News
April–June 2006
News Release: May 25, 2006 | ![]() |
Docket Number: P-2277 |
Commission seeks comment on Independent Panel Report
examining Taum Sauk Reservoir breach in Missouri
The Federal Energy Regulatory Commission today released for public
comment a report by an Independent Panel of Consultants on the
technical reasons for the December
14, 2005, breach of the Taum Sauk Pumped Storage Project upper
reservoir dam.
"This marks the completion of the first stage of our investigation.
Now that we have the facts before us, we will consider what further
action is required," Commission
Chairman Joseph T. Kelliher said.
The report cites the primary cause of the Taum Sauk breach as
overtopping of the upper reservoir dam due to improperly maintained
and installed water level monitors.
The report states that the monitors became loose and indicated
reservoir levels lower than actual levels.
In addition, the panel found, emergency backup sensors proved
ineffective because they "were set at an elevation above the lowest points
along the parapet wall; thus, they failed their protection role
because this enabled overtopping to occur before the
probes could trigger shutdown."
Another factor contributing to the overtopping was that AmerenUE
typically operated with high water levels of one foot below the
top of the parapet wall, which was
not enough to take into account possible mistakes in project
operation, the report said.
A secondary cause, the panel said, was the marginally
stable dumped "dirty" (silt,
sands and gravels) rockfill embankment and associated parapet
wall on top of the upper reservoir dam.
The independent panel was convened by the Commission's Director
of Dam Safety to establish an independent assessment of the technical
causes of the release of the
upper reservoir at the project. The investigation by the panel
included a review of the operation of the project and a forensic
evaluation of the breach.
The Commission will review the report's findings
to determine
their applicability to other pumped-storage projects under the
Commission's jurisdiction.
The Commission's dam safety staff conducted
an exhaustive forensic investigation of the breach, which is
detailed in a report released
April 28. On April 7, the licensee for
the project, AmerenUE, submitted a report prepared by an independent
consultant it retained under a directive from the Commission.
Both reports were forwarded to the
Independent Panel of Consultants for consideration in its preparation
of the report released today.
On December 14, 2005, the northwest corner of the Taum Sauk project's
upper reservoir breached at approximately 5:20 a.m. CST. Approximately
4,300 acre-feet of
stored water, or more than 1 billion gallons, flowed through
a state park and into the East Fork of the Black River, upstream
from the project's lower reservoir. An acre-foot is the
amount of water it would take to flood an acre of land one-foot
deep. The project is located near Lesterville, Missouri.
Immediately following the Taum Sauk breach of the upper reservoir,
the Commission initiated a review of all Commission-regulated
pump storage projects to
assure project safety and determine the need for, and development
of guidelines for the safe operation of pump storage projects.
This ongoing effort includes a review of the
effectiveness of the instrumentation and monitoring systems,
operating procedures, operator training programs, and Emergency
Action Plans. In addition, the Commission
requested each operator to conduct a fault-tree analysis of possible
failure mechanisms addressing the project structures, all instrumentation
and monitoring systems, backup
alarms and computer controls.
"The Commission's hydropower safety program is a model for the world. To
the extent this unfortunate event provides lessons we can apply
to the program, we will make
it even better," Chairman Kelliher said.
The public has 30 days to comment on the report. The entire report
is available on the Commission's website, www.ferc.gov.
Comments may be filed with the Commission at 888 First Street,
N.E., Washington, D.C. 20426. Comments should include the docket
number for the project, P-2277.
R-06-33
![]() |