The following VA FLITE Program updates/changes have occurred since the previous update of September 23, 2008:

Contracting Action Projected RFP Release Date Projected Award Date Award Date
PMOS 09/16/2008 02/27/2009  
SAM Hardware 06/03/2008   09/23/2008
SAM Database Licenses 09/19/2008 09/26/2008  
SAM Pilot Implementation 07/16/2008 02/26/2009  
IFAS Draft RFP 11/10/2008 N/A  
IFAS Implementation TBD 08/17/2009  
Data Warehouse TBD TBD  
IV&V TBD TBD  

 
  • Program Management Office Support (PMOS) Contracting Officer is Ms. Melissa Fauber.  Ms. Fauber can be reached at melissa.fauber@va.gov.
  • Integrated Financial and Accounting System (IFAS) contracting point of contact is Mr. Cory Price.  Mr. Price can be reached at cory.price@va.gov.
    1. IFAS Draft RFP is projected to be posted on FedBizOpps.
  • Strategic Asset Management (SAM) Contracting Officer is Ms. Mary Craig. Ms. Craig can be reached at mary.craig@va.gov.
    1. SAM Pilot Implementation is in source selection phase.

Return to top Return to top of page

As of September 23, 2008


The following VA FLITE Program updates/changes have occurred since the previous update of August 8, 2008:

Contracting Action Projected RFP Release Date Projected Award Date Award Date
PMOS 09/16/2008 01/20/2009  
SAM Hardware 06/03/2008   09/23/2008
SAM Database Licenses 09/19/2008 09/26/2008  
SAM Pilot Implementation 07/16/2008 02/26/2009  
IFAS Draft RFP 09/19/2008 N/A  
IFAS Implementation 11/17/2008 08/28/2009  
Data Warehouse TBD TBD  
IV&V TBD TBD  

 
  • Program Management Office Support (PMOS) Contracting Officer is Mr. Wayne Miller.  Mr. Miller can be reached at wayne.miller6@va.gov.
  • The public announcement for the A-76 Streamlined Competition for Department of Veterans Affairs solicitation, in accordance with Office of Management and Budget (OMB) Circular A-76 (Revised), dated May 29, 2003, was posted to FedBizOpps on September 16, 2008.

Return to top Return to top of page

As of August 8, 2008


The following VA FLITE Program updates/changes have occurred since the previous update of June 19, 2008:

  • SAM Pilot Implementation RFP released 7/18/2008 under the National Institutes of Health (NIH) Chief Information Officer – Solutions and Partners 2 Innovations (CIO-SP2i) GWAC.  For information regarding the NIH CIO-SP2i GWAC contact http://nitaac.nih.gov/ciosp2.asp. Opens in New Window
  • SAM Pre-Proposal Conference slides are attached for information purposes only. Adobe Acrobat File Opens in New Window (716kb)
  • Program Management Office Support (PMOS) Contracting Officer is Ms. Melissa Fauber.  Ms. Fauber can be reached at melissa.fauber@va.gov.
  • Data Warehouse – Anticipated solicitation release and award Fiscal Year (FY) 2010.
  • Data Warehouse – anticipated feeder systems other than IFAS and SAM is TBD.
  • Data Warehouse – acquisition strategy is TBD.
  • Data Warehouse – OCI Matrix  is updated and attached.  Note OCI for the Data Warehouse requirement is TBD. Microsoft Excel Document Opens in New Window (26.5kb)

Return to top Return to top of page

As of June 19, 2008


The following VA FLITE Program updates/changes have occurred since Industry Day (February 12, 2008):

  • Data Warehousing has been added as a major effort under FLITE Business Opportunities in addition to IFAS and SAM projects.  Acquisition strategy TBD.  Projected solicitation release and award date TBD.
  • The Program Management Office (PMO) support effort and the Organizational Change Management (OCM) effort have been combined into one acquisition at the Program level and will provide program, project and site level services working in coordination with IFAS and SAM implementation contractors.
  • The IFAS key dates have changed:
    • Projected RFP Release - Quarter 1 FY 2009
    • Projected Award – Quarter 4 FY 2009
  • SAM Pilot Implementation will be solicited under the National Institutes of Health (NIH) Chief Information Officer - Solutions and Partners 2 Innovations (CIO-SP2i) GWAC.
  • The number of Beta sites for SAM is now TBD.
  • SAM key dates have changed:
    • Projected RFP Release for Pilot Implementation – early Quarter 4 FY 2008
    • Projected Award – Quarter 1 FY 2009
  • SAM hardware key dates have changed:
    • RFQ released June 6, 2008 via NASA SEWP
    • Projected Award – August 2008
  • Program Management Office Support (PMOS)(the combined PMO and OCM efforts) dates have changed:
    • Projected RFP Release – Quarter 4 FY 2008
    • Projected Award – Quarter 1 FY 2009
  • IV&V acquisition key dates are TBD.