DEPARTMENT OF DEFENSE

Defense Acquisition Regulations System

48 CFR Parts 204 and 252

RIN 0750-AF98


Defense Federal Acquisition Regulation Supplement; U.S.-
International Atomic Energy Agency Additional Protocol (DFARS Case
2004-D003)

AGENCY: Defense Acquisition Regulations System, Department of Defense
(DoD).

ACTION: Final rule.

-----------------------------------------------------------------------

SUMMARY: DoD has issued a final rule amending the Defense Federal
Acquisition Regulation Supplement (DFARS) to add a contract clause
requiring a contractor to notify DoD if the contractor is required to
report its activities under the U.S.-International Atomic Energy Agency
Additional Protocol. The clause will be included in contracts for
research and development or major defense acquisition programs
involving fissionable materials, other radiological source materials,
or technologies directly related to nuclear power production.

DATES: Effective Date: January 15, 2009.

FOR FURTHER INFORMATION CONTACT: Ms. Michele Peterson, Defense
Acquisition Regulations System, OUSD (AT&L)

[[Page 2412]]

DPAP (DARS), IMD 3D139, 3062 Defense Pentagon, Washington, DC 20301-
3062. Telephone 703-602-0311; facsimile 703-602-7887. Please cite DFARS
Case 2004-D003.

SUPPLEMENTARY INFORMATION:

A. Background

    Under the U.S.-International Atomic Energy Agency Additional
Protocol (U.S.-IAEA AP), the United States is required to declare a
wide range of public and private nuclear-related activities to the IAEA
and potentially provide access to IAEA inspectors for verification
purposes. The Department of Commerce issued a final rule at 73 FR 65120
on October 31, 2008, to implement the U.S.-IAEA AP.
    The U.S.-IAEA AP permits the United States unilaterally to declare
exclusions from inspection requirements for activities with direct
national security significance. This DFARS rule contains a contract
clause requiring a contractor to notify the applicable DoD program
manager if the contractor is required to report any of its activities
under the U.S.-IAEA AP. Upon such a notification, DoD will determine if
access may be granted to IAEA inspectors, or if a national security
exclusion should be applied.
    DoD published a proposed rule at 73 FR 48185 on August 18, 2008.
DoD received no comments on the proposed rule. DoD has adopted the
proposed rule as a final rule with minor changes to clarify the text
and to update references to a related DoD publication.
    This rule was not subject to Office of Management and Budget review
under Executive Order 12866, dated September 30, 1993.

B. Regulatory Flexibility Act

    DoD certifies that this final rule will not have a significant
economic impact on a substantial number of small entities within the
meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq.,
because the rule applies only to those DoD contractors involved in
certain nuclear-related activities. The rule provides for exceptions to
inspection requirements that might otherwise apply to such contractors,
if DoD determines that an exception is necessary in the interest of
national security.

C. Paperwork Reduction Act

    This final rule contains a new information collection requirement.
The Office of Management and Budget has approved the information
collection under Control Number 0704-0454.

List of Subjects in 48 CFR Parts 204 and 252

    Government procurement.

Michele P. Peterson,
Editor, Defense Acquisition Regulations System.

0
Therefore, 48 CFR parts 204 and 252 are amended as follows:
0
1. The authority citation for 48 CFR parts 204 and 252 continues to
read as follows:

    Authority: 41 U.S.C. 421 and 48 CFR Chapter 1.

PART 204--ADMINISTRATIVE MATTERS

0
2. Sections 204.470 through 204.470-3 are added to read as follows:


204.470  U.S.-International Atomic Energy Agency Additional Protocol.


204.470-1  General.

    Under the U.S.-International Atomic Energy Agency Additional
Protocol (U.S.-IAEA AP), the United States is required to declare a
wide range of public and private nuclear-related activities to the IAEA
and potentially provide access to IAEA inspectors for verification
purposes.


204.470-2  National security exclusion.

    (a) The U.S.-IAEA AP permits the United States unilaterally to
declare exclusions from inspection requirements for activities, or
locations or information associated with such activities, with direct
national security significance.
    (b) In order to ensure that all relevant activities are reviewed
for direct national security significance, both current and former
activities, and associated locations or information, are to be
considered for applicability for a national security exclusion.
    (c) If a DoD program manager receives notification from a
contractor that the contractor is required to report any of its
activities in accordance with the U.S.-IAEA AP, the program manager
will--
    (1) Conduct a security assessment to determine if, and by what
means, access may be granted to the IAEA; or
    (2) Provide written justification to the component or agency treaty
office for application of the national security exclusion at that
location to exclude access by the IAEA, in accordance with DoD
Instruction 2060.03, Application of the National Security Exclusion to
the Agreements Between the United States of America and the
International Atomic Energy Agency for the Application of Safeguards in
the United States of America.


