[Federal Register: January 16, 2001 (Volume 66, Number 10)]
[Rules and Regulations]               
[Page 3466]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr16ja01-8]                         

=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF TRANSPORTATION

Coast Guard

33 CFR Part 117

[CGD05-00-055]

 
Drawbridge Operation Regulations; Great Egg Harbor Bay, New 
Jersey

AGENCY: Coast Guard, DOT.

ACTION: Notice of temporary deviation from regulations.

-----------------------------------------------------------------------

SUMMARY: The Commander, Fifth Coast Guard District, has approved a 
temporary deviation from the regulations governing the operation of the 
Route 9/Beesleys Point Bridge across Great Egg Harbor Bay, mile 3.5, 
between Somers Point and Beesleys Point, in New Jersey. Beginning at 7 
a.m. on January 22, 2001, through 5 p.m. on March 22, 2001, the bridge 
may remain in the closed position. This closure is necessary to conduct 
the installation of a new deck.

DATES: This deviation is effective from 7 a.m. on January 22, 2001, 
until 5 p.m. on March 22, 2001.

FOR FURTHER INFORMATION CONTACT: Ann B. Deaton, Bridge Administrator, 
Fifth Coast Guard District, at (757) 398-6222.

SUPPLEMENTARY INFORMATION: The Coast Guard received a letter by fax 
from the contractor on December 1, 2000, requesting a temporary 
deviation from the current operating schedule of the Route 9/Beesleys 
Point Bridge. The draw currently is required to open on signal at all 
times. This requirement is included in the general operating 
regulations at 33 CFR 117.5. The contractor intends to install a new 
deck on the bascule span of the bridge. To facilitate the installation, 
the bascule span will be bolted down in the closed position so that the 
old deck can be removed and a new deck installed. This work requires 
completely immobilizing the operation of the bascule span. In the event 
of an emergency, openings of the span will be provided as quickly as 
possible, but may take up to 48 hours to accomplish. Requests for 
emergency openings can be made by calling the bridge manager at (609) 
390-3190 or (609) 624-0949.
    In accordance with 33 CFR 117.35, the District Commander approved 
the contractor's request for a temporary deviation from the governing 
regulations in a letter dated December 12, 2000.
    The Coast Guard has informed the known commercial users of the 
waterway of the bridge closure so that these vessels can arrange their 
transits to minimize any impact caused by the temporary deviation.
    The temporary deviation allows the Route 9/Beesleys Point Bridge 
across Great Egg Harbor, mile 3.5, between Somers Point and Beesleys 
Point, New Jersey to remain closed from 7 a.m. on January 22, 2001, 
until 5 p.m. on March 22, 2001.

    Dated: December 21, 2000.
John E. Skhor,
U.S. Coast Guard, Commander, Fifth Coast Guard District.
[FR Doc. 01-1212 Filed 1-12-01; 8:45 am]
BILLING CODE 4910-15-M