Memorandum: No. 101-M


May 16, 1996

MEMORANDUM FOR CORRESPONDENTS


(NOTE: The DoD Selected Acquisition Reports summarize the latest estimates of cost, schedule, and technical status. These reports are prepared annually for Congress in conjunction with the President's budget. Subsequent quarterly exception reports are required only for those programs experiencing unit cost increases of at least 15 percent or schedule delays of at least six months. Quarterly SARs are also submitted for initial reports, final reports, and for programs that are rebaselined/restructured.

Below is a SAR summary, summary narratives of significant SAR cost changes for this period and a SAR program acquisition cost summary. News media queries regarding overall SAR policy should be directed to Lt. Col. Joan Ferguson, Directorate for Defense Information, (703) 695-0192. For system specific questions, contact the appropriate Military Department Public Affairs office. BMDO contact is Maj. Monica Aloisio, Directorate for Defense Information, (703) 697-5131.)

The Department of Defense has released details on major defense acquisition program cost and schedule changes since the December 1995 reporting period. This information is based on the Selected Acquisition Reports (SARs) submitted to the Congress for the March 31, 1996, reporting period.

The total program cost estimates provided in the SARs include research and development, procurement, and military construction. Total program costs reflect actual costs to date as well as anticipated costs for future efforts. All estimates include allowances for anticipated inflation.

The current estimate of program acquisition costs for programs covered by SARs for the prior reporting period (December 1995) was $714,482.2 million. After subtracting the costs for terminated reports and adding the costs for new programs, the December 1995 adjusted current estimate of program acquisition costs was $699,440.8 million. There was a net increase of $2,367.3 million during the current reporting period (March 1996). The cost changes between December 1995 and March 1996 are summarized below:

                                           Current Estimate
                                              ($ in Millions)
     December 1995 (73 programs*)               $ 714,482.2
     Less four terminated reports (MLRS, JTUAV,   -23,925.5
     TRIDENT II SUB, and JTIDS)
     Plus one new program (ATIRCM/CMWS) and one new
     component of existing SAR (JSOW UNITARY VARIANT)+8,884.1
     December 1995 Adjusted (70 programs*)      $ 699,440.8
     Changes Since Last Report:
        Economic                                     $ -3.2
        Quantity                                        0.0
        Schedule                                     +563.6
        Engineering                                  +493.6
        Estimating                                   +546.0
        Other                                        +708.9
        Support                                       +58.4
                               Net Cost Change   $ +2,367.3
March 1996 (70 programs*)                        $701,808.1
*Excludes classified costs for the Air Force's MILSTAR program.

For the March 1996 reporting period, exception SARs were submitted for PATRIOT PAC-3 and THAAD to report revised total program cost estimates to the Congress. The December 1995 SARs for these programs did not include cost estimates beyond FY 2001.

DoD:

PATRIOT PAC-3 (PATRIOT Advanced Capability) -- Program costs increased $1,354.1 million (+23.0%) from $5,899.3 million to $7,253.4 million, due primarily to a revised estimate associated with restructure of missile procurement ($+519.2 million), restructure of the upgrade program to include Enhanced Launcher Electronics System and Fire Solution Computer ($+282.2 million), and modification of three battalions associated with radar integration deferred beyond FY 2001 ($+210.0 million); the inclusion of initial spares for Ballistic Missile Defense Organization (BMDO)-procured items ($+133.4 million); program adjustments due to lethality, targets and test requirements ($+115.2 million); and a revised annual procurement buy profile ($+92.4 million).

THAAD (Theater High Altitude Area Defense) -- Program costs increased $1,013.2 million (+20.5%) from $4,947.2 million to $5,960.4 million, due primarily to a revised estimate associated with a three-year extension of R&D (i.e., FY 2002-FY 2004) resulting from the BMDO Program Review restructure ($+948.1 million) and modification of lethality, target and Operational Test & Evaluation program requirements ($+67.2M).