DEFENSE NUCLEAR FACILITIES SAFETY BOARD
September 7, 1995
MEMORANDUM FOR: |
|
G. W. Cunningham, Technical Director |
|
|
|
COPIES: |
|
Board Members |
|
|
|
FROM: |
|
Randall Robinson |
|
|
|
SUBJECT: |
|
Report on Review of Solutions Stabilization at Rocky Flats |
- Purpose: This report documents the Defense Nuclear Facilities Safety Board's
(Board's) staff review of the Solutions Stabilization at the Rocky Flats Environmental
Technology Site (RFETS) by R. Kasdorf, R. Robinson, and J. Leary (OE) on August 22-24,
1995.
- Summary: Based on the findings of this review, the Board's staff feels that the
planned processing technology used for solution stabilization has low technical risk.
After planned upgrades are completed to Buildings 771 and 371, the facilities will be
adequate for processing. There is some concern that:
- the final step for stabilization of Plutonium (Pu) solutions will not
place the resulting solid in the desired stable condition (the plans call for calcination
at 500°C and interim storage in an undetermined container for later calcination at
1000°C at an undetermined date)
- the plans for stabilization of Pu solutions will not meet the
schedule recommended in Recommendation 94-1 without aggressive management attention
- the training of operators at Los Alamos National Laboratory (LANL) for the solution
stabilization program may not be adequate since there are differences
in procedures and equipment between the two facilities
- the authorization bases methodology is not in place to accomplish
the solutions stabilization.
- Background: Recommendation 94-1, Sub-Recommendation 5, states "That
preparation be expedited to process the containers of possible unstable residues at the
Rocky Flats Plant and to convert constituent plutonium to a form suitable for safe interim
storage." The current plans are to stabilize nearly 30,000 liters of solutions
contained in 172 tanks and associated piping in Buildings 371 and 771, and 4-liter plastic
bottles located in Buildings 371, 559, 771, 774, 777, and 779. The plan calls the use of
five processes diagramed in the Attachment and described
as follows:
- Oxalate Process in Building 771: This process will be used
on solutions containing >6 gPu/l, and on solutions containing >1.5 gPu/l and <6
gPu/l not blended. The oxalate precipitation process will eliminate 20.6% of the total
solutions volume.
- Bottle box cementation in Building 774: This process will
be used on solutions in bottles containing > 0.0245 gPu/l or < 6 gPu/l, eliminating
10.1% of the total solutions volume.
- Carrier precipitation in Building 774/374: This process
will be used on solutions in bottles containing less than 0.0245 gPu/l, eliminating 6.1%
of the total solutions volume. Carrier precipitation in Building 774 will also process
filtrates from the oxalate precipitation and hydroxide precipitation from Building 771.
The process is two stage: accepting solutions < 0.0245 g/l actinides for the first
stage and <0.001 g/l actinide for the second stage. The underflow from this process
will be stored as a sludge for an indefinite period in tanks in Building 774 until a yet
undefined process is available. Filtrate from this process and the Caustic Waste Treatment
System (CWTS) in Building 371 will be transferred to the carrier precipitation process in
Building 374 for removal of trace quantities of actinides. The carrier precipitation
process in Building 374 accepts solutions from Building 371 having <0.004g/l actinides,
and from all other locations a concentration <0.001 g/l actinides. Building 374 carrier
precipitation process is essentially the same as that in Building 774, except that it is
single staged. The underflow from the carrier precipitation will be stored as a sludge for
an indefinite period in tanks in Building 374 until a yet undefined process is available.
The filtrate from the carrier precipitation for Building 374 are transferred to an
evaporator where the overheads and underflow are converted to process water and low-level
waste (saltcrete), respectively.
- CWTS in Building 371: This process will be used on all
tanks and piping solutions containing Pu in Building 371, eliminating 62.3% of the total
solutions volume.
- Hydroxide precipitation in Building 771: This process will
be used to process solutions containing uranium and Pu at concentrations > 6 g
Actinide/l, solutions containing >1.5 g Actinide/l but <6 g Actinide/l not used for
dilution, and solutions containing >1 g/l chloride. This small process will eliminate
1% of total solutions volume.
- Discussion/Observations:
- Processing in Building 371: A total of 18,705 liters of
solution from tanks and piping in Building 371 will be processed in the CWTS. The process
entails transferring solutions to a holding tank where it is adjusted to <6 gPu/liter,
if necessary, transfers to one of two 25-liter glass tanks, and struck with Mg(OH)2
to precipitate Pu and impurities as hydroxides. The mixture is digested and filtered. The
solids are transferred to a container on a hot plate where they are heated to 500°C. The
solids are later transferred to the stacker/retriever storage until it can be calcined at
high temperatures in Building 707 or Building 371. After it is confirmed that the filtrate
is sufficiently low in actinides, it will be transferred to Building 374 holding tanks
where it will be processed by the carrier precipitation. There is currently no process for
treatment of the sludges from carrier precipitation and they may be stored for years in
that state waiting for processing.
The CWTS process is straightforward and mature. No serious operating difficulties are
expected to be encountered. However, the Board's staff is concerned that the final solid
product will not be characterized (e.g. water content). Without characterization, safe
interim storage is not assured.
Although the official schedules meet the commitments in Recommendation 94-1, the Board's
staff feels that the schedule is optimistic because the facility is still under
construction, the requirements for the Building 371 Authorization Basis are not yet
defined, the delays in the past caused by problems with building equipment (e.g.
ventilation) will likely continue, and an Operational Readiness Review (ORR) will be
required.
