Weekly Highlights for September 16 - 20, 2002

 

Activities Underway

 

Office of Safeguards and Security Evaluations (OA-10)

 

OTS/AL Comprehensive Inspection:  The team in Albuquerque is scheduled to complete data collection & report writing this week. 

 

CMPC Special Reviews:  Comments on the Headquarters and SNL-NM draft reports have been received and will be considered in finalizing the reports.  The LLNL review data collection has been completed and the report writing is nearing completion. 

 

ANL-W Comprehensive Inspection:  Final preparations are underway for the planning meeting at ANL-W next week. 

 

The OA classified LAN server components have been installed and the final wiring connections are to be made as early as this week.  Development of the system security plan is complete, and work continues on test documentation. 

 

Office of Cyber Security Evaluations (OA-20)

 

OA-20 has initiated coordination activities with representatives in the DOE Office of Energy Assurance to support an assessment of cyber security vulnerabilities associated with infrastructure assets under the control of an electrical power utility.  This effort is intended to support the transfer cyber security investigation capabilities to the Office of Energy Assurance in support the Department’s efforts to protect critical energy infrastructure assets throughout the United States. 

 

OA-20 personnel have initiated activities to evaluate the Chicago Operations Office cyber security program.  A performance test agreement between OA and the Chicago Operations Office has been developed. 

 

OA-20 personnel have initiated a special study (Perimeter Scanning Project) to map and identify vulnerabilities in DOE computer networks exposed to potential attack from the Internet.  A project team has been formed.  Initial tasks include development of a project plan, creation of a database to store scanning data, and the identification of the scope of DOE computer networks through both internal and external sources.  The Office of the Chief Information Officer has reviewed a copy of the draft project plan.  Outreach activities to communicate the scope and objectives of the project will be initiated in the near future.

 

Office of Emergency Management Oversight (OA-30)

 

The Safety/Emergency Management Nevada Test Site Inspection data collection phase was completed this week.  The onsite validation/closeout visit is scheduled for October.

 

OA-30 and OA-50 continue to plan for the combined review at Pantex that is scheduled to begin on October 28.  Biweekly conference calls are occurring to coordinate the upcoming review. 

 

OA-30 and OA-50 are in the initial stages of planning for an evaluation of the Sandia National Laboratories, New Mexico.  The scoping visit is currently scheduled for October.

 

Office of Environment, Safety and Health Evaluations (OA-50)

 

OA-50 staff will revise the report that analyzes independent environmental protection program assessments that have been conducted at DOE facilities over the past several years.

 

Comments on the revised DOE Order 470.2B, “Independent Oversight and Performance Assurance Program” were received from the FMC.  Meetings and follow-up discussions are being conducted with various organizations to seek final resolution.

 

The Corrective Action Plan (CAP) for the Hanford (PFR specific) safety management inspection was disapproved by EM-1 in a memorandum dated August 19, 2002.  The CAP is to be revised and resubmitted within 30 days of the aforementioned memorandum.

 

A final corrective action plan for the ANL-East safety and emergency management inspection was due on August 27, 2002.

 

A final corrective action plan for the safety and emergency management inspection at LLNL has been requested. 

 

Nevada Test Site inspection activities continue with travel back to Germantown to begin report writing.

 

Coordination of the upcoming safety and emergency management inspection at the Pantex Plant continues.

 

A preliminary CAP for the WIPP safety and emergency management inspection has been received and is under review.

 

OA has requested an overall schedule of activities and copies of completed reports regarding the status of line actions taken to address the DNFSB concerns on the effectiveness of ISM for BJC activities at ORO.  Many of the documents have been received, but an overall schedule is yet to be provided.  A follow-up meeting will be scheduled upon receipt of all of the requested documents.

 

Planning discussions are being held with the Office of Kirtland Site Operations and Sandia National Laboratories in preparation for the October 2002 scoping visit.

 

Review of DOE Draft Order 460.1B, Transportation Safety is underway.  Comments are due by September 30, 2002.

 

Activities Completed

 

Office of Safeguards and Security Evaluations (OA-10)

 

OA-10 developed a white paper that discusses policy gaps that would clarify implementation of nuclear material control and accountability activities at DOE closure sites.  The paper is currently being reviewed with the Office of Environmental Management, who is responsible for closure of former nuclear weapons facilities, and the Office of Security, who is responsible for MC&A policy development.

 

Office of Cyber Security Evaluations (OA-20)

 

OA-20 personnel completed inspection of the Albuquerque Operations Office/Office of Transportation Safeguard cyber security program.  A draft report has been completed and transmitted to site managers for review.

 

Office of Environment, Safety and Health Evaluations (OA-50)

 

The Director OA-50 participated in the Best Practices Workshop at the Lawrence Berkley National Laboratory on September 17, 2002.

 

A staff member attended Groundwater Modeling Systems Training in Paducah, Kentucky on September 17-19, 2002.

Back to Weekly Highlights