JHT 2007-2009 Project Schedule
- Make preparations
for and begin real-time testing during 2007 hurricane season.
- Semi-annual
reports due 16 October 2007.
- Each PI make
presentation at IHC in March 2008, possibly meet with TPC/NHC points of
contact.
- Year-one annual
reports/Renewal proposals due 16 April 2008.
- Second year of
funded activity for renewed projects begins April 2008.
- Make preparations
for and continue real-time testing and evaluation during 2008 hurricane
season.
- Semi-annual
reports projects due 16 October 2008.
- Each PI make
presentation at IHC in March 2009, possibly meet with TPC/NHC points of
contact.
- Final reports due
for projects on 16 April 2009.
- Decision on operational implementation
of the all projects by the TPC Director in January 2010.
|