DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

 
Notice of Application Accepted for Filing and Soliciting Motions 
To Intervene, Protests, and Comments

August 22, 2001.

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Application: Preliminary Permit.
    b. Project No.: 12097-000.
    c. Date filed: July 30, 2001.
    d. Applicant: Green River 3 Associates.
    e. Name of Project: Green River Dam 3.
    f. Location: On the Green River in Ohio County, Kentucky at the 
U.S. Army Corps of Engineers' Green River Lock and Dam 3. All lands of 
the proposed project are federal lands.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: David Brown Kinloch, Soft Energy Associates, 
414 S. Wenzel Street, Louisville, Kentucky 40204, (502) 589-0975.
    i. FERC Contact: Elizabeth Jones (202) 208-0246.
    j. Deadline for filing motions to intervene, protests, and 
comments: 60 days from the issuance date of this notice.
    All documents (original and eight copies) should be filed with: 
David P. Boergers, Secretary, Federal Energy Regulatory Commission, 888 
First Street, N.E. Washington, D.C. 20426. Comments, protests and 
interventions may be filed electronically via the Internet in lieu of 
paper. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the 
Commission's web site under the ``e-Filing'' link.
    Please include the Project Number (12097-000) on any comments, 
protests, or motions filed.
    The Commission's Rules of Practice and Procedure require all 
interveners filing a document with the Commission to serve a copy of 
that document on each person in the official service list for the 
project. Further, if an intervener files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    k. Description of the Project: The proposed project would place 
turbines in the existing lock chamber of the dam that was deactivated 
in 1981. The proposed project would consist of: (1) An existing 353-
foot-long, 23.5-foot-high timber crib and rock-filled dam; (2) an 
existing 137.5-foot-long, 35.8-foot-wide, lock chamber; (3) a proposed 
series of axial flow propeller turbines with a total installed capacity 
of 1.2 MW; (4) proposed three-phase line running approximately 500 feet 
across the river to connect with an existing three-phase distribution 
line; and (5) appurtenant facilities.
    The project would have an estimated annual generation of 4 GWH.
    l. Copies of this filing are on file with the Commission and are 
available for public inspection. Copies of this filing are on file with 
the Commission and are available for public inspection. This filing may 
also be viewed on the web at http://www.ferc.gov using the ``RIMS'' 
link, select ``Docket#'' and follow the instructions (call 202-208-2222 
for assistance). A copy is also available for inspection and 
reproduction at the address in item `h' above.
    m. Preliminary Permit--Anyone desiring to file a competing 
application for preliminary permit for a proposed project must submit 
the competing application itself, or a notice of intent to file such an 
application, to the Commission on or before the specified comment date 
for the particular application (see 18 CFR 4.36). Submission of a 
timely notice of intent allows an interested person to file the 
competing preliminary permit application no later than 30 days after 
the specified comment date for the particular application. A competing 
preliminary permit application must conform with 18 CFR 4.30(b) and 
4.36.
    n. Preliminary Permit--Any qualified development applicant desiring 
to file a competing development application must submit to the 
Commission, on or before a specified comment date for the particular 
application, either a competing development application or a notice of 
intent to file such an application. Submission of a timely notice of 
intent to file a development application allows an interested person to 
file the competing application no later than 120 days after the 
specified comment date for the particular application. A competing 
license application must conform with 18 CFR 4.30(b) and 4.36.
    o. Notice of Intent--A notice of intent must specify the exact 
name, business address, and telephone number of the prospective 
applicant, and must include an unequivocal statement of intent to 
submit, if such an application may be filed, either a preliminary 
permit application or a development application (specify which type of 
application). A notice of intent must be served on the applicant(s) 
named in this public notice.
    p. Proposed Scope of Studies under Permit--A preliminary permit, if 
issued, does not authorize construction. The term of the proposed 
preliminary permit would be 36 months. The work proposed under the 
preliminary permit would include economic analysis, preparation of 
preliminary engineering plans, and a study of environmental impacts. 
Based on the results of these studies, the Applicant would decide 
whether to proceed with the preparation of a development application to 
construct and operate the project.
    q. Comments, Protests, or Motions to Intervene--Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a

[[Page 45027]]

party to the proceeding. Any comments, protests, or motions to 
intervene must be received on or before the specified comment date for 
the particular application.
    r. Filing and Service of Responsive Documents--Any filings must 
bear in all capital letters the title ``COMMENTS'', ``NOTICE OF INTENT 
TO FILE COMPETING APPLICATION'', ``COMPETING APPLICATION'', 
``PROTEST'', ``MOTION TO INTERVENE'', as applicable, and the Project 
Number of the particular application to which the filing refers. Any of 
the above-named documents must be filed by providing the original and 
the number of copies provided by the Commission's regulations to: The 
Secretary, Federal Energy Regulatory Commission, 888 First Street, 
N.E., Washington, D.C. 20426. An additional copy must be sent to 
Director, Division of Hydropower Administration and Compliance, Federal 
Energy Regulatory Commission, at the above-mentioned address. A copy of 
any notice of intent, competing application or motion to intervene must 
also be served upon each representative of the Applicant specified in 
the particular application.
    Agency Comments--Federal, state, and local agencies are invited to 
file comments on the described application. A copy of the application 
may be obtained by agencies directly from the Applicant. If an agency 
does not file comments within the time specified for filing comments, 
it will be presumed to have no comments. One copy of an agency's 
comments must also be sent to the Applicant's representatives.

Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 01-21549 Filed 8-24-01; 8:45 am]