NIOSH Mining Safety Idea

Ideas to Reduce Work-Related Musculoskeletal Disorders


Cable Hanging


Old Way:Manually lifting cable up to the roof, and hanging it on along the rib using a hook or twist ties. The risk factors include frequent bending; heavy loads and static (prolonged) postures.
New Way:Use a skid that has the cable arranged in a "figure 8". As the skid is pulled forward, the cable travels over a pulley and is lifted to the desired height. The miner then secures the cable. This device eliminates bending the trunk and lifting of the cable, which are known risk factors that contribute to back injuries.

Lifting cable  Using a cable skid
Old Way New Way
Page last updated: 9/17/2008
Page last reviewed: 5/28/2008
Content Source: National Institute for Occupational Safety and Health (NIOSH) Mining Division