SUMMARY OF 95-1 IMPLEMENTATION PLAN COMMITMENTS

Commitment 1:
Develop the system requirements for the depleted UF6 cylinder program
Deliverable:
Systems Requirements Document
Responsibility:
Lockheed Martin Energy Systems
Date:
November 30, 1995
Commitment 2:
Develop the actions necessary to meet the systems requirements
Deliverable:
Systems Engineering Management Plan
Responsibility:
Lockheed Martin Energy Systems
Date:
March 31, 1996
Commitment 3:
Identify the required development tasks, with subsequent completion schedules
Deliverable:
Engineering Development Plan
Responsibility:
Lockheed Martin Energy Systems
Date:
June 1, 1996
Commitment 4:
Define the plan for managing cylinders
Deliverable:
Depleted UF6 Cylinder Program Management Plan
Responsibility:
Lockheed Martin Energy Systems
Date:
July 31, 1996
Commitment 5:
An analysis showing the technical safety basis for the storage of depleted UF6.
Deliverable:
Draft Safety Analysis Reports
Responsibility:
Lockheed Martin Energy Systems
Date:
September 30, 1996
Deliverable:
Approved Safety Analysis Reports
Responsibility:
The Department of Energy, Office of Nuclear Energy, Science and Technology
Date:
March 30, 1997
Deliverable:
Final Safety Evaluation Reports with letter stating the Department's position on the adequacy of the cylinder safety basis
Responsibility:
The Department of Energy, Office of Nuclear Energy, Science and Technology
Date:
March 30, 1997