operations Office:  Testing and inspection activities have been completed for the evaluation of cyber security at the Chicago Operations Office.  A final draft report was transmitted to the Chicago Operations Office for review.

 

Perimeter Scanning Project:  OA-20 personnel have initiated a special study (Perimeter Scanning Project) to map and identify vulnerabilities in DOE computer networks exposed to potential attack from the Internet.  The Project Plan has been approved and was distributed to headquarters and field organizations.  Outreach activities to communicate project objectives and coordinate vulnerability testing agreements have been initiated.  Several vulnerability testing agreements with DOE organizations have been signed and scanning activities have commenced.

 

Unannounced Testing/Red Teaming:  OA-20 personnel have continued to refine a concept paper on establishing an unannounced cyber security performance testing capability within the Office.

 

Office of Emergency Management Oversight (OA-30)

 

The final report of the Inspection of Environment, Safety, and Health Management and Emergency Management at the Nevada Test Site, October 2002 is now being prepared for distribution.  The date for the interim corrective action plan has been extended 2 weeks and will be submitted by November 29.

 

The combined OA-30 and OA-50 Pantex Inspection data collection phase was conducted from October 28 to November 8.  Onsite validation and closeout is scheduled for the week of November 18.

 

OA-30 and OA-50 are in the initial stages of planning for an inspection of Sandia National Laboratories, New Mexico.  The scoping visit was completed the week of October 15-17 and the final plan is being developed.

 

OA-30 has notified the Office of Transportation Safeguards of an emergency management program inspection to be conducted in 2003.  Planning has begun and a scoping visit has been scheduled.

 

Office of Environment, Safety and Health Evaluations (OA-50)

 

OA-50 has drafted a document for OA-1 consideration that summarizes a series of observations to support the FY 2002 Department of Energy Annual Performance Plan for review.  The observations from OA provided information from selected inspections at SC, EM, and NNSA sites as well as general information from all FY ’02 reviews.  The office is also looking at the FY 2003 plan for inclusion with the FY 2003 inspection plans.

 

A final approved corrective action plan for the safety and emergency management inspection at LLNL was received on November 1, 2002.

 

A corrective action plan for the Nevada Test Site (NTS) inspection has been requested.  The site had no comments on the report.

 

Onsite inspection activities for the Pantex safety and emergency management inspection were initiated on October 28, 2002.

 

Coordination of the upcoming safety and emergency management inspection at the Sandia National Laboratory continues.

 

Discussions with Y-12 Site Office management regarding the scoping visit for the safety management inspection are ongoing.

 

Activities Completed

 

Office of Safeguards and Security Evaluations (OA-10)

 

OA-10 participated in a meeting with representatives from the Offices of Security,

Counter-intelligence, the National Nuclear Security Administration, and others to develop a consolidated DOE response to address concerns identified in an IG report regarding the foreign visits and assignments program. 

 

Office of Emergency Management Oversight (OA-30)

 

OA-30 met with the Director of Administration, ME-40, to review progress made in response to the Review of the Headquarters Facilities Emergency Response Plans, March 2002.  ME initiated several significant improvements and is effectively working closely with the Office of Security (SO) and the principal secretarial offices.  OA will continue to monitor the program implementation progress and participate as a member of the HQ Occupant Emergency Planning Team.

 

OA-30 has expressed concerns with, and offered options to address, the evolving definition of roles and responsibilities between SO and the National Nuclear Security Administration (NNSA) for the management of the HQ Emergency Operations Center and the management of the HQ Emergency Management Team.  OA noted that the revised version of DOE Order 151.1B, currently in REVCOM for comments, does not adequately define SO and NNSA responsibilities and interfaces for these functions.  OA-30 will be providing formal comments on the revisions proposed in DOE Order 151.1B.

 

Office of Environment, Safety and Health Evaluations (OA-50)

 

EM approved the Corrective Action Plan (CAP) for the Hanford (PFP specific) safety management inspection on October 8, 2002.  OA has reviewed the plan and found that the CAP appropriately addressed all findings identified as a result of the subject inspection.

 

The OA-50 office director visited the Pantex site on November 4, 2002, where she participated in management meetings and toured various facilities.

 

Final preparations have been made for the upcoming AAAHC survey and consultative visits at Sandia National Laboratories-New Mexico and California and Brookhaven National Laboratory.

Back to Weekly Highlights