Dear Franklin users,
Franklin quad core upgrade phase 2 is tentatively scheduled to start on
next Wednesday, August 13, at 7am PDT. The scheduled system maintenance
and dedicated IO testing are expected to finish at 9pm PDT. Franklin
will then be back in production with 3 columns of quad core nodes and 14
columns of dual core nodes.
5 columns of dual core nodes will be moved one week later to the test
environment for quad core upgrade and Franklin will be in production
with 3 columns of quad core nodes and 9 columns of dual core nodes.
Please refer to the detailed information along with the user environment
changes and usage guide for phase 2 at:
https://www.nersc.gov/nusers/systems/franklin/quadcore_upgrade.php#phase2
Best Regards,