[Code of Federal Regulations]
[Title 34, Volume 3]
[Revised as of July 1, 2002]
From the U.S. Government Printing Office via GPO Access
[CITE: 34CFR413.34]

[Page 93]
 
                           TITLE 34--EDUCATION
 
  CHAPTER IV--OFFICE OF VOCATIONAL AND ADULT EDUCATION, DEPARTMENT OF 
                                EDUCATION
 
PART 413--NATIONAL CENTER OR CENTERS FOR RESEARCH IN VOCATIONAL EDUCATION--Table of Contents
 
         Subpart D--What Conditions Must Be Met After an Award?
 
Sec. 413.34  What activities must be performed during the final year of an award?

    During the fifth year of the award cycle, the National Center or 
Centers shall develop and remain prepared to implement a contingency 
plan for completing all substantive work by the end of the eleventh 
month of that year and transferring all projects, services, and 
activities to a successor during the twelfth month of that year.

(Approved by the Office of Management and Budget under Control No. 1830-
0013)

(Authority: 20 U.S.C. 2404)