Sec. 215.51  Monitoring and reporting program performance.

    (a) Recipients are responsible for managing and monitoring each 
project, program, subaward, function or activity supported by the award. 
Recipients shall monitor subawards to ensure subrecipients have met the 
audit requirements as delineated in Sec. 215.26.
    (b) The Federal awarding agency shall prescribe the frequency with 
which the performance reports shall be submitted. Except as provided in 
Sec. 215.51(f), performance reports shall not be required more 
frequently than quarterly or, less frequently than annually. Annual 
reports shall be due 90 calendar days after the grant year; quarterly or 
semi-annual reports shall be due 30 days after the reporting period. The 
Federal awarding agency may require annual reports before the 
anniversary dates of multiple year awards in lieu of these requirements. 
The final performance reports are due 90 calendar days after the 
expiration or termination of the award.
    (c) If inappropriate, a final technical or performance report shall 
not be required after completion of the project.
    (d) When required, performance reports shall generally contain, for 
each award, brief information on each of the following.
    (1) A comparison of actual accomplishments with the goals and 
objectives established for the period, the findings of the investigator, 
or both. Whenever appropriate and the output of programs or projects can 
be readily quantified, such quantitative data should be related to cost 
data for computation of unit costs.
    (2) Reasons why established goals were not met, if appropriate.
    (3) Other pertinent information including, when appropriate, 
analysis and explanation of cost overruns or high unit costs.
    (e) Recipients shall not be required to submit more than the 
original and two copies of performance reports.
    (f) Recipients shall immediately notify the Federal awarding agency 
of developments that have a significant impact on the award-supported 
activities. Also, notification shall be given in the case of problems, 
delays, or adverse conditions which materially impair the ability to 
meet the objectives of the award. This notification shall include a 
statement of the action taken or contemplated, and any assistance needed 
to resolve the situation.
    (g) Federal awarding agencies may make site visits, as needed.
    (h) Federal awarding agencies shall comply with clearance 
requirements of

[[Page 32]]

5 CFR part 1320 when requesting performance data from recipients.