1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008
|
|
REQUEST |
APPROVAL DATE |
CHANGE REQUEST TITLE |
M-34-98-01A |
01/06/1999 |
Negotiation/dispute settlement of Hanford Federal Facility Agreement and Consent Order (Agreement) commitments for the removal of spent nuclear fuel, debris, sludge, and water from the K East and K West Basins |
M-32-98-01 |
02/11/1999 |
219-S construction upgrade schedule revision (Interim Milestone M-32-02) |
M-16-98-05 |
03/23/1999 |
Revision to Remedial Action Milestones, 300-FF-1 Operable Unit |
M-16-99-01 |
06/14/1999 |
Extend completion date for M-16-08B for the 100-BC-1 and 100-BC-2 Operable Units |
M-32-99-03 |
06/17/1999 |
Revision to Target Date M-32-03-T06 to clarify that the associated project revision was rescoped |
M-24-99-01 |
06/18/1999 |
Establish Calendar Year 1999 interim milestone for TPA M-24-00K - RCRA Well installation |
M-15-99-02 |
07/14/1999 |
Modifications to the groundwater sampling and analysis for the 100-FR-3 Operable Unit Groundwater Sampling Project |
M-15-99-03 |
07/14/1999 |
Modifications to the groundwater sampling and analysis for the 100-BC-5 Operable Unit Groundwater Sampling Project |
M-32-99-01 |
07/15/1999 |
Delete Hanford Federal Facility Compliance Agreement and Consent Order (TPA) Interim Milestone M-32-08 and Target Date M-32-08-T01 |
M-15-99-01 |
08/02/1999 |
Establishment of PFP Tank 241-Z-361 sludge disposition milestones |
M-34-99-01A |
08/11/1999 |
Change completion date for Milestone M-34-14A, Complete K West Basin Cask Facility Modifications. NOTE: this is Revision A of the change control form and replaces the original Change Control Form M-34-99-01 |
M-89-99-01 |
08/18/1999 |
Complete closure of non-permitted mixed waste units in the 324 Building as described in the 324 Building REC/HLV Closure Plan, (DOE/RL-96-73). Due date for completion of closure activities may now be established as October 31, 2005, replacing the current TBD due date status of the Major Milestone M-89-00 |
M-81-98-01 |
08/24/1999 |
Agreements in regard to DOEs Fast Flux Test Facility (FFTF) for standby and transition activities. Placement of agreement FFTF transition milestones and targets in abeyance (M-81-00 SERIES). Modification of Agreement Milestone M-20-29A |
M-45-99-01 |
09/20/1999 |
Add Tri Party Agreement Interim Milestone M-45-03B |
M-92-98-01 |
10/02/1999 |
Agreements in regard to DOEs sodium facilities acquisition and disposition activities. Placement of Agreement M-92-09 and M-92-10 Interim Milestones in abeyance. Modification of Agreement M-92-10 Interim Milestone to delete reference to M-81-02-T01 Target |
M-41-99-01 |
10/14/1999 |
Deletion of uncompleted Milestones and target dates from the Department Of Energys High-Level Radioactive Waste Tank Interim Stabilization Program (M-41-00) and Interim Milestone M-40-07 from the scope of the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) |
M-13-99-01 |
10/25/1999 |
Modification of Interim Milestones M-13-23 and M-13-24 and establishment of new interim milestones to support 200 Area operable unit work plans |
M-26-99-01 |
10/26/1999 |
Extend Interim Milestone M-26-01J, Submittal of the 2000 LDR Report to July 31, 2000 |
M-45-99-02 |
11/10/1999 |
Interim stabilization of the 244-AR Vault. Deletion of obsolete Milestone and Target Dates M-32-06 and M-32-06-T01. Corresponding addition of new Tri Party Agreement Interim Milestones M-45-11 and M-45-11A |