204.470-3  Contract clause.

    Use the clause at 252.204-7010, Requirement for Contractor to
Notify DoD if the Contractor's Activities are Subject to Reporting
Under the U.S.-International Atomic Energy Agency Additional Protocol,
in solicitations and contracts for research and development or major
defense acquisition programs involving--
    (a) Any fissionable materials (e.g., uranium, plutonium, neptunium,
thorium, americium);
    (b) Other radiological source materials; or
    (c) Technologies directly related to nuclear power production,
including nuclear or radiological waste materials.

PART 252--SOLICITATION PROVISIONS AND CONTRACT CLAUSES

0
3. Section 252.204-7010 is added to read as follows:


252.204-7010  Requirement for Contractor to Notify DoD if the
Contractor's Activities are Subject to Reporting Under the U.S.-
International Atomic Energy Agency Additional Protocol.

    As prescribed in 204.470-3, use the following clause:
REQUIREMENT FOR CONTRACTOR TO NOTIFY DOD IF THE CONTRACTOR'S ACTIVITIES
ARE SUBJECT TO REPORTING UNDER THE U.S.-INTERNATIONAL ATOMIC ENERGY
AGENCY ADDITIONAL PROTOCOL (JAN 2009)
    (a) If the Contractor is required to report any of its
activities in accordance with Department of Commerce regulations (15
CFR part 781 et seq.) or Nuclear Regulatory Commission regulations
(10 CFR part 75) in order to implement the declarations required by
the U.S.-International Atomic Energy Agency Additional Protocol
(U.S.-IAEA AP), the Contractor shall--
    (1) Immediately provide written notification to the following
DoD Program Manager:
    [Contracting Officer to insert Program Manager's name, mailing
address, e-mail address, telephone number, and facsimile number];
    (2) Include in the notification--
    (i) Where DoD contract activities or information are located
relative to the activities or information to be declared to the
Department of Commerce or the Nuclear Regulatory Commission; and
    (ii) If or when any current or former DoD contract activities
and the activities to be declared to the Department of Commerce or
the Nuclear Regulatory Commission have been or will be co-located or
located near enough to one another to result in disclosure of the
DoD activities during an IAEA inspection or visit; and
    (3) Provide a copy of the notification to the Contracting
Officer.

[[Page 2413]]

    (b) After receipt of a notification submitted in accordance with
paragraph (a) of this clause, the DoD Program Manager will--
    (1) Conduct a security assessment to determine if and by what
means access may be granted to the IAEA; or
    (2) Provide written justification to the component or agency
treaty office for a national security exclusion, in accordance with
DoD Instruction 2060.03, Application of the National Security
Exclusion to the Agreements Between the United States of America and
the International Atomic Energy Agency for the Application of
Safeguards in the United States of America. DoD will notify the
Contractor if a national security exclusion is applied at the
Contractor's location to prohibit access by the IAEA.
    (c) If the DoD Program Manager determines that a security
assessment is required--
    (1) DoD will, at a minimum--
    (i) Notify the Contractor that DoD officials intend to conduct
an assessment of vulnerabilities to IAEA inspections or visits;
    (ii) Notify the Contractor of the time at which the assessment
will be conducted, at least 30 days prior to the assessment;
    (iii) Provide the Contractor with advance notice of the
credentials of the DoD officials who will conduct the assessment;
and
    (iv) To the maximum extent practicable, conduct the assessment
in a manner that does not impede or delay operations at the
Contractor's facility; and
    (2) The Contractor shall provide access to the site and shall
cooperate with DoD officials in the assessment of vulnerabilities to
IAEA inspections or visits.
    (d) Following a security assessment of the Contractor's
facility, DoD officials will notify the Contractor as to--
    (1) Whether the Contractor's facility has any vulnerabilities
where potentially declarable activities under the U.S.-IAEA AP are
taking place;
    (2) Whether additional security measures are needed; and
    (3) Whether DoD will apply a national security exclusion.
    (e) If DoD applies a national security exclusion, the Contractor
shall not grant access to IAEA inspectors.
    (f) If DoD does not apply a national security exclusion, the
Contractor shall apply managed access to prevent disclosure of
program activities, locations, or information in the U.S.
declaration.
    (g) The Contractor shall not delay submission of any reports
required by the Department of Commerce or the Nuclear Regulatory
Commission while awaiting a DoD response to a notification provided
in accordance with this clause.
    (h) The Contractor shall incorporate the substance of this
clause, including this paragraph (h), in all subcontracts that are
subject to the provisions of the U.S.-IAEA AP.