Milestone Chart Example
A Gantt chart is an indispensable tool for scheduling and planning projects. Presented below is an example
"proposal" milestone chart that will be part of the Phase II proposal. As the Phase II project progresses, a milestone
chart based on the actual activities performed (including start and end dates) will be attached to each progress report.
(To obtain a Blank Milestone Chart, click on the link.) Upon completion of the Phase II project,
a completed "actual" milestone chart will be part of the Phase II Final Report.
The Gantt chart portion must show duration and timing of tasks. Indicate
a beginning and ending of each task by "^".
Gantt Chart
(X= 1 month effort)
Lower case x = 1/2 month effort |
Estimate
Duration for each Task |
Reporting Period
0-6 months |
Reporting Period
6-12 months |
Reporting Period
12-18 months |
Reporting Period
18-24 months |
Task 1: Optimize Optics Design |
6 months |
^XXXXXX^ |
Task 2: Design and Fabricate Modules |
10 months |
^XXXXXXXXXX^ |
Task 3: Confirm Detection Limits |
15 months |
^XXXXXXXXXXXXXXX^ |
Task 4: Demonstrate System Feasibility |
12 months |
^XXXXXXXXXXXX^ |
Task 5: Prepare Final Report |
6 months |
^XXXXXX^ |
Effort (person-
months) List Key by Name. Provide levels of effort in person-mths
including consultants and subawardees |
Estimate Total Months Effort for Entire Project |
Reporting Period 0-6 months
4/1 - 9/30 |
Reporting Period 6-12 months
10/1 - 3/30 |
Reporting Period 12-18 months
4/1 - 9/30 |
Reporting Period 18-24 months
10/1 - 3/30 |
Actual for the Entire Project |
Key Personnel |
|
|
|
|
|
|
John Doe, PI |
12 |
3 |
2 |
5 |
2 |
12 |
K. Jones |
8 |
3 |
2 |
2 |
2 |
8 |
S. Michaels |
2 |
0.5 |
1.5 |
0 |
0 |
2 |
Consultant |
|
|
|
|
|
|
J. Smith |
4 |
0.5 |
0.5 |
1.5 |
0.5 |
4 |
Subawards |
|
|
|
|
|
|
U of MD |
4 |
|
2 |
2 |
|
4 |
Expenditures Provide dollar amount for: Key Personnel Consultants
Subawardees Permanent Equipment
Other* (List by Name) |
Estimate Total Dollars Effort for Entire Project |
Reporting Period 0-6 months
4/1 - 9/30 |
Reporting Period 6-12 months
10/1 - 3/30 |
Reporting Period 12-18 months
4/1 - 9/30 |
Reporting Period 18-24 months
10/1 - 3/30 |
Actual for the Entire Project |
Key Personnel |
|
|
|
|
|
|
John Doe |
$110,000 |
$30,000 |
$20,000 |
$50,000 |
$10,000 |
$110,000 |
K. Jones |
$ 80,000 |
$20,000 |
$20,000 |
$20,000 |
$20,000 |
$ 80,000 |
S. Michaels |
$ 20,000 |
$ 5,000 |
$15,000 |
|
|
$ 20,000 |
Consultant |
|
|
|
|
|
|
J. Smith |
$ 30,000 |
|
$10,000 |
$15,000 |
$ 5,000 |
$ 30,000 |
Subawards |
|
|
|
|
|
|
U of MD |
$ 60,000 |
$10,000 |
$15,000 |
$15,000 |
$20,000 |
$ 60,000 |
Perm. Equip. |
|
|
|
|
|
|
R&D Testing |
$ 15,000 |
$ 7,500 |
$ 7,500 |
|
|
$ 15,000 |
Other* |
$ 20,000 |
|
$10,000 |
$ 5,000 |
$ 5,000 |
$ 20,000 |
|
|
|
|
|
|
|
TOTALS: |
$335,000 |
$ 65,000 |
$ 90,000 |
$ 95,000 |
$ 60,000 |
$335,000 |
*Other includes non-key personnel, indirect costs, materials, travel, etc.
|
|
|