Hydrokinetic Pilot Project Licensing Procedures

Post-Filing Activity
  1. Applicant Files License Application (Including Revised Monitoring Plan), Applicant Prepared DBA, CZMA Application, and 401 Application (if needed) [15 days]

    • Commission Issues Acceptance & REA Notice; and Request for Interventions [30 days]
    • Commission Issues BA


  2. Agencies and Others File Recommendations, Conditions, and Comments on the Application [60 days]

  3. Commission Issues Single EA if FONSI [30 days]


  4. Agencies and Others Comment on EA; 10J Resolution


  5. Ready for Commission Decision