Skip to content.Skip to side navigation. Quick Navigation: Skip to content.Skip to side navigation.
GPO Access Home Page.
Jump to selected topic.
Navigation Bar
About.Help. A-Z Resource List. Locate a Federal Depository Library. Buy Publications. Legislative. Executive. Judicial.
National Archives and Records Administration logo.
Database Features.
Browse
Simple Search
Advanced Search
* Boolean
  * Proximity
Search History
Search Tips
Corrections

Latest Updates

User Info
FAQs
Agency List
e-CFR Main Page
Related Resources
Code of Federal Regulations
Federal Register
List of CFR
Sections Affected
Regulations.gov
Unified Agenda
All NARA Publications
About Government.
Ben's Guide Logo.
Get Adobe Reader

blue pill
e-CFR Data is current as of January 14, 2009


Title 7: Agriculture
PART 1726—ELECTRIC SYSTEM CONSTRUCTION POLICIES AND PROCEDURES
Subpart B—Distribution Facilities

Browse Previous | Browse Next

§ 1726.51   Distribution line construction.

(a) Contract forms. The borrower must use RUS Form 790, or 830, as outlined in this paragraph (a), for distribution line construction, except for minor modifications or improvements.

(1) The borrower may use RUS Form 790, Electric System Construction Contract—Non-Site Specific Construction, under the following circumstances:

(i) For contracts for which the borrower supplies all materials and equipment; or

(ii) For non-site specific construction contracts accounted for under the work order procedure; or

(iii) If neither paragraph (a)(1)(i) or (a)(1)(ii) of this section are applicable, the borrower may use RUS Form 790 for contracts, up to a cumulative total of $250,000 or one percent of net utility plant (NUP), whichever is greater, per calendar year of distribution line construction, exclusive of the cost of owner furnished materials and equipment.

(2) The borrower must use RUS Form 830, Electric System Construction Contract—Project Construction, for all other distribution line construction.

(b) Procurement procedures. (1) It is the responsibility of each borrower to determine the procurement method that best meets its needs to award contracts in amounts of up to a cumulative total of $250,000 or one percent of NUP, whichever is greater, per calendar year of distribution line construction (including minor modifications or improvements), exclusive of the cost of owner furnished materials and equipment.

(2) In addition to the cumulative total stipulated in paragraph (b)(1) of this section, a borrower may use Multiparty Unit Price Quotations to award contracts in amounts of up to a cumulative total of $350,000 or 1.5 percent of NUP, whichever is greater, per calendar year of distribution line construction (including minor modifications or improvements), exclusive of the cost of owner furnished materials and equipment.

(3) The borrower shall use formal competitive bidding for all other distribution line contract construction. The amount of contracts bid using the formal competitive bidding procedure do not apply to the cumulative total stipulated in paragraph (b)(1) of this section.

(4) An amendment which increases the scope of the contract by adding a project is not considered competitively bid, therefore, the amount of that amendment does apply to the cumulative total stipulated in paragraph (b)(1) of this section.

(c) Contract approval. Contracts for distribution line construction are not subject to RUS approval and need not be submitted to RUS unless specifically requested by RUS on a case by case basis.

[60 FR 10155, Feb. 23, 1995, as amended at 69 FR 7109, Feb. 13, 2004]

Browse Previous | Browse Next