- Processing in Building 771: The current plan is to process
most of the Pu solutions using the oxalate precipitation process. Sequentially, 1,246
liters of high level actinide tank solutions, followed by high level bottle solutions, low
volume tank solutions, and solutions from piping, will be processed. In the process,
solutions will be vacuum transferred to a precipitation vessel where the acidity is
adjusted with Mg(OH)2, the valence is adjusted to Pu(III) with a reducing
agent, and oxalic acid crystals will be added to precipitate the actinides. The
precipitate will be filtered, air dried, and heated to 500°C on a hot plate. The
resulting cake will be stored similar to the CWTS cake. The filtrate will be sampled and,
if within specification (<0.0245 gPu/l), transferred to Building 774 for carrier
precipitation. If out of specification, the process will be repeated until <0.0245
gPu/l is achieved in the filtrate that can be shipped to Building 774. A total of 4,816
liters of solutions from tanks bottles and piping will be processed through the oxalate
precipitation process with an additional 1,356 liters of solutions from piping classified
as "nonactinide."
Solutions containing >1 g/l chloride, U-Pu >6 g/l actinide, and U-Pu solutions in
the range 1.5 - 6.0 g/l actinide, not used for dilutions will be treated in the hydroxide
precipitation process. The hydroxide precipitation process is performed on a laboratory
scale in open 4-liter vessels in a glovebox. Mg(OH)2, is added to the solution
to precipitate the actinides from solution. The supernate will be decanted and the
resulting slurry will be filtered. The filter cake will be air dried and heated on a hot
plate at 500°C to convert the actinides to a meta- and diuranate and plutonium oxide for
interim storage. The filtrates from the hydroxide precipitation process will be bottled
and transported to Building 774 for bottle-box cementation.
All other solutions in Building 771 (<6 gPu/l, <6 g/l actinide, and <1 g/l
chloride), will be transported to Building 774 for bottle-box cementation.
The major milestones in the plans for Building 771 are: start tank draining in September
1995; and liquid stabilization complete by December 1997 (a commitment in Recommendation
94-1).
The process technology used to stabilize liquid solutions at RFETS is straightforward. No
serious problems would be encountered in operation. The operator training for these
processes will be performed at LANL where the equipment and procedures are not exactly the
same as at RFETS. The Board's staff is concerned that the differences in procedures and
equipment between the two sites may not provide the appropriate training. The training
received at LANL would only be interim while final training would be done using procedures
and equipment at RFETS. The Board's staff again is concerned that no characterization will
be made of the solids produced by the various processes before they are put into interim
storage. In view of the potential sources of delay (Authorization Basis, ORRs, etc.), the
Board's staff also feels that the schedules are optimistic.
- Building 886 HEUN Removal: The removal of Highly Enriched
Uranyl Nitrate (HEUN) from Building 886 is contingent on the selection of one of two
plans: bottling or blending. The blending option calls for isotopically diluting the HEUN
to a level that the HEUN can be shipped in special 3500 gallon tanker trucks to Nuclear
Fuel Services, Erwin, TN (NFS) for processing. The bottling option plans for direct
draining of HEUN into bottles that are approved for shipment. Three Single Source
Transport (SST) trucks have been identified as licensed by the Nuclear Regulatory
Commission (NRC) to carry HEUN over the highways. There are presently two types of
containers licensed to contain HEUN: a 1 liter bottle, and a 10-liter bottle, the L10,
owned by GE. The L10 containers are available, however the NRC license will expire in July
1996. Although General Electric Company (GE) is planning to try to relicense the L10
container, it is not certain whether the NRC will accept the renewal.
The advantage to blending is that bulk shipment can be made that will require
approximately 6-12 tankers at 3,500 gallons each over a period of two-five months. The
disadvantages to blending are: (1) the liquid cannot be shipped during winter months
because of the possibility of freezing; (2) the license for the tanker is up for renewal
and there is no assurance that it will be renewed; (3) there is some concern about the
tanker safety versus the SST; (4) more building preparation will be needed versus the
bottling option.
The advantages to the bottling option are: (1) simplicity of operation; (2) significant
reduction in Building readiness, maintenance, and Readiness Assessment; (3) if the L10s
can be used, the maximum shipment of 210 liters/truck (21 L10s) using three SSTs per
shipment (or 630 liters per shipment) requiring approximately three-four shipments. The
disadvantages to bottling are: (1) the schedule is dependent on the availability of the
SSTs; (2) if the 1-liter bottles are used only 42 liters/SST or 126 liters/convoy is
possible for a total shipment time of 50 weeks.
The decision between the two treatment options is expected in September 1995. The
milestones presented by the contractor were to remove HEUN from Building 886 by March 1997
(bottle option) or by October 1997 (blending option). These dates do not meet the
commitments in Recommendation 94-1.
The Board's staff felt that the bottling option applied a simpler approach with fewer
uncertainties and less risk than the blending option. A recent memorandum from the
Department of Energy to Kaiser-Hill at Rocky Flats took strong exception to the above
milestones and has strongly urged that Kaiser-Hill choose an option as soon as possible.
- Hydrogen Generation in Process Systems: All of the high
risk process tanks have been vented (tanks 993 and 550 were measured to contain about 50%
H2). Three-way valves have been added to ten tanks of concern in Building 771
to provide venting and gas purging of the tanks. Kaiser-Hill is currently evaluating
whether to periodically open the vents or to use a continuous low flow purge to keep the H2
sufficiently low. Four tanks in Building 371 have been opened to the exhaust ventilation
system, however, this will not actively vent the tanks. The concern now is the possibility
of H2in the closed piping systems containing some Pu solutions and with other
tanks that were predicted to have lower levels of H2 but still above the lower
flammability limit. Kaiser-Hill is committed to develop a comprehensive plan to address
all of the H2 issues in Buildings 771 and 371. Kaiser-Hill is communicating the
concern to the workers and has developed a remedial plan to eliminate sources of ignition.