Final NITAAC Industry Council Meeting Minutes
Date:
December 20, 2001
Time: 11:30
a.m. – 1:30 p.m.
Attendees:
Names |
Contract |
Organization |
---|---|---|
Dr. Leamon Lee |
All |
NIH OA-NITAAC |
David Ramos |
All |
NIH-NITAAC |
Victor Powers |
All |
NIH-NITAAC |
Donald Wilson |
IW2 |
NIH-NITAAC |
June Evans |
BMOCO |
NIH-NITAAC |
Esther Burgess |
All |
IAC Chair-STG |
Jim Terry |
IW2 |
IAC-MTS Technologies, Inc. |
Kevin Razzaghi |
CIO-SP2 |
IAC- Booz, Allen & Hamilton |
Mary Hopewell |
CIO-SP2 |
IAC-Titan Systems Corp. |
Barry Oxford |
CIO-SP2 |
IAC-Premier Technologies |
Ed Treacy |
CIO-SP2 |
IAC-Northrop / Grumman |
Debbie Mays |
IW2 |
IAC-A-TEK |
Diane McLaughlin |
IW2 |
Ciber (PSI Net) |
Ajay Sagar |
IW2 |
Pixl, Inc. |
Louis Dorsey II |
ECS2 |
ECS Technologies, Inc. |
Stuart Kramer |
All |
NRC-SRA |
Polly Seleski |
All |
NRC-Eistream |
Jeffrey Westerhoff |
All |
NRC-SRA |
The meeting began with the administrative
items as follows:
The meeting then moved on to discuss the
council business as follows:
1. Dr. Leamon Lee updated the council
on the SBA 8(a) status stating that the SBA had sent documents to his office to
add two provisions to the contracts.
The first was the 51% work rule for the 8(a) contractor and the second
was required SBA contract boilerplate wording to be placed in all required
contracts. Additional discussions
continued to also include that no 8(a) set aside would be considered and that
there were still efforts underway to get 8(a) credits to be passed through the
prime, however, this would not be likely.
2. The council inquired if the past IAC minutes and IAC membership
rosters were posted on the NITAAC web site.
Mr. Tim Warrington joined the IAC meeting and gave an update that all
IAC information had been put up on the web site.
3. A contractor teaming arrangement discussion got underway to see how
contractors could move between primes for task orders. Contract language is being considered to
allow on a task order by task order basis when approved by the NITAAC COs and
primes.
4. The NITAAC End of Year Accomplishments and Award Ceremony (NEYAAC)
planning committee passed out their November 11th, 2002 meeting
minutes. Ms. Diane McLaughlin led the
status update and a spirited rounds of discussions began on how to run this
upcoming event. Several ceremony details still need to be worked out but much
work was accomplished during the NEYAAC‘s earlier planning sessions. Lessons learned from the first NITAAC
ceremony were reviewed and recommendations were made. The date of the NEYAAC
has still to be negotiated with consideration for room availability, other
events/meetings, calendar, scheduling of speakers, and awardees. Suggestions
for guest speakers should be forwarded to Ms. McLaughlin.
5. A review and update of the current prime contractor POC list was
requested. A follow-up IAC committee
Email responsibility call list would then be reviewed and updated.
6. The NITAAC Online Ordering System (NOOS) status was reviewed. A
reassessment of vendor software is underway and should be accomplished by the
first or second week of January 2002.
The implementation of the system should be accomplished within 120 days
after the vendor has approved.
7. The next NITAAC IAC Council
Meeting will be held January 17th, 2002 at 11:30 a.m. in Dr. Leamon
Lee’s briefing room.