SUMMARY OF 95-1 IMPLEMENTATION PLAN COMMITMENTS
Commitment 1: | Develop the system requirements for the depleted UF6 cylinder program | |
Deliverable: | Systems Requirements Document | |
Responsibility: | Lockheed Martin Energy Systems | |
Date: | November 30, 1995 |
Commitment 2: | Develop the actions necessary to meet the systems requirements | |
Deliverable: | Systems Engineering Management Plan | |
Responsibility: | Lockheed Martin Energy Systems | |
Date: | March 31, 1996 |
Commitment 3: | Identify the required development tasks, with subsequent completion schedules | |
Deliverable: | Engineering Development Plan | |
Responsibility: | Lockheed Martin Energy Systems | |
Date: | June 1, 1996 |
Commitment 4: | Define the plan for managing cylinders | |
Deliverable: | Depleted UF6 Cylinder Program Management Plan | |
Responsibility: | Lockheed Martin Energy Systems | |
Date: | July 31, 1996 |
Commitment 5: | An analysis showing the technical safety basis for the storage of depleted UF6. | |
Deliverable: | Draft Safety Analysis Reports | |
Responsibility: | Lockheed Martin Energy Systems | |
Date: | September 30, 1996 |
Deliverable: | Approved Safety Analysis Reports | |
Responsibility: | The Department of Energy, Office of Nuclear Energy, Science and Technology | |
Date: | March 30, 1997 |
Deliverable: | Final Safety Evaluation Reports with letter stating the Department's position on the adequacy of the cylinder safety basis | |
Responsibility: | The Department of Energy, Office of Nuclear Energy, Science and Technology | |
Date: | March 30, 1997 |