Intelligent Transportation Systems Engineering
Fiber Optic Markout Requests
Field Markouts
If a review of the ITS Inventory database
reveals any Fiber Optic Cable or Conduit facilities, then field markouts
of the underground fiber optic network are required prior to doing
any work in the vicinity of those facilities. Markouts must be requested
a minimum of ten State Business Days prior to when the work is proposed
and must be submitted by fully completing the Markout Form. Submit
the Form to the respective office as specified below:
North:
work in the counties of Bergen, Essex, Hudson, Hunterdon, Middlesex, Morris,
Passaic, Somerset, Sussex, Union, and Warren
South: work in the
counties of Atlantic, Burlington, Camden, Cape May, Cumberland,
Gloucester, Mercer, Monmouth*, Ocean, and Salem (* except for markouts on Route 9 which will be completed by Traffic Operations North)
Adesta: for work along
the following sections of highways, in addition to submitting this form to the respective North
or South office, you must also notify the One-Call service at 1-800-272-1000:
Route 1 northbound MP 6.66 to 6.76,
Route 38, MP 0.5 to 9.5,
Route 42 MP 6.3 to 13.2, Route 70 MP 0.0 to 5.4,
I-80 MP 54.7 to 68.3,
I-95 (Mercer County) MP 1.56 to 8.77,
I-195 MP 0.06 to 6.25,
I-295 MP 40.6 to 67.55,
Mercer County Route 579 (Bear Tavern Road) MP 2.21 to 3.11,
Mercer County Route 634 (West Upper Ferry Road) MP 1.17 to 1.46,
Mercer County Route 634 (Parkway Avenue) MP 1.46 to 2.67,
and Intersection of Parkway Avenue (Mercer County Route 634) at
Lower Ferry Road into NJDOT headquarters.
Fiber Optic Markout
Request Form
An automatic response will be generated to the requestor when the
Form has been received and the requestor will be notified when the
markouts have been completed. The requestor is required to maintain
the markouts until their work is completed. For requests that exceed one mile in length provide for an additional two days time for each
additional mile of markout requested. Additional time may be required if the fiber is within the limits of an active construction
project to allow for coordination with the Resident Engineer and respective
contractor.
Designers are to use the as-built
plans in the development of projects and request markouts only
when test pits are being done in areas identified as a potential
conflict. Designers should note that relocation of fiber optic cables
may require a significant length of relocation to ensure proper connectivity.
Conduits
The ITS infrastructure inventory includes conduits that are labeled
for future fiber use. Markout
requests for these conduits may also be made to ensure these
are not adversely impacted by proposed work.
Other Infrastructures
Before performing any work within NJDOT Right-of-Way areas, please
contact
NJDOT about anti-icing systems, traffic counting devices, weather
stations, and weigh-in-motion systems.
|
|