[Code of Federal Regulations]
[Title 2, Volume 1]
[Revised as of January 1, 2005]
From the U.S. Government Printing Office via GPO Access
[CITE: 2CFR215.62]

[Page 34-35]
 
                     TITLE 2--GRANTS AND AGREEMENTS
 
   CHAPTER II--OFFICE OF MANAGEMENT AND BUDGET CIRCULARS AND GUIDANCE
 
PART 215_UNIFORM ADMINISTRATIVE REQUIREMENTS FOR GRANTS AND AGREEMENTS WITH 
 
                    Subpart C_Post Award Requirements
 
Sec. 215.62  Enforcement.

    (a) Remedies for noncompliance. If a recipient materially fails to 
comply with the terms and conditions of an award, whether stated in a 
Federal statute, regulation, assurance, application, or notice of award, 
the Federal awarding agency may, in addition to imposing any of the 
special conditions outlined in Sec. 215.14, take one or more of the 
following actions, as appropriate in the circumstances.
    (1) Temporarily withhold cash payments pending correction of the 
deficiency by the recipient or more severe enforcement action by the 
Federal awarding agency.
    (2) Disallow (that is, deny both use of funds and any applicable 
matching credit for) all or part of the cost of the activity or action 
not in compliance.
    (3) Wholly or partly suspend or terminate the current award.
    (4) Withhold further awards for the project or program.
    (5) Take other remedies that may be legally available.
    (b) Hearings and appeals. In taking an enforcement action, the 
awarding agency shall provide the recipient an opportunity for hearing, 
appeal, or other administrative proceeding to which the recipient is 
entitled under any statute or regulation applicable to the action 
involved.
    (c) Effects of suspension and termination. Costs of a recipient 
resulting from obligations incurred by the recipient during a suspension 
or after

[[Page 35]]

termination of an award are not allowable unless the awarding agency 
expressly authorizes them in the notice of suspension or termination or 
subsequently. Other recipient costs during suspension or after 
termination which are necessary and not reasonably avoidable are 
allowable if paragraphs (c)(1) and (2) of this section apply.
    (1) The costs result from obligations which were properly incurred 
by the recipient before the effective date of suspension or termination, 
are not in anticipation of it, and in the case of a termination, are 
noncancellable.
    (2) The costs would be allowable if the award were not suspended or 
expired normally at the end of the funding period in which the 
termination takes effect.
    (d) Relationship to debarment and suspension. The enforcement 
remedies identified in this section, including suspension and 
termination, do not preclude a recipient from being subject to debarment 
and suspension under E.O.s 12549 and 12689 and the Federal awarding 
agency implementing regulations (see Sec. 215.13).