    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Application: Preliminary Permit.
    b. Project No.: 12104-000.
    c. Date filed: August 2, 2001.
    d. Applicant: NatEl System US.
    e. Name of Project: W. D. Mayo Dam Project.
    f. Location: On the Arkansas River, in Sequoyah and LeFlore 
Counties, Oklahoma. Would utilize the U.S. Army Corps of Engineer's 
existing W. D. Mayo Dam Lock and Dam #14.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Mr. Gary F. Ricketts, 2760 76th Avenue SE., 
Suite 208, Mercer Island, WA 98040, (206) 275-0390.
    i. FERC Contact: Robert Bell, (202) 219-2806.
    j. Deadline for filing motions to intervene, protests and comments: 
60 days from the issuance date of this notice.
    All documents (original and eight copies) should be filed with: 
David P. Boergers, Secretary, Federal Energy Regulatory Commission, 888 
First Street, NE., Washington, D.C. 20426. Comments, protests and 
interventions may be filed electronically via the Internet in lieu of 
paper. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the 
Commission's web site under the ``e-Filing'' link.
    Please include the project number (P-12104-000) on any comments or 
motions filed.
    The Commission's Rules of Practice and Procedure require all 
interveners filing documents with the Commission to serve a copy of 
that document on each person in the official service list for the 
project. Further, if an intervener files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    k. Competing Application: Project No. 11932-000, Date Filed: March 
29, 2001, Date Notice Closed: August 8, 2001.
    l. Description of Project: The proposed project using the U.S. Army 
Corps of Engineer's W. D. Mayo Dam and impoundment would consist of: 
(1) A proposed powerhouse containing 7 generating units having a total 
installed capacity of 35 MW, (2) a proposed 2-mile-long, 25 kV 
transmission line, and (3) appurtenant facilities.
    The project would have an annual generation of 155 GWh that would 
be sold to a local utility.
    m. Copies of this filing are on file with the Commission and are 
available for public inspection. Copies of this filing are on file with 
the Commission and are available for public inspection. This filing may 
also be viewed on the

[[Page 53596]]

web at http://www.ferc.gov using the ``RIMS'' link, select ``Docket#'' 
and follow the instructions (call 202-208-2222 for assistance).
    n. Preliminary Permit--Public notice of the filing of the initial 
preliminary permit application, which has already been given, 
established the due date for filing competing preliminary permit 
applications or notices of intent. Any competing preliminary permit or 
development application or notice of intent to file a competing 
preliminary permit or development application must be filed in response 
to and in compliance with the public notice of the initial preliminary 
permit application. No competing applications or notices of intent to 
file competing applications may be filed in response to this notice. A 
competing license application must conform with 18 CFR 4.30 (b) and 
4.36.
    o. Proposed Scope of Studies under Permit--A preliminary permit, if 
issued, does not authorize construction. The term of the proposed 
preliminary permit would be 36 months. The work proposed under the 
preliminary permit would include economic analysis, preparation of 
preliminary engineering plans, and a study of environmental impacts. 
Based on the results of these studies, the Applicant would decide 
whether to proceed with the preparation of a development application to 
construct and operate the project.
    p. Comments, Protests, or Motions to Intervene--Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, 
385.211, 385.214. In determining the appropriate action to take, the 
Commission will consider all protests or other comments filed, but only 
those who file a motion to intervene in accordance with the 
Commission's Rules may become a party to the proceeding. Any comments, 
protests, or motions to intervene must be received on or before the 
specified comment date for the particular application.
    q. Filing and Service of Responsive Documents--Any filings must 
bear in all capital letters the title ``COMMENTS'', ``NOTICE OF INTENT 
TO FILE COMPETING APPLICATION'', ``COMPETING APPLICATION'', 
``PROTEST'', ``MOTION TO INTERVENE'', as applicable, and the Project 
Number of the particular application to which the filing refers. Any of 
the above-named documents must be filed by providing the original and 
the number of copies provided by the Commission's regulations to: The 
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., 
Washington, DC 20426. An additional copy must be sent to Director, 
Division of Project Review, Federal Energy Regulatory Commission, at 
the above-mentioned address. A copy of any notice of intent, competing 
application or motion to intervene must also be served upon each 
representative of the Applicant specified in the particular 
application.
    r. Agency Comments--Federal, state, and local agencies are invited 
to file comments on the described application. A copy of the 
application may be obtained by agencies directly from the Applicant. If 
an agency does not file comments within the time specified for filing 
comments, it will be presumed to have no comments. One copy of an 
agency's comments must also be sent to the Applicant's representatives.

David P. Boergers,