Sec. 265.254  Design and operating requirements.

    The owner or operator of each new waste pile on which construction 
commences after January 29, 1992, each lateral expansion of a waste pile 
unit on which construction commences after July 29, 1992, and each such 
replacement of an existing waste pile unit that is to commence reuse 
after July 29, 1992 must install two or more liners and a leachate 
collection and removal system above and between such liners, and operate 
the leachate collection and removal systems, in accordance with Sec. 
264.251(c), unless exempted under Sec. 264.251(d), (e), or (f), of this 
chapter; and must comply with the procedures of Sec. 265.221(b). 
``Construction commences'' is as defined in Sec. 260.10 of this chapter 
under ``existing facility''.

[57 FR 3493, Jan. 29, 1992]