National Security Environmental Programs Nevada Test Site Library About the Nevada Site Office Homepage
 
Horizontal line
FAQs/QUESTIONS
SUBJECT INDEX
SITEMAP
SEARCH
CONTACT US
ABOUT US
HELP
ACRONYMS
FOIA
PRIVACY ACT
WEBSITE POLICIES
HOMEPAGE
Text Banner Library Photo of Desert Scene
Home > Library > Publications > NTS 50th Anniversary Newsletter

Yucca Mountain Studies Authorized in 1976

Photo - Yucca Mountain on Sept. 25, 1985.In 1982, Congress passed the Nuclear Waste Policy Act (NWPA) to set national policy to help solve the issue of high-level nuclear waste disposal. Congress based this law on a concept that most scientists agreed was the best way to dispose of nuclear waste.

The NWPA made the U.S. Department of Energy (DOE) responsible for locating, building, and operating an underground geologic repository for the permanent disposal of high-level nuclear waste.

The quest for a geologic repository dates back to 1957 when the National Academy of Sciences recommended that the best means of protecting public health and safety, and the environment, would be to dispose of high-level waste deep underground in rock. Scientists evaluated many options, including burying it under the ocean floor, disposal under the polar ice sheets, and sending it into outer space.

The NWPA established a detailed schedule for site characterization. To pay for the program, Congress established the Nuclear Waste Fund. People who use power from nuclear plants pay into the fund for nuclear waste disposal through their utility bills.

In 1976, nearly 20 years after the first nuclear power plant went on-line, the government began collecting data on potential repository sites. The 1982 Act was based on what was learned during the earlier program.

In 1983, DOE selected nine locations in six states to consider for potential high-level radioactive waste storage sites.

All the sites were studied, and the findings were submitted to Congress. Based on the studies, President Reagan then approved three sites for comprehensive characterization: Hanford, Washington; Deaf Smith County, Texas; and Yucca Mountain, Nevada.

In December 1987, Congress amended the NWPA and directed DOE to study only Yucca Mountain. This congressional mandate, driven by budgetary concerns and the costs of studying three sites, was criticized by some Nevadans who felt the 1987 Amendments Act unfairly targeted the state to eventually receive the waste.

In the Amendments Act, Congress directed DOE to determine whether or not Yucca Mountain would be suitable for a potential repository. The Act specifies studies will stop immediately if Yucca Mountain is found unsuitable. If that were to happen, the site would be restored to its natural condition and DOE would seek new direction from Congress.

From 1976 to 1986 various site characterization studies were conducted. These included drilling boreholes to obtain information on the mountain's hydrology and earthquake faults.

In 1986, all surface-disturbing activities were stopped on the Yucca Mountain Project. The State of Nevada stated that Yucca Mountain work could not be done under standing NTS permits.

On July 8, 1991, project scientists resumed digging at Trench 14 in the Midway Valley in the southwestern area of the Nevada Test Site, after obtaining the required air quality permit from the State of Nevada. This was followed on March 3, 1992 by the insurance of a water permit, which allowed water to be pumped for dust control.

On June 29, 1992, an earthquake below Little Skull Mountain registered 5.6 on the Richter Scale. Because it was only 12 miles from Yucca Mountain, the earthquake revived concerns about the site.

Scientists have found that information from the quake is invaluable in helping them understand ground motion that may occur with future quakes. This will provide clues to the suitability of the mountain.

In November 1992, work began on the Exploratory Studies Facility (ESF). The ESF will be a technically designed underground laboratory consisting of a 14-mile loop of tunnels on two levels with a north entrance ramp, a main cross tunnel, and a south exit ramp. Alcoves will house individual laboratory and test facilities 1,000 feet below the mountain ridge.

Once the studies are completed (target date is 2001) the findings will be submitted to the Secretary of Energy, who will then recommend appropriate action to the President. If the site receives Presidential approval, DOE will seek a license from the Nuclear Regulatory Commission to begin construction. The state of Nevada will have an opportunity to submit a "notice of disapproval" (veto) after the Presidential decision. Work could only continue if a majority vote in Congress overturned the State's veto.

^ TOP ^


Print Icon PRINT PAGE  |  Email Icon EMAIL PAGE

Date Last Modified: November 25, 2008