Frequently Asked Questions

Contractor Team Arrangements
  1. What is a GSA Schedule Contractor Team Arrangement (CTA)?
  2. What are the benefits of a GSA Schedule Contractor Team Arrangement (CTA)?
  3. How do GSA Schedule Contractor Team Arrangements (CTAs) differ from Prime Contractor/Subcontractor Arrangements under Schedule contracts?
  4. How can an ordering activity ensure that the responses it receives to its Request For Quotation (RFQ) are, in fact, Contractor Team Arrangements (CTAs) and not simply Prime Contractor/Subcontractor Arrangements under Schedule contracts?
  5. Where can I find information on other GSA Schedule contractors who may want to team?
  6. If my company has a Consolidated (formerly Corporate Contracts) Schedule contract or is on multiple GSA Schedules, can I team with myself?
  7. When should GSA Schedule Contractor Team Arrangements (CTAs) be set up?
  8. Who is responsible for crafting the GSA Schedule Contractor Team Arrangement (CTA)?
  9. Does GSA approve a GSA Schedule Contractor Team Arrangement (CTA)?
  10. Will GSA provide a sample GSA Schedule Contractor Team Arrangement (CTA) document?
  11. In a GSA Schedule Contractor Team Arrangement (CTA), who bills the customer?
  12. In a GSA Schedule Contractor Team Arrangement (CTA), who is responsible for reporting sales and remitting the Industrial Funding Fee (IFF)?
  13. How does the ordering activity know that all quoted items are on GSA Schedule?
  14. What happens in the event of a problem, such as warranty or performance issues?
  15. There is a cost involved for my company to participate in a GSA Schedule Contractor Team Arrangement (CTA). How do I recoup these costs under my GSA Schedule contract?
  16. My team member's unit prices or hourly rates are much higher than mine. Can I charge my team member's prices/rates instead of mine?
  17. To whom does the ordering activity communicate in a GSA Schedule Contractor Team Arrangement (CTA)?
  18. Can team members still use subcontractors, and if so, would the subcontractors be considered team members of the GSA Schedule Contractor Team Arrangement (CTA) if the subcontractors did not hold individual GSA Schedule contracts?
  19. Where can I obtain more information regarding Contractor Team Arrangements (CTAs)?
Contractor Team Arrangements
  1. What is a GSA Schedule Contractor Team Arrangement (CTA)?

    A GSA Schedule Contractor Team Arrangement (CTA) is an arrangement between two or more GSA Schedule contractors to work together to meet agency requirements. The CTA document is a written agreement between team members detailing the responsibilities of each team member. The CTA allows the contractor to meet the government agency needs by providing a total solution that combines the supplies and/or services from the team members' separate GSA Schedule contracts. It permits contractors to complement each other's capabilities to compete for orders for which they may not independently qualify. A customer benefits from a CTA by buying a solution rather than making separate buys from various contractors.

  2. What are the benefits of a GSA Schedule Contractor Team Arrangement (CTA)?


    • Satisfies the customer with a single solution;
    • Increases competitive edge;
    • Increases market share;
    • Increases visibility;
    • Focuses on core capabilities;
    • Obtains complementary capabilities;
    • Integrates different skills;
    • Offers additional opportunities with customers;
    • Builds direct relationships with customers;
    • Maximizes use of one or more GSA Schedule solutions;
    • Shares risks and rewards;
    • Allows more opportunities for small and small disadvantaged businesses; and
    • Reduces the number of items Schedule contractors need to carry on their Schedule contracts, thus reducing inventory and tracking costs.

  3. How do GSA Schedule Contractor Team Arrangements (CTAs) differ from Prime Contractor/Subcontractor Arrangements under Schedule contracts?

