Skip to content.Skip to side navigation. Quick Navigation: Skip to content.Skip to side navigation.
GPO Access Home Page.
Jump to selected topic.
Navigation Bar
About.Help. A-Z Resource List. Locate a Federal Depository Library. Buy Publications. Legislative. Executive. Judicial.
National Archives and Records Administration logo.
Database Features.
Browse
Simple Search
Advanced Search
* Boolean
  * Proximity
Search History
Search Tips
Corrections

Latest Updates

User Info
FAQs
Agency List
e-CFR Main Page
Related Resources
Code of Federal Regulations
Federal Register
List of CFR
Sections Affected
Regulations.gov
Unified Agenda
All NARA Publications
About Government.
Ben's Guide Logo.
Get Adobe Reader

blue pill
e-CFR Data is current as of January 13, 2009


Title 7: Agriculture
PART 1730—ELECTRIC SYSTEM OPERATIONS AND MAINTENANCE
Subpart B—Operations and Maintenance Requirements

Browse Previous | Browse Next

§ 1730.28   Emergency Restoration Plan (ERP).

(a) Each borrower with an approved RUS electric program loan as of October 12, 2004 shall have a written ERP no later than January 12, 2006. The ERP should be developed by the borrower individually or in conjunction with other electric utilities (not all having to be RUS borrowers) through the borrower's unique knowledge of its system, prudent utility practices (which includes development of an ERP) and the borrower's completed VRA. If a joint electric utility ERP is developed, each RUS borrower shall prepare an addendum to meet the requirements of paragraphs (e), (f), and (g) of this section as it relates to its system.

(b) Each applicant that has submitted an application for an RUS electric program loan or grant prior to October 12, 2004, but whose application has not been approved by RUS by such date, shall have a written ERP in accordance with §1730.28(a).

(c) Each applicant that submits an application for an RUS electric program loan or grant between October 12, 2004 and January 12, 2006, shall have a written ERP in accordance with §1730.28(a).

(d) Each applicant that submits an application for an RUS electric program loan or grant on or after January 12, 2006 shall include with its application package a letter certification that such applicant has a written ERP.

(e) The ERP shall include:

(1) A list of key contact emergency telephone numbers (emergency agencies, borrower management and other key personnel, contractors and equipment suppliers, other utilities, and others that might need to be reached in an emergency);

(2) A list of key utility management and other personnel and identification of a chain of command and delegation of authority and responsibility during an emergency;

(3) Procedures for recovery from loss of power to the headquarters, key offices, and/or operation center facilities;

(4) A Business Continuity Section describing a plan to maintain or re-establish business operations following an event which disrupts business systems (computer, financial, and other business systems); and

(5) Other items, if any, identified by the borrower as essential for inclusion in the ERP.

(f) The ERP must be approved and signed by the borrower's Manager or Chief Executive Officer, and approved by the borrower's Board of Directors.

(g) Copies of the most recent approved ERP must be made readily available to key personnel at all times.

(h) The ERP shall be Exercised at least annually to ensure operability and employee familiarity. Completion of the first exercise of the ERP must occur on or before January 12, 2007.

(i) If modifications are made to an existing ERP:

(1) The modified ERP must be prepared in compliance with the provisions of paragraphs (e), (f), and (g) of this section; and

(2) Additional Exercises may be necessary to maintain employee operability and familiarity.

(j) Each borrower shall maintain records of such Exercises.

[69 FR 60541, Oct. 12, 2004]