DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

 
Notice of Application for Amendment of License and Soliciting 
Comments, Motions to Intervene, and Protests

March 15, 2001.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Application Type: Amendment of License.
    b. Project No.: 2413-043.
    c. Date Filed: January 2, 2001.
    d. Applicant: Georgia Power Company.
    e. Name of Project: Wallace Dam.
    f. Location: The Wallace Dam Project is located on the Oconee River 
in Putnam, Hancock, Greene, Morgan, Oconee, and Oglethorpe Counties, 
Georgia. The project does not utilize federal or tribal lands.
    g.  Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r)
    h. Applicant's Contact: Mike Phillips, Georgia Power Company, 241 
Ralph McGill Boulevard NE, Atlanta, GA 30308-3374, (404) 506-2392.
    i. FERC Contact: Any questions on this notice should be addressed 
to Mr. Sean Murphy, e-mail address sean.murphy@ferc.fed.us, or 
telephone 202-219-2964.
    j. Deadline for filing comments, motions, to intervene and protest: 
30 days from the issuance date of this notice.
    All documents (original and eight copies) should be filed with: 
David P. Boergers, Secretary, Federal Energy Regulatory Commission, 888 
First Street, NE, Washington, DC 20426. Comments, protests and 
interventions may be filed electronically via the internet in lieu of 
paper. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the 
Commission's website at http://www.ferc.fed.us/efi/doorbell.htm.Please 
include the project number (P-2413-043) on any comments or motions 
filed.
    The Commission's Rules of Practice and Procedure require all 
interveners filing documents with the Commission to serve a copy of 
that document on the official service list for the project. Further, if 
an intervener files comments

[[Page 15857]]

or documents with the Commission relating to the merits of an issue 
that may affect the responsibilities of a particular resource agency, 
the intervener also must serve a copy of the document on that resource 
agency.
    k. Description of Amendment: Georgia Power Company, licensee for 
the Wallace Dam Project, requests Commission authorization to permit 
the City of Greensboro, GA, to increase the rate of water withdrawal at 
their intake facility from 3.8 cubic feet per second (cfs)\1\, 2.45 
million gallons per day (MGD), from Lake Oconee, to 3.3 MGC.
---------------------------------------------------------------------------

    \1\ FERC 25 para.62,058, Order Approving Change in Land Rights, 
issued July 29, 1980.
---------------------------------------------------------------------------

    l. Locations of the Application: A copy of the application is 
available for inspection and reproduction at the Commission's Public 
Reference room, located at 888 First Street NE, Room 2A, Washington, DC 
20426, or by calling (202) 208-1371. This filing may be viewed on 
http://www.ferc.fed.us/online/rims.htm (call (202) 208-2222 for 
assistance). A copy is also available for inspection and reproduction 
at the address in item h, above.
    m. Comments, Protests, or Motions to Intervene--Anyone may submit 
comments a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the subject application.
    n. Filing and Service of Responsive Documents--Any filings must 
bear in all capital letters the title ``COMMENTS'', ``RECOMMENDATIONS 
FOR THE TERMS AND CONDITIONS'', ``PROTEST'', OR ``MOTION TO 
INTERVENE'', as applicable, and the project name and number, ``Martin 
Dam Amendment of License, No. 349-070''. Any of the above-named 
documents must be filed by providing the original and the number of 
copies provided by the Commission's regulations to: The Secretary, 
Federal Energy Regulatory Commission, 888 First Street, NE, Washington, 
DC 20426. A copy of any motion to intervene must also be served upon 
the representative of the APC specified in item h, above.

David P. Boergers,
Secretary.
[FR Doc. 01-6958 Filed 3-20-01; 8:45 am]