    In prime/sub arrangements, the relationship is very tightly defined and controlled by the prime contractor; whereas, in CTAs, the roles and responsibilities are defined by the team, as accepted by the government. The following chart summarizes key differences:
    Contractor Team Arrangement (CTA)Prime Contractor/Subcontractor Arrangement
    Each team member must have a GSA Schedule contract. Only the prime contractor must have a GSA Schedule contract.
    Each team member is responsible for duties addressed in the CTA document. The prime contractor cannot delegate responsibility for performance to subcontractors.
    Each team member has privity of contract with the government and can interact directly with the government. Only the prime contractor has privity of contract with the government and can interact with the government. The prime contractor is responsible for its subcontracting activities. (Ordering activities are encouraged to specify in the Request for Quotation (RFQ) that the use of subcontractors requires prior approval by the ordering activities.)
    The ordering activity is invoiced at each team member's unit prices or hourly rates as agreed in the task or delivery order or GSA Schedule BPA. The ordering activity is invoiced in accordance with the prime contractor's GSA Schedule contract, including any applicable price reductions.
    Total solutions, otherwise impossible under individual GSA Schedule contracts, can be put together quickly and easily. The prime contractor is limited to the supplies and/or services awarded on its GSA Schedule contract.

  4. How can an ordering activity ensure that the responses it receives to its Request For Quotation (RFQ) are, in fact, Contractor Team Arrangements (CTAs) and not simply Prime Contractor/Subcontractor Arrangements under Schedule contracts?

    GSA strongly recommends that an ordering activity's RFQ indicates that all CTAs must be specifically identified as such, and that the CTA document be submitted to the government as part of the quotation in response to the RFQ. Do not be confused, for example, by a "Team ABC" response; the response should clearly identify that the GSA Schedule contractors are proposing a "Contractor Team Arrangement." The CTA should designate all team members, their corresponding GSA Schedule contract numbers, and describe the tasks to be performed by each team member, along with the associated proposed prices (e.g., unit prices, labor categories, and hourly rates). If applicable, the team lead should also be identified, as should the individual team members responsible for delivery, warranty, and other issues. The ordering activity should then be able to verify that any proposed unit prices or hourly rates do not exceed the prices awarded under each team member's GSA Schedule contract and avoid any misunderstandings regarding each team member's responsibilities and prices.

  5. Where can I find information on other GSA Schedule contractors who may want to team?

    Please visit GSA eLibrary (formerly Schedules e-Library) to find GSA Schedule contractors who match the supply or service criteria.

  6. If my company has a Consolidated (formerly Corporate Contracts) Schedule contract or is on multiple GSA Schedules, can I team with myself?

    A contractor holding multiple GSA Schedule contracts may offer a solution that crosses those contracts. Such a solution would not be considered a Contractor Team Arrangement (CTA).

  7. When should GSA Schedule Contractor Team Arrangements (CTAs) be set up?

    GSA Schedule contractors may establish a CTA in advance of any known requirement or after requirements are defined and the Request for Quotation (RFQ) issued. Having an on-the-shelf team arrangement for non-complex buys will allow the contractors to respond quickly and easily when requirements emerge. For highly complex buys, a customized CTA may be required. In either case, the CTA should include the names of the team members, their respective GSA Schedule contract numbers, and a description of the responsibilities of each team member. Agencies should review CTAs to ensure that the CTAs clearly delineate team member responsibilities and provide for coordination and cooperation between team members, thus diminishing the risk for all parties involved.

  8. Who is responsible for crafting the GSA Schedule Contractor Team Arrangement (CTA)?

    GSA Schedule contractors are responsible for crafting the CTA document. The government is not involved in this process. When submitting a response to an RFQ, submitting the defined CTA document as part of the response is a best practice aiding both contractors and agency customers.

  9. Does GSA approve a GSA Schedule Contractor Team Arrangement (CTA)?

    No. The CTA is solely between the team members and cannot conflict with the underlying terms and conditions of each team member's GSA Schedule contract. As part of the review of quotations, however, ordering activities may identify deficiencies in the CTA in order to enhance the probability of successful performance.

