Decommissioning of Pacific OCS
Facilities
This NTL supersedes NTL No.
99-P05.
On May 17, 2002, the Minerals
Management Service (MMS) published a final rule on Decommissioning
Activities in the Federal Register (67 FR 35398), that took effect
on July 16, 2002. The rule includes requirements for
decommissioning platforms and pipelines, plugging wells, and
clearing lease sites. This NTL describes some of the requirements
and gives general guidelines regarding the permitting process for
decommissioning platforms, pipelines and other related oil and gas
facilities on the Pacific Outer Continental Shelf (OCS). It
provides advice and guidance to you (lessees/operators) on
procedures for coordinating with MMS and other affected parties.
Plugging of wells (covered by 30 CFR 250.1710 through 1723) and
site clearance (covered by 30 CFR 250.1740 through 1743) are not
discussed in this NTL.
In addition, we remind you
that, in accordance with 30 CFR 250.107(a), operators must protect
health, safety, and property, and the environment by (1)
performing all operations in a safe and workmanlike manner and (2)
maintaining all equipment in a safe condition. These
requirements remain in effect during decommissioning operations,
from the cessation of production through the actual removal
activities. During the time the platform is stacked,
equipment must be maintained in a safe condition. Questions
regarding the platform equipment safety requirements should be
directed to the District Supervisor.
Decommissioning
Requirements
Certain OCS platforms may be
approaching the end of their projected economic life, so you may
be in the early stages of developing applications for
decommissioning and removing such facilities. In developing
these applications you should refer to your Lease Agreements and
the Code of Federal Regulations (30 CFR Part 250, Subpart Q) for
specific requirements pertaining to Permanently Plugging Wells
(250.1710 through 1717), Removing Platforms and Other Facilities
(250.1725 through 1780), Site Clearance for Wells, Platforms, and
Other Facilities (250.1740 through1743), and Pipeline
Decommissioning (250.1750 through 1754).
You should also review lease
stipulations and approval conditions for your Development and
Production Plan and its modifications, including those placed on a
former lessee/operator for
which the current
lessee/operator is now responsible pursuant to MMS granting an
assignment of that lease.
We will conduct a detailed
technical and environmental review of proposed decommissioning
projects to ensure that you conduct operations in a safe and
environmentally sound manner. We will conduct this review in close
consultation with Federal, State, and local agencies and other
affected parties. The technical review will focus on engineering and
safety considerations and compliance with applicable regulations and
requirements. We will conduct the environmental review according to
Federal Regulations (40 CFR 1501.4 and 1506.6) and Departmental
procedures that implement the National Environmental Policy Act.
The MMS environmental review will also involve consultation (formal
or informal) with the National Marine Fisheries Service and U.S.
Fish and Wildlife Service pursuant to the requirements of the
Endangered Species Act, Marine Mammal Protection Act, and the
Sustainable Fisheries Act/Magnuson-Stevens Fishery Conservation and
Management Act.
Early Notification and
Coordination
We urge you to meet at the
earliest practicable time with us to discuss your plans for
decommissioning OCS oil and gas facilities. These meetings should
take place during the early conceptual design stages of the project,
before you submit the initial platform removal application, which is
due to the MMS at least 2 years before production is projected to
cease.
We also encourage you to
schedule early coordination meetings with Federal, State, and local
regulatory agencies and other affected parties to review preliminary
information outlining the conceptual framework and general timetable
for decommissioning facilities. The goal of these meetings is
to share information and promote open communication by all parties.
This approach will help identify permitting requirements and
timetables, information needs, environmental concerns, and other
issues that could have an important bearing on how you conduct
decommissioning operations. This approach will also provide an
opportunity for regulatory agencies to develop a more coordinated
and streamlined process for reviewing and approving projects.
Decommissioning
Applications and Timing
According to 30 CFR 250.1704,
the initial platform removal application is due to the MMS at least
2 years before production is projected to cease, and a final
platform removal application is due not more than 2 years after the
submittal of the initial platform removal application. As is
the case for other MMS requirements, applicants may propose
alternate timing, which will be considered by the MMS on a
case-by-case basis. These applications and the pipeline
decommissioning/removal application referenced below are to be
submitted to the Chief, Office of Facilities, Safety and
Enforcement.