  10. Will GSA provide a sample GSA Schedule Contractor Team Arrangement (CTA) document?

    No. CTA documents are developed by the team members themselves and will vary from one CTA document to another. While not all-inclusive, GSA has developed Elements of a Contractor Team Arrangement (CTA) Document, which identifies areas that are typically of interest to the government. GSA strongly encourages the submission of the CTA document in response to a Request for Quotation (RFQ) so that an ordering activity may gain an understanding of how the arrangement will work, and may identify any areas of responsibility that may require clarification.

  11. In a GSA Schedule Contractor Team Arrangement (CTA), who bills the customer?

    The CTA document should designate who is responsible for invoicing and payment. While the team lead may submit an invoice on behalf of all team members, GSA recommends that payment be made to each team member. GSA recognizes, however, that there may be instances where it is advantageous to craft the CTA document so that payment is made to the team lead who, in turn, pays each team member. Under such circumstances, the CTA document should clearly indicate that all team members agree to this payment arrangement. The CTA document should also acknowledge that any dispute involving the distribution of payment between the team lead and the team members will be resolved by the team members, without any involvement by the government.

  12. In a GSA Schedule Contractor Team Arrangement (CTA), who is responsible for reporting sales and remitting the Industrial Funding Fee (IFF)?

    Each GSA Schedule contractor is responsible for reporting its GSA Schedule contract sales and remitting the appropriate IFF.

  13. How does the ordering activity know that all quoted items are on GSA Schedule?

    In providing a total solution to an agency's requirement under a Contractor Team Arrangement (CTA), the supplies and services proposed should be identified under each team member's GSA Schedule contract. Any proposed supplies and services that are not part of a GSA Schedule contract (i.e., open market items) may be included only after all applicable acquisition regulations have been followed (see Federal Acquisition Regulation (FAR) 8.402(f)) and must be clearly labeled as such.

  14. What happens in the event of a problem, such as warranty or performance issues?

    Since each team member in a GSA Schedule Contractor Team Arrangement (CTA) has a GSA Schedule contract, each team member is held accountable under the terms and conditions of its contract for any problems such as warranty or performance issues. The CTA document should spell out which team member is responsible, at each phase of the project. When conducting past performance evaluations, the ordering activity contracting officer should evaluate each team member accordingly.

  15. There is a cost involved for my company to participate in a GSA Schedule Contractor Team Arrangement (CTA). How do I recoup these costs under my GSA Schedule contract?

    The CTA document should spell out any costs associated with the arrangement and how they will be allocated among team members. Each team member should consider such costs and compensate accordingly when the team develops its price quotation. The benefits of a CTA may more than compensate for a contractor's costs by expanding the firm's capabilities and broadening its customer base. Please keep in mind that each team member is governed by its own GSA Schedule contract, and that its price quotation cannot exceed the awarded unit prices or hourly rates under the GSA Schedule contract.

  16. My team member's unit prices or hourly rates are much higher than mine. Can I charge my team member's prices/rates instead of mine?

    No. Each team member's work should be priced in accordance with its own GSA Schedule contract.

  17. To whom does the ordering activity communicate in a GSA Schedule Contractor Team Arrangement (CTA)?

    Points of contact should be spelled out in the CTA document for the team lead and for each team member.

  18. Can team members still use subcontractors, and if so, would the subcontractors be considered team members of the GSA Schedule Contractor Team Arrangement (CTA) if the subcontractors did not hold individual GSA Schedule contracts?

    Team members may still use subcontractors as allowed by their GSA Schedule contracts and as may be addressed in the CTA. Those subcontractors, however, would not be considered members of the "team," and the responsibility for the subcontractors would rest with the applicable team member who employs them.

  19. Where can I obtain more information regarding Contractor Team Arrangements (CTAs)?

    To obtain a wealth of information on CTAs, visit the Center for Acquisition Excellence.

Back to Top