According to 30 CFR 250.1725(a)
- (c), you must remove all platforms and other facilities within 1
year after the lease or pipeline right-of-way terminates, unless you
receive approval from the MMS to maintain the structure to conduct
other activities; you must submit a final removal application to the
MMS for approval; and you must remove a platform or other facility
according to the approved application.
The information to be included
in the initial and final platform removal applications is specified
at 30 CFR 250.1726 and 1727 and listed here in abbreviated form for
easy reference:
Initial Platform Removal
Application
a. Platform/facility removal
procedures, including the types of vessels and equipment you will
use;
b. Facilities (including
pipelines) you plan to remove or leave in place;
c. Platform/facility
transportation and disposal plans;
d. Plans to protect marine life
and the environment during decommissioning operations, including a
brief assessment of the environmental impacts of the decommissioning
operations and procedures and mitigation measures that will be taken
to minimize such impacts; and
e. Projected
decommissioning schedule and duration.
Final Platform Removal
Application
a. Identification of the
applicant…
b. Identification of the
structure…
c. Description of the structure…
d. Description, including anchor
pattern, of the vessel(s) you will use…
e. Identification of the purpose
[of the removal]…
f. Description of the removal
method…
g. Plans for transportation and
disposal (including as an artificial reef) or salvage…
h. If available, the results of
any recent biological surveys conducted in the vicinity of the
structure and recent observations of turtles or marine mammals at
the structure site.
i. Plans to protect
archaeological and sensitive biological features during removal
operations, including a brief assessment of the environmental
impacts of the removal operations and procedures and mitigation
measures you will take to minimize such impacts.
j. A statement whether or not
you will use divers to survey the area after removal to determine
any effects on marine life.
Pipeline
Decommissioning/Removal Application
Pipeline decommissioning/removal
requirements are at 30 CFR 250.1750 through 1754.
Decommissioning pipelines in place is covered by 30 CFR 250.1750
through 1751. Removal of pipelines is covered by 30 CFR
250.1752. The regulations specify that pipeline
decommissioning or removal applications must be submitted to the MMS
for approval before the proposed activity is performed, and
identifies the information to be included.
Environmental Considerations and Information
Sources
As specified above,
environmental information is required to be included in the initial
and final platform removal applications; such information is also
required for pipeline removal applications. Although
decommissioning of oil and gas facilities may have long-term
environmental benefits, the process of removing the facilities can
potentially cause short-term adverse impacts to water quality, air
quality, sensitive species (marine mammals) and habitats (hard
bottoms), commercial and recreational fishing, and other resources.
You should consider these impacts when formulating decommissioning
applications and develop effective measures to minimize such
impacts. The environmental documents prepared for Development
and Production Plans provide detailed information on environmental
concerns and mitigation measures. To date, Exxon’s Offshore
Storage and Treatment Vessel (OS&T) was the only oil and gas
facility decommissioned on the Pacific OCS. The environmental
document MMS prepared for the OS&T project provides a perspective on
environmental concerns and mitigation measures that Exxon adopted or
MMS and other regulatory agencies required. The comprehensive
mitigation program Chevron (now ChevronTexaco) developed for
removing Platforms Hope, Heidi, Hilda, and Hazel from State
Tidelands in the Santa Barbara Channel also provides a reference
point for other lessees/operators considering similar projects on
the OCS. Information regarding the Chevron project can
be obtained from the California State Lands Commission.
We look forward to working
closely with you on decommissioning and removing OCS oil and gas
facilities as the need arises. Again, we encourage you to
contact MMS at the earliest practicable time to discuss plans for
decommissioning facilities.
Paperwork Reduction Act of
1995 Statement:
The collection of information referred to in this
notice provides clarification, description, or interpretation of
requirements in 30 CFR 250, subparts B, J, and Q. The Office of
Management and Budget (OMB) approved the information collection
requirement in these regulations and assigned OMB control numbers
1010-0049, 1010-0050, and 1010-0142, respectively, for these
subparts. This notice does not impose additional information
collection requirements subject to the Paperwork Reduction of 1995.